Meeting Handout on Summary of HP Performance During RF16
ML071350109
Person / Time
Site: Summer 
Issue date: 05/02/2007
From:
SCANA Corp, South Carolina Electric & Gas Co
To:
Office of Nuclear Reactor Regulation
References
Download: ML071350109 (8)


Text

  • Benchmark Dose Rate 9.1 mrem/hr
  • Outage Exposure Goal 65 Rem
  • RF16 Actual 64.134 Rem (ED)
  • TLD corrected to 56.129 Rem
  • 11.880 Rem Emergent Work
  • 10.681 Rem resulted from CRDM repairs
  • Best Dose performance ever at VCS!

Summary of HP Performance during RF16

CRDM Leak Repair and Cleanup Activities 6.112 Rem Significant Emergent Dose Activities for RF16 RV Head Permanent Shield/Shroud/Insulation Removal/Replacement 4.551 Rem

Reactor Building Sump Mod Challenges (4.369 Rem)

  • Space
  • Hexavalent Chrome (CrVI)
  • Welding Resource
  • Dose Rate vs. man-hrs Significant Dose Activities for RF16

Volumetric Head Inspection Challenges (3.830 Rem)

  • LHRA Controls
  • Contamination Controls
  • Location in RB
  • High dose rates (1.5 to 7.0 R/hr)

Significant Dose Activities for RF16

Damaged Fuel Assembly (RP Response)

  • Underwater Surveys

- Captured high activity metal fragment (>1000 R/hr) prior to drain down

  • Close scrutiny on no mode valve work (1st off RCS valves)
  • Increased Hot Particle sweeps
  • Discontinued use of RM-24 Radon instrument (alpha discrimination)

ALARA Remote Camera Monitoring and Telemetric Dosimetry Robotic bare metal video inspection RV Head HydraNut Closure Mod

Radwaste Transportation WHITE Finding in 1st qtr 2006 61 Shipments were made during RF16 with no issues95-001 Follow up inspection closed out finding post outage

Closing Remarks Jeff Archie Vice President, Nuclear Operations