Interim Rept of Potentially Reportable Deficiency 179 Re Welding Program.Review & Evaluation of Welds Ongoing.Next Rept Will Be Submitted by 841130
ML20108A322
Person / Time
Site: Waterford Entergy icon.png
Issue date: 10/31/1984
From: Cook K
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
179, W3P84-2976, NUDOCS 8411140537
Download: ML20108A322 (1)


Text

,__ \

Louisiama f mo -o~oe E.7 0 .o .ex. coo 30WER & L1GHT / NEW CALEANS LoursuWA 7o1744000 9 (So4)3864345 MIDlLE SOUTH UtluilES SYSTEM October 31, 1984 W3P84-2976 Q-3-A35.07 3-A1.01.04 A4.05 Mr. John T. Collins '

Regional Administrator, Region IV U.S. Nuclear Regulatory Commission

] ))Qf7p" j 611 Ryan Plaza Drive, Suite 1000 g Arlington, Texas 76011 d NO\' -- l 19M

Dear Mr. Co.111ns:

Subject:

Waterford 3 SES Docket No. 50-382 POTENTIALLY REPORTABLE DEFICIENCY NO. 179 LP&L (Maintenance) Welding Program Deficiencies

. Extension of Report Schedule

Reference:

LP&L letter W3P84-2858 dated October 17, 1984 The referenced letter provided an interim report on the subject deficiency and related that the LP&L evaluation was expected to be completed by the end of October. Review and evaluation of the welds performed by the Maintenance Depart-ment is ongoing. The determination of the safety significance of PRD-179 is contingent on the results of the evaluation which is currently rescheduled for completion by November 30 at which time our report will be submitted pursuant to 10CFR50.55(e)(3).

Very truly yours, l K.W. Cook l Nuclear Support & Licensing Manager KWC:GEW:sms cc: NRC, Director, Office of I&E NRC, Director, Office of Management G.W. Knighton, NRC-NRR E.L. Blake W.M. Stevenson W.A. Cross INP0 Records Center (D.L. Gillispie)

O oh82 I 0

PDR 1

. /