|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24008A2112024-01-25025 January 2024 Evaluation of Seismic Risk for V. C. Summer Under the Process for Ongoing Assessment of Natural Hazard Information (Poanhi) - January 25, 2024 (Slides) ML24008A2182024-01-25025 January 2024 Seismic Data to Support Public Meeting with Dominion Regarding NRC Staff Evaluation of Seismic Risk at V.C. Summer Generating Station - January 25, 2024 (Tables) ML23313A1292023-11-0909 November 2023 Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application - November 14 Meeting Slides ML23131A4182023-05-25025 May 2023 V.C. Summer Nuclear Station 2022 Annual Assessment Meeting.Pptx ML22115A0502022-04-21021 April 2022 VC Summer, 2021 Annual Assessment Meeting ML20091G7232020-03-31031 March 2020 V.C. Summer 2019 Assessment Meeting Presentation ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML14323A4522014-11-19019 November 2014 V.C. Summer Construction Update ML14266A3912014-09-23023 September 2014 September 23, 2014, Category 1 Public Meeting with V. C. Summer - Presentation Slides ML14232A5372014-08-21021 August 2014 8-21-14 CIP Mtg Slides - FFD and ITAAC ML14219A4762014-08-0707 August 2014 Operating Experience on Initial Test Program ML14106A4762014-04-16016 April 2014 End of Cycle 2013 Public Meeting Memo ML14057A4202014-02-27027 February 2014 Public Meeting 2/27/2014 VCS Construction Update ML14028A4272014-01-23023 January 2014 Vendor Inspection Finding & ITAAC (Pdf) ML13309A8592013-11-0505 November 2013 V. C. Summer Construction Status and Lesson Learned AD Torres ML13170A1302013-06-18018 June 2013 Public Slide - NFPA 805 Transient Combustible Controls ML13170A1192013-06-18018 June 2013 Public Slide - Control Room Evacuation Due to Fire, Based on NFPA 805 ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13098A8042013-03-26026 March 2013 Combined Emergency Plan Review ML12228A6292012-08-16016 August 2012 Report ITAAC Presentation ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML11350A0902011-12-20020 December 2011 Draft VC Summer Public Meeting 20 Dec 2011 ML11242A0502011-08-30030 August 2011 Slides - Licensee Perspective on ITAAC Completion Process NRC Commission Briefing ML1120707792011-07-26026 July 2011 Enclosure 3: Presentation Slides/Handouts ML1115204732011-06-0101 June 2011 Meeting Summary - V. C. Summer - Presentation Slides ML1016705202010-06-17017 June 2010 Fire Protection Screening Criteria - V.C. Summer Nuclear Station ML1012600102010-05-0505 May 2010 Meeting Slides ML1012600092010-05-0505 May 2010 Meeting Posters ML0911000692009-04-17017 April 2009 Summary of Meeting with Public/Open House to Discuss NRC Reactor Oversight Process and the Annual Assessment of the Virgil C. Summer Nuclear Station ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 ML0811405532008-04-23023 April 2008 V. C. Summer Nuclear Station, Slides - Refuel 17 Plans ML0723400122007-08-22022 August 2007 Public Outreach Meeting South Carolina E&G Summer Nuclear Power Plant Combined License Application ML0715806282007-05-31031 May 2007 Enclosure 8 - OBE Exceedance Issues ML0713501062007-05-0202 May 2007 Meeting Handout on CRDM Canopy Seal Clamp Installation ML0713501092007-05-0202 May 2007 Meeting Handout on Summary of HP Performance During RF16 ML0713501022007-05-0202 May 2007 Meeting Handout on RB Tendon/Iwe/Iwl Inspection ML0713500972007-05-0202 May 2007 Meeting Handout on Alternate Safety Power Source - Summer ML0713500662007-05-0202 May 2007 Meeting Handout on RF16 Outage Review V.C. Summer ML0706703232007-03-0101 March 2007 (Westinghouse AP1000) ML0629904782006-10-24024 October 2006 VC Summer, Enclosure to Meeting Summary, September 13, 2006, Meeting with South Carolina Electric & Gas, on Generic Letter 96-06 (TAC M96872) ML0707202262006-06-22022 June 2006 Sce&G VC Summer Site - Site Characterization Visit (Handouts) ML0609405532006-03-20020 March 2006 Meeting Summary - Enclosure 2. Handouts for Meeting with South Carolina Electric & Gas Company Re Results of Root Cause Evaluation for the High Failure Rate on the January 10, 2006, Operator Licensing Initial Written Examination ML0600304352005-12-30030 December 2005 Rii Presentation Revised - RF-15 Outage Information IR 05000395/20050072005-03-10010 March 2005 Final Significance Determination for a Green Finding (NRC IR 05000395/2005007 Virgil C. Summer Nuclear Station) ML0409805332004-03-11011 March 2004 RIC 2004 Presentation - T11 - Alexander Marion - Emergent Technical Topics ML0404902122004-01-28028 January 2004 Handouts from 01/28/04 Management Meeting ML0328101372003-10-0606 October 2003 Presentation Slides for Post-Refueling Outage Meeting ML0327206212003-09-24024 September 2003 Examiner - Vendor Matrix with Phone Number ML0327206112003-09-22022 September 2003 Exam Process ML0309805902003-03-31031 March 2003 Annual Assessment Meeting for Virgil C. Summer Nuclear Station. NRC Presentation Slides 2024-01-25
[Table view] |
Text
Introduction Reason for Commitment Change
" Management Challenge
- Design Change Package late issue
- Planning & Scheduling not timely
- Implementation Resources
" Risk of implementing Design Change
- Risk of impact to SW supply to RBCU function without corresponding risk improvement from design change Plant Safety in Current Configuration VCSNS will remain safe:
- Water hammer condition exists only when SW aligned to RBCU's and LOOP
- Becomes significant only when SW aligned to RBCU's, w/LOOP, and w/LOCA or MSLB
- PRA indicates very low risk (1.74E-07/yr)
- Phase 1 actions in place
- No damage to piping or hangers Enclosure 2
I Schedule for Design Change Implementation (Commitment change required)
Implementation by 5/2008 (Refueling 17)
- Extensive modification
- Unit shutdown required
- Next scheduled shutdown for refueling Resolution of Technical Issues from NRC letter August 22, 2006
" VCSNS reviewed NRC ltr. dated 8/22/2006
" No additional explanation necessary
" VCSNS expects to respond in the next 60 days
Introduction Purpose of Visit
" Discuss VCSNS commitments associated with Generic Letter (GL) 96-06.
- Implement design changes by 10/06
- 1. Delay opening 3107A/B
- 2. Install vacuum relief valves
- 3. Replace 3107AJB
" VCSNS wishes to alter this commitment FIGURE 2a Modification WWIl Coilutkrain - RBCUsalignedWithSWsysem WATERHAMAMER 14110A110N- hAM1.WU 2 .W-SMMSWSPq upmd~ard rg.~mdSWBP PHASE 1 - LOOPo.,an SWb-W P.W. Wd-OLW PHASE 2- VW. 3107Afttdo- 8WdkqP PHASE 32-SAMdIotM SMW310A IA Need I -NSWH PHASES. ý1 31OIAISE.W 1.SW 301 ICStupy va*,m
-lc
.IiI HA.
"TO,SW Pond
V. C. Summer Nuclear Station Generic Letter 96-06 Discussion Brad Stokes, Manager Design Engineering Alan Torres, Manager Planning and Scheduling Chuck Barbier, Principle Design Engineer - Piping CM
ýe ýZý Agenda
- Plant Safety in Current Configuration
- Schedule for Implementation of Modifications
- Resolution of Technical Issues
NRC/VCSNS Open Discussion FIGURE 2a Modification Inital Configuration - RBCUs aligned with SW system 3109A WATER HAMMER MITIGATION - Mod to install: XAA-1
- 1. vacuum relief valve downstream of 3107A
- 2. replace 3107A with an air operated butterfly valve that fast closes upon de-energize ofSWBP 3108B 3109B
- 3. delay opening of valve 3107A for five seconds after start of SWBP XAA-I B Lý PHASE 1 - LOOP occurs causing SW booster pumps to de-energize.
Fast closing valve PHASE 2 - Valve 3107A fast closes and traps traps water above it Column of fluid above it PHASE 3 - Void formed below 3107A is filled with air by vacuum relief valves PHASE 4 - After 41 seconds, SW Vacuum booster pumps re-energized, 3107A valve 5 sec Relief delayed opening allows fluid flow momentum to Valve build preventing further void formation PHASE 5 - air void downstream 3107A flushed to SW pond
'AIAA SW Booster Pump SW Supply De-energizedIdue -
to LOOP IC Supply IC Return Vacuum relief valve replaces vacuum void To SW Pond with air