Part 21 Report Regarding Potentially Unqualified Component in Certain Allen Bradley Timing RelaysML15134A016 |
Person / Time |
---|
Site: |
Millstone, Browns Ferry, Perry, Saint Lucie, Grand Gulf, North Anna, River Bend, Ginna, South Texas, Fort Calhoun |
---|
Issue date: |
05/01/2015 |
---|
From: |
Bolt T Nuclear Logistics |
---|
To: |
Document Control Desk, Office of Nuclear Reactor Regulation, NRC Region 4 |
---|
References |
---|
Download: ML15134A016 (7) |
|
|
---|
Category:Deficiency Correspondence (per 10CFR50.55e and Part 21)
MONTHYEARML24023A2802024-01-23023 January 2024 Final Report of a Deviation or Failure to Comply Associated with a Relay in the Reactor Core Isolation Cooling Condensate Pump ML22075A2192021-11-29029 November 2021 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10CFR21-0133, Rev. 0 - Swing Check Valve, P/N ESl50359 ML20296A2762020-10-0606 October 2020 Lake Engineering Co. - Third Interim Notification Per 10 CFR Part 21 - Degraded Snubber SF1154 Hydraulic Fluid Batch No. 17BLVS293 ML20049A0752020-02-11011 February 2020 C&D Technologies, Inc. -10 CFR Part 21 Evaluation Regarding Container Failure in KCR-07 Batteries ML19317D0932019-10-25025 October 2019 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10 CFR21-0127, Rev. 0, Emd Fuel Injectors - Seized Plunger and Bushing ML19080A0592019-03-0808 March 2019 Interim Report of Potential 10CFR Part 21, Eaton A200 Series Starters/Contactors ML19008A0432019-01-0404 January 2019 Third Interim Notification Per 10 CFR Part 21 Degraded Snubber SF1154 Hydraulic Fluid Batch No. 11KLVS146 ML19029A1552018-12-27027 December 2018 10 CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10CFR21-0123, Rev. 1 ML18353A4282018-11-30030 November 2018 Engine Systems, Inc., 10CFR21-0123, Rev. 0, for a 10CFR21 Reportable Condition on Emd Fuel and Soakback Pumps ML18302A2282018-10-19019 October 2018 Itt Enidine - USNRC 10CFR Part 21 Notification ML18159A0392018-06-0606 June 2018 National Technical Systems (Nts) - Potential Part 21 on Dedicated Items Not Available for Pmi Testing (NUPIC) ML18075A3552018-03-0606 March 2018 10 CFR Part 21 Notification of Defect on Crane Nuclear Figure Number 83 1/2 Spl 10x8x10 and 6x4x6 Bolted Bonnet Gate Valve ML17355A1392017-12-0505 December 2017 Potentially Degraded Snubber SF1154 Hydraulic Fluid Batch 14ELVS145 Final Report Per 10 CFR Part 21 ML17325B0222017-11-17017 November 2017 Fisher Controls International LLC Information Notice (FIN) 2017-05 ML17250A1572017-08-31031 August 2017 Commitments for Resolution of Anchor Darling Double Disc Gate Valve Part 21 Issues ML17228A0482017-08-14014 August 2017 Final 10 CFR Part 21.21 Report Re Defect of Manual Flow Controller Used at Fort Calhoun Nuclear Station ML17192A2652017-06-30030 June 2017 Areva Np, Inc. - Closure of Interim Report of an Evaluation of a Deviation Pursuant to 10 CFR 21.21(a)(2) ML17114A0692017-04-19019 April 2017 Part 21 Report - Control Rod Drive Mechanisms Contaminated with Chlorides ML17101A3662017-04-0606 April 2017 Part 21 Notification - Failure of Vishay Diodes ML17096A2692017-04-0303 April 2017 Part 21 Notification - Failure of Vishay Diodes ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML17006A0102016-12-29029 December 2016 Engine Systems, Inc. - Part 21 Issues Identified with the Enterprise Diesel Engine Subcover ML17006A0142016-12-13013 December 2016 Enercon - Part 21 - Notification-Design Basis Errors Using Flo-2D Software ML16342A9812016-11-23023 November 2016 Enercon - Part 21 Notification - Design Basis Errors Using FLO-2D Software ML16328A3102016-11-18018 November 2016 Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML16313A0622016-10-18018 October 2016 C&D Technologies, Inc. - 10 CFR Part 21 Evaluation Regarding Terminal Welding Failure in 3DCU-9 Batteries ML16252A2742016-08-29029 August 2016 Azz/Nli - Part 21 Report - Potential Allen Bradley Timing Relay ML15303A0142015-10-26026 October 2015 Part 21 Report Regarding Pressure Seal Valve Noncompliance, Per Millstone ML15243A1742015-08-25025 August 2015 Part 21 Furmanite Nuclear Grade Leak Seal Material FSC-N-1B ML15224A5432015-08-10010 August 2015 Part 21 Interim Report - Notification of Pressure Seal Valve Yoke Material Compliance ML15223B2662015-08-0707 August 2015 Part 21 Report - Crane Nuclear Pressure Seal Valve with Retaining Rings ML15201A2872015-07-0808 July 2015 Crane Nuclear, Inc. - Part 21 Interim Report - Notification of Pressure Seal Valve Yoke Material Compliance ML15188A0662015-06-25025 June 2015 Part 21 Report - Deviation in Nozzle Modeling Internal Reports ML15134A0162015-05-0101 May 2015 Part 21 Report Regarding Potentially Unqualified Component in Certain Allen Bradley Timing Relays ML15089A4362015-03-21021 March 2015 Part-21 Report - Valve Seat Leakage Defect ML14309A5292014-10-31031 October 2014 Closure of 10 CFR Part 21 Interim Report - Engine Systems, Inc., Emergency Diesel Generator Heat Exchanger CEY564L-HEX ML14318A1962014-09-0505 September 2014 CFR Part 21 Interim Report - Engine Systems, Inc. - Emergency Diesel Generator Heat Exchanger CEY564L-HEX ML14216A3772014-07-30030 July 2014 Part 21 Report - Incorrect Industrial Irradiator Dose ML14204A7072014-07-23023 July 2014 Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Unseating of Valve Spring on SSPV ML14210A0102014-07-23023 July 2014 Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve ML14189A4172014-07-0707 July 2014 Closure of 10 CFR Part 21 Interim Report - Limitorque Valve Motor - Motor Operator of SMB-0 Valve Actuator ML14192A0382014-07-0303 July 2014 Part 21 Report Incorrect Industrial Irradiator ML14079A0272014-03-13013 March 2014 Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve ML14069A4672014-02-26026 February 2014 Part 21 Report Involving a Potential Manufacturing Defect in Replacement Masterpact Cradles ML13260A0772013-09-12012 September 2013 10 CFR Part 21 Interim Report - General Electric (GE) Hitachi Nuclear Energy - Sbm Type Manual Switch ML13246A0872013-08-23023 August 2013 Nuclear Nonconformance Event Number 49302 - 10CFR21 Notification ML13191A5712013-06-28028 June 2013 10CFR21 Interim Report - Linear Indications/Cracks in Flange Forging, Model N-E13DM Pressure Transmitter ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML13094A1772013-03-18018 March 2013 Notice to the U.S. Nuclear Regulatory Commission of a Possible Deviation or Defect in Nuclear Qualified High Efficiency Particulate Air Filters Manufactured by Aaf ML13044A0752013-02-0808 February 2013 Part 21 - Completed Evaluation for Potential Error in Main Steam Line High Flow Calculational Methodology 2024-01-23
[Table view] Category:Deficiency Report (per 10CFR50.55e and Part 21)
MONTHYEARML23348A3942023-12-14014 December 2023 Interim Part 21 Report of a Potential Deviation or Failure to Comply Associated with Starter Contactors for the High Pressure Coolant Injection Suppression Pool Inboard Suction Valve ML23335A0722023-12-0101 December 2023 Interim Report of a Deviation or Failure to Comply Associated with a Relay in the Unit 2 Reactor Core Isolation Cooling Condensate Pump ML23320A2542023-11-16016 November 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump ML23282A0022023-10-0606 October 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23241A0022023-08-25025 August 2023 Paragon Final Part 21 Report on Defect with Eaton/Cutler Hammer Size 4 and 5 Freedom Series Contactors Modified by Paragon with Special Coils And/Or with RTV to Improve the Securing of Shading Coils RBG-48245, Part 21 Notification of a Failure to Comply Identified During Preinstallation Testing on a Motor Driven Relay2023-08-24024 August 2023 Part 21 Notification of a Failure to Comply Identified During Preinstallation Testing on a Motor Driven Relay ML23221A3702023-08-0303 August 2023 Paragon Energy Solutions, 10CFR Part 21 Initial Notification: P21-08032023-IN, Rev. 0 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23100A1072023-04-10010 April 2023 Framatome Part 21 Report Re Erroneous Change of State for Circuit Breaker ML23066A2212023-03-0707 March 2023 Velan, Inc. - Revised Part 21 Notification Re Butterfly Valves Found to Have a Number of Fasteners Loose ML23038A0192023-02-0606 February 2023 Curtiss-Wright Part 21 Notification for Qualtech Np Supplied Eaton TMR5 Timing Relays ML22341A0322022-11-30030 November 2022 10 CFR Part 21 Notification from Curtiss-Wright Nuclear Division for Qualtech Np Supplied Eaton TRM5 Timing Relays ML22301A1742022-10-28028 October 2022 Global Nuclear Fuel Americas, LLC (GNF) - Part 21 60-Day Interim Report Notification: GNF3 Raised Water Rod (SC-22-04 Rt) ML22208A0042022-06-17017 June 2022 Nutherm International, Inc., USNRC 10CFR Part 21 Notification Reference: Arnold Magnetics Power Supply Part Number PBM-24-106 ML22153A0792022-04-0707 April 2022 10CFR Part 21 Notification for Curtiss-Wright Supplied RCS-Dresser Actuator P/N: SURE-24-10-4 ML22305A5152022-02-22022 February 2022 EN 56192 - Grand Gulf Nuclear Station Re Elevation Outer Containment Personnel Airlock Door Failed Its Technical Specification Leakage Test ML22019A1762021-12-28028 December 2021 Lake Engineering Company - Interim Notification Per 10 CFR Part 21: Degraded Snubber SF1154 Hydraulic Fluid Batch No . 18CLVS431 ML21306A1802021-10-28028 October 2021 United Controls International - Part 21 Notification for York Pin: TCM-1 a Temperature Control Modules ML21294A0292021-10-0404 October 2021 Flowserve Part 21 Notification for Limitorque Supplied DC Motor ML21271A2342021-09-23023 September 2021 EN 55282 (Updated) - Framatome Part 21 Reportable Defect - Vacuum Breakers ML21260A0072021-09-0909 September 2021 Ametek Solidstate Controls, Notification of Potential Defect - 10CFR Part 21 Report Re Omron Timer Relay ML21225A0812021-08-0404 August 2021 Lake Engineering Co., Final Report Per 10 CFR Part 21 Degraded Snubber SF1154 Hydraulic Fluid Batch No. 17BLVS293 ML21181A2202021-06-29029 June 2021 Part 21 Written Notification - P21-03302021 Rev. 2 - Failures of Size 1 and 2 Freedom Series Full Voltage Reversing Starters ML21168A2172021-06-17017 June 2021 GE Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Fuel Support Side Entry Orifice Meta-Stable Flow for 2 Beam Locations in the BWR/6 Reactors M210077, GE Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Fuel Support Side Entry Orifice Meta-Stable Flow for 2 Beam Locations in the BWR/6 Reactors2021-06-17017 June 2021 GE Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Fuel Support Side Entry Orifice Meta-Stable Flow for 2 Beam Locations in the BWR/6 Reactors ML21126A1722021-04-29029 April 2021 Paragon Energy Solutions Failures of Size 1 and 2 Freedom Series Full Voltage Reversing Starters ML20366A0482020-12-0707 December 2020 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10 CFR21-0114, Rev. 1 ML21014A2342020-12-0707 December 2020 Fourth Interim Notification Per 10 CFR Part 21 Re Degraded Snubber SF1154 Hydraulic Fluid Batch No. 17BLVS293 ML20366A0472020-11-18018 November 2020 Curtiss-Wright 10 CFR Part 21 Notification for SF-1154 Hydraulic Fluid Batch 17BLVS293 ML20304A1612020-10-14014 October 2020 Lake Engineering Co., Degraded Snubber SF1154 Hydraulic Fluid Batch No. 16DLVS852 Final Report Per 10 CFR Part 21 ML20176A4322020-06-24024 June 2020 GE-Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Non-Conservative BWR/6 Side Entry Orifice (SEO) Loss Coefficients M200087, GE-Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Non-Conservative BWR/6 Side Entry Orifice (SEO) Loss Coefficients2020-06-24024 June 2020 GE-Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Non-Conservative BWR/6 Side Entry Orifice (SEO) Loss Coefficients ML20136A2552020-04-21021 April 2020 10 CFR Part 21 Report Notification for Curtiss Wright Scientech Certain RTL500 and RTL851 Modules ML20108F5302020-03-20020 March 2020 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10CFR21-0129, Rev. 0, Test Stand Deficiency - EMD Fuel Injectors P/N H40084720 ML20097B6912020-03-20020 March 2020 Second Interim Notification Per 10 CFR Part 21: Degraded Snubber SF1154 Hydraulic Fluid Batch No. 16DLVS852 ML20049A0752020-02-11011 February 2020 C&D Technologies, Inc. -10 CFR Part 21 Evaluation Regarding Container Failure in KCR-07 Batteries ML20042E2522020-01-31031 January 2020 EN 54485 Target Rock Redacted Update to Part 21 Report on Defect of Modification of Valve Component and Main Disc Lift Misadjustment ML20029D1612020-01-21021 January 2020 10 CFR Part 21 Report, Notification of a Defect Modification of a Valve Component and Main Disc Lift Misadjustment ML19347A4262019-12-10010 December 2019 General Atomics - Reportable Occurrence Under 10CFR21: Reported Failure in Analog High Range Radiation Monitor (RP-2C) ML19317D0932019-10-25025 October 2019 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10 CFR21-0127, Rev. 0, Emd Fuel Injectors - Seized Plunger and Bushing ML19253A0532019-08-29029 August 2019 Azz Nuclear - Report of Potential 1O CFR Part 21, Eaton Size 1 and 2 A200 Series Starters/Contactors ML19120A1062019-04-17017 April 2019 Interim Report of Potential 10 CFR Part 21, Eaton Size 1 and 2 A200 Series Starters/Contactors ML19121A1552019-04-15015 April 2019 Curtiss-Wright Nuclear Division, Enertech - 10 CFR Part 21 Notification for SF-1154 Hydraulic Fluid ML19101A0972019-04-0404 April 2019 Weir Valves & Controls USA, Inc. Part 21 Written Notification - Event Number: 53973 - 24 Class 150 Globe Alve for RHRSW HX Isolation MOV, E1150F068B at Detroit Edison - Fermi, Unit 2, Experienced Two Stem Failures ML19080A0592019-03-0808 March 2019 Interim Report of Potential 10CFR Part 21, Eaton A200 Series Starters/Contactors ML19072A0632019-03-0606 March 2019 10 CFR Part 21 Report Notification of a Defect with Target Rock Modulating Valve Positioner; Model 810000-X ML19071A1122019-03-0101 March 2019 Lake Engineering Co., Corrected Potentially Degraded Snubber SF1154 Hydraulic Fluid Batch 11KLVS146 Final Report, Per 10 CFR Part 21 ML19053A5002019-02-0101 February 2019 Sor, Inc. Part 21 Notification of Deviation Sor R-Series Housing with Terminal Block 2023-09-06
[Table view] |
Text
0510112015 Paop I 050/5U.S. Nuclear Reeulatrv Commision Onerations Center Event Rennrt Pavep Part 21 (PAR) Event# 51030 Rep Org: NUCLEAR LOGISTICS, INC Notification Date I Time: 05/01/2015 13:32 (EDT)
Supplier: ALLEN BRADLEY Event Date I Time: 04/30/2015 (CDT)
Last Modification: 05/01/2015 Region: 4 Docket #:
City: Fort Worth Agreement State: Yes County: License #:
State: TX NRC Notified by: TRACY BOLT Notifications: MEL GRAY R1DO HQ Ops Officer: DANIEL MILLS FRANK EHRHARDT R2DO Emergency Class: NON EMERGENCY ROBERT ORLIKOWSKI R3DO 10 CFR Section: GEOFFREY MILLER R4DO 21.21(d)(3)(i) DEFECTS AND NONCOMPLIANCE PART 21/50.55 REACTORS EMAIL POTENTIALLY UNQUALIFIED COMPONENT IN CERTAIN ALLEN BRADLEY TIMING RELAYS The following is an excerpt from a document received from the licensee via email:
"Report of potential 10 CFR Part 21, Allen Bradley Timing Relay Model 700RTC "Pursuant to 10 CFR 21.21(d)(3)(ii), AZZ/NLI is providing written notification of the identification of a potential failure to comply.
"On the basis of our evaluation, it is determined that AZZ/NLI does not have sufficient information to determine if the subject condition would, or has, created a Substantial Safety Hazard or would have created a Technical Specification Safety Limit violation as it relates to the subject plant applications.
"The specific part which fails to comply or contains a defect:
"As of 2009-2010, Allen Bradley relays base model 700RTC, contain an unevaluated CPLD (Complex Programmable Logic Device). This was an unpublished design change that was implemented to replace an obsolete integrated circuit chip. The undocumented design change did not result in a part number change from Allen-Bradley. There was no change to the appearance of the relay that would identify any design changes were made to the relay configuration. Therefore, NLI qualification/dedication of the relays after 2009 have not included additional testing for the new CPLD component.
"The timing relay model 700RTC has been dedicated/qualified for multiple applications for various plants.
"Between 2009-2010 Allen Bradley made a design change without changing the part number of the commercial
0510112015 12:29 TAX) P.O0011006 A&AZZ NLIN To:
Fax (301) 816- 5151 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 From:
Tracy Bolt Director of Quality Assurance AZZ INLI Nuclear Logistics, Inc.
7410 Pebble Drive Fort Worth, Texas 76118 817-284-0077 Pursuant to 10CFR 21.21 (d) (3) (1i), AZZINLI is providing in the following letter the written notification of the identification of a potential failure to comply.
Total Pages Including this page: 6 NUCLEAR LOGISTICS INC. www.,n.c*om 7410 Pebble Drive Fort Worth, Texas 76118
- 800.448.4124 Phone W 817.590.0484 Fax
0510112015 12:30 P.0021006.
AAZZ NLI" Date: April 30, 2015 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 Part 21 Report No: P21-04302015
Subject:
Report of potential 10CFR Part 21, Allen Bradley Timing Relay Model 700RTC Pursuant to 10CFR 21.21 (d) (3) (ii), AZZINLI is providing written notification of the identification of a potential failure to comply, On the basis of our evaluation, it is determined that AZZINLI does not have sufficient information to determine if the subject condition would, or has, created a Substantial Safety Hazard or would have created a Technical Specification Safety Limit violation as it relates to the subject plant applications.
The following information is required per 10CFR 21.21 (d) (4).
(i) Name and address of the individual or individuals informing the Commission.
Tracy Bolt, Director of Quality Assurance Nuclear Logistics, Inc 7410 Pebble Drive Ft. Worth, TX 76118 (ii) Identification of the facility, activity, or the basic component supplied for such facility or such activity within the United States which fails to comply or contains a defect.
The specific part which fails to comply or contains a defect:
As of 2009-2010, Allen Bradley relays base model 700RTC, contain an unevaluated CPLD (Complex Programmable Logic Device). This was an unpublished design change that was implemented to replace an obsolete integrated circuit chip. The undocumented design change did not result in a part number change from Allen-Bradley. There was no change to the appearance of the relay that would identify any design changes were made to the relay configuration. Therefore, NLI qualification/dedication of the relays after 2009 have not included additional testing for the new CPLD component.
The timing relay model 700RTC has been dedicated/qualified for multiple applications for various plants.
Page 1 of 5 NUCLEAR LOGISTICS INC. ,www.azz.cem 7410 Pebble Drive e Fort Worth, Texas 76118 o 800.448.4"124 Phone
0510112015 12:30 TAN) P.0031006 (iii) Identification of the firm constructing or supplying the basic component which fails to comply or contains a defect.
NLI procured the commercial grade relays, dedicated, qualified and supplied the subject relays as Safety Related.
(iv) Nature of defect or failure to comply and the safety hazard which is created or could be created by such defect or failure to comply.
Between 2009-2010 Allen Bradley made a design change without changing the part number of the commercial relay or providing any documented evidence of a design change. The manufacturer specification data sheets maintain the classification that the relays are "solid state", which would imply that there are no digital devices installed in the relay. However, after inspection of the internals of the timing relay (Figure 2), it has been identified that the unit does contain a CPLD which meets w1 the definition of a digital device under the guidance of NEI 01-01. See Figures 1 and 2 below:
Figure 1- Original qualified design (prior to 2009).
Relays supplied prior to 2009 are not affected by this issue.
Page 2 of 5
0510112015 12:30 TAX) P.0041006 Figure 2 - New design circuit board and CPLD / that repiaced the original component.
(v) The date on which the information of such defect or failure to comply was obtained.
On April 27, 2015, enough information was gathered from the evaluations being performed to determine the reportability of the failure to comply that is the root cause for the event.
Page 3 of 5
4 05101/2015 12:30 TAX) P.0051006 (vi) In the case of a basic component which contains a defect or fails to comply, the number and location of these components in use at, supplied for being supplied for, or may be supplied for, manufactured or being manufactured for one or more facilities or activities subject to the regulations in this part.
Relays that have been procured and dedicated from 2009 to present are identified below.
Plant Name Purchase order Serial Number Browns Ferry 72923-i 29760-001-00003
/ Ginna Station 6617899 51475-001-00001 and -00002, 52656K1-01-0001 4/ Grand Gulf 10304816 34182-001-00001 9 Grand Gulf 10400205 56319-001-00001 r Invensys 4540224951 39228-001-00001 thru -00017 39407-001-00001 thru -00008, 39407-002-00001 thru -
KHNP Y12-0292-010 00005
_Lungmen 874941 IEO07CO 38486-001-00001 and -00002, 38486-002-00001 Millstone 45735761 31998K1-01-0001
'I Millstone 45735761 31391-001-00001 Nine Mile Point 530734 63245-001-00001 thru -00018
-North Anna 70239037 55133-001-00001 & -00002 39602-001-00001 and -00002, 39602-002-00001 thru -
z North Anna 70239037 00003 2- 40033-001-00001 and 40033-001-00002, 40033-002-00001 North Anna 70239037 thru -00003 33846-001-00001 thru -00009, 33846-001-00011 thru 5
OPPD Ft Calhoun 155213 33846-001-00015, 33846-002-00002 & -00003 OPPD Ft Calhoun 163495 35941-001-00001 thru -00004 OPPD Ft Calhoun 164936 35891K1-01-0001 thru -0005 OPPD Ft Calhoun 164936 36888-001-0000 1, -00003 thru -00005 OPPD Ft Calhoun 164936 36888K2-01-0001 OPPD Ft Calhoun 177878 39194-001-00001 thru -00006 OPPD Ft Calhoun 182681 40743-001-00001 thru -00003, 40743-002-00001 17 OPPD Ft Calhoun 187625 51477-001-00001 thru -00004 Perry Station 45354401 33357-001-00001 thru -00003 River Bend Station 10349942 38585-001-00001 thru -00004 River Bend Station 10362573 40077-001-00001 River Bend Station 10378904 51627-001-00001 South Texas Project 134783 33750-001-00001 & -00002 South Texas Project 147962 37204-001-00001 thru -00006 Page 4 of 5
4 0510112015 12:30 (FAX) P.0061006 C' South Texas Project 154172 51592-001-00001 thru -00004 qI South Texas Project 171193 57894-001-00001 thru -00006 Z. St Lucia Bechtel PO: 25486-974-FPA-EMRO-00001 385490l100002 thru -00005 (vii) The corrective action which has been, is being, or will he taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action.
The relays that are currently in stock at NLI have been placed on hold until after the units have been qualified for the specific application. NLI will perform EMC qualification testing per the requirements of EPRI TR-102323 Rev. 3 for the following tests, as applicable: CEI01, CE102, RE10I, RE102, RS101, RSl03, CSI01, CSI14, CS115 and CSI16. Estimated completion date is August 28, 2015.
(viii) Any advice related to the defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to purchasers or licensees.
The functions of the relays supplied by NLI were tested for the following critical characteristics:
Pick-up at rated voltage Drop-out when the voltage is removed Pick-up at degraded voltage Over-Voltage operation Insulation resistance Off delay settings are adjustable from 2-120 seconds Pick-up voltage Drop-out voltage Dimensions and Configuration The relays are dedicated for generic application usage in timing applications. The specific plant application(s) is unknown by AZZ. The EMC qualification of the relay is dependent on the installed configuration and location in the plant. The plant should evaluate whether the installed relays are subjected to unevaluated EMI/KFI conditions in the plant.
Please contact me with any questions or comments.
Sincerely, Tracy Bo Director of Quality Assurance Page 5 of 5