MONTHYEARIR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 IR 05000302/20210012021-08-12012 August 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021001 and 05000302/2021002 IR 05000302/20200012020-11-19019 November 2020 NRC Inspection Report No. 05000302/2020001, Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, Crystal River, Florida ML20080P2952020-03-23023 March 2020 Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2020401 ML20050D0142020-02-19019 February 2020 NRC Independent Spent Fuel Storage Installation Inspection Report No. 07201035/2020001, Duke Energy Florida, LLC, Crystal River Unit 3, Crystal River, Florida IR 05000302/20190022019-11-20020 November 2019 NRC Inspection Report No. 05000302/2019002 and Independent Spent Fuel Storage Installation Inspection Report No. 07201035/2019002, Duke Energy Florida, LLC, Crystal River Unit 3, Crystal River, Florida IR 05000302/20190012019-05-0101 May 2019 NRC Inspection Report No. 05000302/2019001, Duke Energy Florida, LLC, Crystal River Unit 3, Crystal River, Florida IR 05000302/20180022018-08-16016 August 2018 NRC Inspection Report No. 05000302/2018002, Duke Energy Florida, LLC, Crystal River Unit 3, Crystal River, Florida ML18158A4792018-05-17017 May 2018 Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2018401 (Cover Letter Only) IR 05000302/20180012018-05-14014 May 2018 NRC Inspection Report No. 05000302/2018001, Duke Energy Florida, LLC, Crystal River Unit 3, Crystal River, Florida ML17341A7972017-12-0707 December 2017 NRC Inspection Report No. 07201035/2017002, Duke Energy Florida, Inc., Crystal River Unit 3, Crystal River, Florida IR 05000302/20170022017-10-26026 October 2017 NRC Inspection Report No. 05000302/2017002, Duke Energy Florida, LLC, Crystal River Unit 3, Crystal River, Florida IR 05000302/20170012017-07-13013 July 2017 NRC Inspection Report No. 05000302/2017001, Duke Energy Florida, Inc., Crystal River Unit 3, Crystal River, Florida IR 05000302/20174012017-04-18018 April 2017 ISFSI, Inspection Report 05000302/2017401 and 0720135/2017401, (Cover Letter Only) IR 05000302/20160032016-12-0606 December 2016 NRC Inspection Report 05000302/2016003, Duke Energy Florida, Inc., Crystal River Unit 3, Crystal River, Florida IR 05000302/20160022016-08-24024 August 2016 NRC Inspection Report No. 05000302/2016002, Duke Energy Florida, Inc., Crystal River Unit 3, Crystal River, Florida IR 05000302/20160012016-05-0202 May 2016 IR 05000302/2016001, Duke Energy Florida, Inc., Crystal River Nuclear Plant, Crystal River, Fl, Inspection Report, Public IR 05000302/20164012016-02-17017 February 2016 IR 05000302/2016401, Duke Energy Florida, Inc., Crystal River Nuclear Plant, Crystal River, Florida (Letter Only) IR 05000302/20154012015-11-0404 November 2015 IR 05000302/2015401, on 10/05-08/2015, Crystal River Nuclear Plant. Cover Letter IR 05000302/20150092015-10-21021 October 2015 Duke Energy Florida, Inc., Crystal River Unit 3, NRC Inspection Report 05000302/2015009 IR 05000302/20150082015-07-28028 July 2015 IR 05000302/2015008 on 5/4-7/2015, 6/22-25/2015 and 6/30/2015, Duke Energy Florida, Inc., Crystal River Unit 3, Crystal River, Fl IR 05000302/20150072015-04-13013 April 2015 IR 05000302-15-007 on 1/1/15 - 3/31/15, Duke Energy Florida, Inc., Crystal River Unit 3, Crystal River, Fl IR 05000302/20140042015-01-12012 January 2015 IR 05000302/2014004, Duke Energy Florida, Inc., Crystal River Unit 3, Crystal River, Florida IR 05000302/20144032014-12-0404 December 2014 IR 05000302-14-403, Duke Energy Florida, Inc. Crystal River Nuclear Plant, Crystal River, Florida(Pub) IR 05000302/20140032014-10-21021 October 2014 NRC Inspection Report No. 05000302/2014003, Duke Energy Florida, Inc., Crystal River Nuclear Plant, Crystal River, Florida IR 05000302/20140022014-07-16016 July 2014 IR 05000302-14-002 on 06/09-12/14, Crystal River Nuclear Plant, Unit 3 IR 05000302/20140012014-04-29029 April 2014 IR 05000302-14-001, on 02/11/14 - 03/31/14, Duke Energy Florida, Inc., Crystal River Nuclear Plant - Unit 3, NRC Inspection Report IR 05000302/20130082013-11-0606 November 2013 IR 05000302-13-008, on 9/30/13 - 10/3/13, Duke Energy Florida, Inc., Crystal River Nuclear Plant, Crystal River, Fl, Review of Operations, Management Oversight, Maintenance, CAP, Fire Protection and Plant Support Activities IR 05000302/20130032013-08-28028 August 2013 IR 05000302-13-003; 04/01/2013 - 07/31/2013; Crystal River Unit 3; In-Plant Airborne Radioactivity Control and Mitigation IR 05000302/20134042013-07-18018 July 2013 IR 05000302-13-404, on 06/07/13, Crystal River Nuclear Generating Plant, Unit 3 IR 05000302/20130022013-04-24024 April 2013 IR 05000302-13-002, on 01/01/2013-03/31/2013, Crystal River Unit 3, Routine Integrated Report IR 05000302/20120012013-03-0404 March 2013 Annual Assessment Letter for Crystal River Nuclear Plant Unit 3 (IR 05000302-12-001) IR 05000302/20120052013-01-28028 January 2013 IR 05000302-12-005; 10/01/2012 -12/31/2012; Crystal River Unit 3; Routine Integrated Report IR 05000302/20125022012-12-0707 December 2012 IR 05000302-12-502; 11/12/2012 - 11/16/2012; Crystal River Unit 3; Baseline Inspection IR 05000302/20124042012-10-30030 October 2012 Nuclear Generating Plant - U.S. Nuclear Regulatory Commission Security Inspection Report 05000302-12-404 IR 05000302/20120042012-10-24024 October 2012 IR 05000302-12-004, 07/01/2012 - 09/30/2012, Crystal River Unit 3; Routine Integrated Report IR 05000302/20124032012-08-17017 August 2012 IR 05000302-12-403, 7/26/2012, Crystal River Unit 3, Cover Letter IR 05000302/20120032012-07-27027 July 2012 IR 05000302-12-003, on 04/01/2012-06/30/2012, Crystal River Unit 3; Routine Integrated Report IR 05000302/20125032012-06-14014 June 2012 Supplemental IR 05000302-12-503, on 04/30/12 - 05/03/2012, Crystal River, Unit 3 IR 05000302/20110022012-04-19019 April 2012 IR 05000302-11-002, on 01/01/2012-03/31/2012, Crystal River Unit 3, Routine Integrated Report IR 05000302/20120072012-03-0808 March 2012 IR 05000302-12-007, January 17 - 23, 2012, and January 30 - February 2, 2012; Crystal River Unit 3; Biennial Inspection of the Problem Identification and Resolution Program ML1206501972012-03-0505 March 2012 Annual Assessment Letter for Crystal River Nuclear Plant Unit 3 2011007 IR 05000302/20115022012-03-0505 March 2012 Nuclear Generating Plant - NRC Emergency Preparedness Annual Inspection Report No. 05000302-11-502 2024-04-17
[Table view] Category:Letter
MONTHYEARML24179A0702024-07-26026 July 2024 Shpo S106 Completion Crystal River Unit 3 ML24205A2192024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Muscogee Nation ML24205A2182024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Nation of Oklahoma ML24179A0912024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Tribe of Florida ML24205A2202024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3_Miccosukee Tribe of Florida ML24190A1912024-07-0808 July 2024 Fws Concurrence for Crystal River Unit 3 ML24172A2552024-06-20020 June 2024 Fws to NRC Species List: Florida Ecological Services Field Office 06/20/2024 ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24114A2262024-04-24024 April 2024 Amended Special Package Authorization for the Cr3 Middle Package (Crystal River 3 Middle Package - Docket No. 71-9393) IR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 ML24054A0612024-04-0202 April 2024 Request to Initiate Section 106 Consultation Regarding the License Termination Plan for Crystal River Unit 3 in Citrus County, Florida ML24079A2472024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Cypress, Talbert ML24079A2492024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Johnson, Lewis Johnson ML24054A0582024-04-0202 April 2024 Achp S106 Initiation Crystal River Unit 3 - Letter 1 ML24079A2482024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Hill, David Hill ML24054A0812024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Osceola, Marcellus ML24089A0362024-03-29029 March 2024 Response to Audit Plan in Support of Accelerated Decommissioning Partners and Request to Add License Condition to Include License Termination Plan Requirements. W/Enclosures 1 to 5 ML24073A1922024-03-11011 March 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24054A6452024-02-29029 February 2024 Letter - Reply to Request for RAI Extension Related to the Crystal River License Termination Plan ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23342A0942024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commission'S Analysis of ADP CR3, Llc'S Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan ML21238A0952021-10-13013 October 2021 Issuance of Amendment No. 259 Approving the ISFSI-Only Emergency Plan, Revision Draft a IR 05000302/20210012021-08-12012 August 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021001 and 05000302/2021002 ML21182A1032021-07-0606 July 2021 Request for Additional Information (RAI) Related to the ISFSI-Only Emergency Plan 2024-07-08
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD.
KING OF PRUSSIA, PA 19406-2713 February 19, 2020 Terry Hobbs Decommissioning General Manager Duke Energy Florida, LLC Crystal River Unit 3 15760 W. Power Line Road Crystal River, FL 34428-6708
SUBJECT:
NRC INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT NO. 07201035/2020001, DUKE ENERGY FLORIDA, LLC, CRYSTAL RIVER UNIT 3, CRYSTAL RIVER, FLORIDA
Dear Mr. Hobbs:
On February 11 - 12, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an on-site inspection under Inspection Manual Chapter 2690, Inspection Program for Dry Storage of Spent Reactor Fuel at Independent Spent Fuel Storage Installations and for 10 CFR Part 71 Transportation Packagings. The inspector examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and the conditions of your license. The inspection consisted of observations by the inspector, interviews with personnel, and a review of procedures and records. The results of the inspection were discussed with you and other members of the CR-3 staff on February 12, 2020 and are described in the enclosed report. No findings of safety significance were identified.
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter, its enclosure(s), and your response, if any, will be made available electronically for public inspection in the NRC Public Document Room or from the NRC document system (ADAMS),
accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.
Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Radioactive Waste; Decommissioning of Nuclear Facilities; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday (except Federal holidays).
T. Hobbs 2 No reply to this letter is required. Please contact Katherine Warner, at 610-337-5389, if you have any questions regarding this matter.
Sincerely,
/RA/
Anthony Dimitriadis, Chief Decommissioning, ISFSI, and Reactor HP Branch Division of Nuclear Materials Safety Docket No. 07201035 License No. DPR-72
Enclosure:
Inspection Report 07201035/2020001 w/Attachment cc w/encl: Distribution via ListServ
T. Hobbs 3 NRC INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT NO.
07201035/2020001, DUKE ENERGY FLORIDA, LLC, CRYSTAL RIVER UNIT 3, CRYSTAL RIVER, FLORIDA DATED February 19, 2020.
DOCUMENT NAME: G:\WordDocs\Current\Insp Report\RDPR-72.2020001.docx SUNSI Review Complete: KWarner After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: C = Copy w/o attach/encl E =
Copy w/ attach/encl N = No copy ML20050D014 OFFICE DNMS/RI N DNMS/RI DNMS/RI NAME KWarner/kw ADimitriadis/ad DATE 2/19/20 2/19/20 OFFICIAL RECORD COPY
U.S. NUCLEAR REGULATORY COMMISSION REGION I INSPECTION REPORT Inspection No. 07201035/2020001 Docket No. 07201035 License No. DPR-72 Licensee: Duke Energy Florida, LLC (Duke Energy)
Facility: Crystal River Unit 3 (CR-3)
Location: 15760 W. Power Line Road Crystal River, FL 34428-6708 Inspection Dates: February 11 - 12, 2020 Inspector: Katherine Warner, Health Physicist Decommissioning, ISFSI, and Reactor HP Branch Division of Nuclear Materials Safety, Region 1 Approved By: Anthony Dimitriadis, Chief Decommissioning, ISFSI, and Reactor HP Branch Division of Nuclear Materials Safety, Region I
EXECUTIVE
SUMMARY
Duke Energy Crystal River Nuclear Plant NRC Inspection Report Nos. 07201035/2020001 An announced CR-3 on-site inspection was performed February 11 - 12, 2020. The inspector assessed whether CR-3 personnel were operating and maintaining the independent spent fuel storage installation (ISFSI) in conformance with the commitments and requirements contained in the Final Safety Analysis Report (FSAR), Safety Evaluation Report (SER), Certificate of Compliance (CoC), Technical Specifications (TS), Quality Assurance (QA) program, site procedures, and 10 Code of Federal Regulations (CFR) Part 72. The inspection consisted of observations by the inspector, interviews with site personnel, a review of procedures and records, and walk-downs. The NRC's program overseeing ISFSIs is described in Inspection Manual Chapter 2690, Inspection Program for Dry Storage of Spent Reactor Fuel at Independent Spent Fuel Storage Installations and for 10 CFR Part 71 Transportation Packages.
Based on the results of this inspection, no findings of safety significance were identified.
ii
REPORT DETAILS
1.0 Background
On February 20, 2013, Duke Energy sent a letter [Agency Documentation and Management System Accession Number ML13056A005] to the NRC certifying the permanent cessation of activities and certifying that the fuel had been permanently removed from the reactor. This met the requirements of 10 CFR 50.82(a)(1)(i) and 50.82(a)(1)(ii). CR-3 is currently in the SAFSTOR phase of decommissioning as described in IMC 2561. CR-3 completed offloading the spent fuel pool to the ISFSI on January 12, 2018. On June 14, 2019, the NRC received and is considering approval of a license transfer application [ML19170A209] and conforming amendment filed by the Duke Energy Florida (DEF), LLC on behalf of itself and Accelerated Decommissioning Partners (ADP) CR3, LLC. The application seeks NRC approval of the direct transfer of Facility Operating License No. DPR-72 for CR-3 and the general license for the CR-3 ISFSI from the current holder, DEF to ADP CR3, which is a wholly owned subsidiary of ADP, LLC.
2.0 Operation of an Independent Spent Fuel Storage Operation
- a. Inspection Scope [Inspection Procedure (IP) 60855]
ISFSI facilities where loading operations have been completed are essentially passive operating facilities. The inspector evaluated the licensees activities related to long-term operation and monitoring of their ISFSI. The inspector assessed whether CR-3 personnel were operating and maintaining the ISFSI in conformance with the commitments and requirements contained in the FSAR, SER, CoC, TS, QA program, CR-3 procedures, and 10 CFR Part 72.
The inspectors review was directed towards confirming the ongoing adequacy of the radiation protection, fire protection, emergency preparedness, surveillance, maintenance, environmental monitoring, training, QA, and corrective action programs as they relate to ISFSI monitoring activities.
The inspector observed activities, performed walk-downs interviewed personnel, and reviewed records and procedures. The inspector also reviewed a sample of changes screened and evaluated by Duke Energy under 10 CFR 72.48 to verify that they did not require prior NRC approval, that changes were consistent with the license or CoC, and that they did not reduce the effectiveness of any programs or processes.
- b. Observations and Findings The inspector determined that 10 CFR 72.48 screenings and evaluations had been properly performed and that Duke Energy had trained and qualified individuals to perform the evaluations. The inspector determined that changes under 10 CFR 72.48 did not require prior NRC approval.
1 Inspection Report No. 07201035/2020001
The inspector determined that issues associated with the ISFSI, including those from the recent emergency preparedness drill, had been identified and entered into the corrective action program in a timely manner and the issues were effectively screened, prioritized and evaluated commensurate with their safety significance. The inspector verified audits had been performed by qualified individuals independent of the organization being audited and that management reviewed the audits and associated corrective actions.
The inspector also reviewed CR-3s 10 CFR 72.212 evaluation report and ensured it was being appropriately updated.
Daily temperature monitoring of the horizontal storage modules was performed by CR-3 personnel in accordance with surveillance requirements in the TS. CR-3 procedures contain backup plans if the primary surveillance method was unavailable. The inspector performed a tour of the ISFSI pad and to assess its material and radiological conditions.
The inspector also verified that transient combustibles had not been stored on the ISFSI pad or in the vicinity of the HSMs and confirmed vehicle entry onto the ISFSI pad was controlled in accordance with site procedures 4.0 Exit Meeting Summary On, February 12, 2020, the inspector presented the inspection results to Mr. Terry Hobbs, Decommissioning General Manager, and the rest of the CR-3 staff. The inspector verified that no proprietary information was retained by the inspector or documented in this report.
2 Inspection Report No. 07201035/2020001
A-1 PARTIAL LIST OF PERSONS CONTACTED T. Hobbs, Decommissioning General Manager B. Akins, Manager, Radiation Protection and Chemistry I. Wilson, Manager Operations and Maintenance D. Bartlett, Radiation Protection Technician M. Garrison, Nuclear ISFSI Coordinator J. Lane, Lead Engineer G. McCallum, Nuclear ISFSI Coordinator C. Miller, Lead Engineer L. Reeder, Senior Scientist M. Van Sicklen, Licensing ITEMS OPEN, CLOSED, AND DISCUSSED None PARTIAL LIST OF DOCUMENTS REVIEWED Audits and Reports 2018-CR3-SEC/RP-01, Nuclear Oversight - Audit Crystal River 3 Physical Security and Radiological QA Programs 2019-CR3-CONS-01, Nuclear Oversight - Site Audit Plan Package, Revision 0 Crystal River Unit 3 - 2018 Annual Radiological Environmental Operating Report Crystal River Unit 3 - 2018 Annual Radioactive Effluent Release Report Condition Reports 02132853 02228817 02301070 02176942 02273189 02306099 02188507 02286701 Miscellaneous 19-02-0001, ISFSIY01, February 12, 2019 20-01-0003, ISFSI MoI Monthly Perimeter Survey, January 22, 2020 10 CFR 72.48 Screenings 02177598, 02178308, 02179671, 02209523, 02221197, 02251723 10 CFR 72.48 Evaluation: 02212624 DSG19-0015 SAFSTOR II CRC Meeting Minutes, Tuesday, October 29 EC 403904, Install Shielding at the ISFSI HSMs and OSSC-3, Revision 2 ISFS-510 Attachment 1 Supporting Information, 10 CFR 72 ISFSI Licensing Basis Document Change Evaluation and Implementation Attachment SF335 NLMS Assigned Jobs Activities Report for G. McCallum, February 11, 2020 Procedures EM-502, Attachment 3 Reactor Plant Event Notification Worksheet, Revision 7 EM-504, Conduct of the Radiation Protection Coordinator, Revision 3 ISFS-110, ISFSI Routine Monitoring, Revision 6 Attachment 1
A-2 Procedures (Contd)
ISFS-190, ISFSI Off-Normal Events, Revision 5 ISFS-212, ISFSI 10 CFR 72.212 Report, Revision 002 ISFS-330, ISFSI Temperature Monitoring System Calibration Check, Revision 3 Work Orders 20282561 20302150 LIST OF ACRONYMS USED ADP Accelerated Decommissioning Partners CAP Corrective Action Program CFR Code of Federal Regulations CoC Certificate of Compliance CR-3 Crystal River Unit 3 Duke Energy/DEF Duke Energy Florida, Inc.
FSAR Final Safety Analysis Report ISFSI Independent Spent Fuel Storage Installation NRC U.S. Nuclear Regulatory Commission QA Quality Assurance TS Technical Specification Attachment 2