MONTHYEARML23325A2452023-11-13013 November 2023 Enclosure 2 - Dominion Slides ML23325A2442023-11-13013 November 2023 Enclosure 1 - Attendance List ML23325A2432023-11-13013 November 2023 Regulatory Conference Summary ML23331A7892023-11-0909 November 2023 Nov. 2023 Enviro Scoping Meetings Related to the V.C. Summer Subsequent License Renewal Application Meeting Summary ML23171A9172023-06-20020 June 2023 Summary of Meeting Concerning the V.C. Summer Nuclear Station, to Discuss Annual Assessment for Period Jan 1, 2022 Through December 31, 2022 ML22270A2042022-09-30030 September 2022 Summary of Meeting Regarding a Potential Request to Modify the Reactor Vessel Surveillance Capsule Withdrawal Schedule for VC Summer ML22151A3332022-05-31031 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting Regarding the V.C. Summer Nuclear Station, Docket No. 50-395, Meeting Number 20220449 ML21131A1612021-05-11011 May 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Virgil C. Summer Nuclear Station, Docket No. 50-395; North Anna Power Station, Docket Nos. 50-338 and 50-339; and Surry Power Station, Docket Nos. 50-280 and 50-281, Meeting ML20213B1672020-08-13013 August 2020 July 23, 2020, Summary Regarding Second Pre-Application Meeting to Discuss Proposed Technical Specification Task Force-425 License Amendment Request ML20181A0052020-07-13013 July 2020 June 24, 2020, Summary Regarding Pre-Application Meeting to Discuss Proposed Technical Specification Task Force-425 License Amendment Request (EPID-L-2020-LRM-0049) ML20105A1482020-04-10010 April 2020 Public Meeting Summary Virgil C. Summer Nuclear Station ML19196A2112019-08-0202 August 2019 July 23, 2019, Meeting Summary Regarding National Fire Protection Association 805 Supplement License Amendment Request ML19123A1332019-05-0101 May 2019 Public Meeting Summary - V.C. Summer Nuclear Station, Docket No. 50-395 to Provide Opportunities to Discuss Annual Assessment of V.C Summer Nuclear Station with the Public for Period of January 01, 20018 - December 31-2018 ML19086A0272019-04-12012 April 2019 April 4, 2019, Meeting Summary Regarding Pre-application Meeting to Discuss Two Proposed Relief Requests ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML18068A0272018-03-22022 March 2018 Summary of March 15, 2018, Pre-Application Meeting with South Carolina Electric and Gas Company to Discuss a Future NFPA-805 Amendment (EPID-L-2018-LRM-0015) ML17103A5222017-04-12012 April 2017 Annual Assessment Meeting Summary 2017 ML15126A1962015-05-0505 May 2015 April 16, 2015 Public Meeting Summary - Category 1 - Virgil C. Summer Nuclear Station Units 2 and 3 Annual Assessment ML15119A5102015-04-29029 April 2015 Meeting Summary with Members of the Public Concerning the Annual Assessment of of Virgil C. Summer Nuclear Station, Unit 1, in Blair, S.C ML14106A4762014-04-16016 April 2014 End of Cycle 2013 Public Meeting Memo ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13199A1772013-07-31031 July 2013 Summary, June 20, 2013 Category 1 Meeting with South Carolina Electric and Gas Company, to Discuss Voluntary Fire Protection Risk Initiative Self-Assessment ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13119A4112013-04-29029 April 2013 Summary of Category 3 Public Meeting, Virgil C. Summer Nuclear Station, Unit 1, Annual Assessment ML13098A8442013-04-11011 April 2013 Summary of Meeting with South Carolina Electric & Gas to Discuss Proposed Emergency Plan Changes ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML1120707482011-07-26026 July 2011 July 20, 2011, Meeting Summary Pre-Application Meeting with South Carolina Electric and Gas Regarding General License Independent Spent Fuel Storage Installation Plans (TAC No. L24544) ML11152A0802011-06-14014 June 2011 Summary of March 31, 2011, Meeting with South Carolina Electric and Gas Company to Discuss NFPA-805 License Amendment ML1115204542011-06-0101 June 2011 Summary of Public Meeting with South Carolina Electric & Gas Co., V. C. Summer to Discuss the NRC Reactor Oversight Process and Annual Assessment ML1023804682010-08-26026 August 2010 08/18/10 Summary of Meeting NRC Initial Exam Writer'S Workshop ML1016704282010-06-17017 June 2010 Meeting Summary Notice ML0930005732009-11-0505 November 2009 Summary of September 14, 2009, Public Conference Call to Discuss Responses to Generic Letter 2004-02 Requests for Additional Information ML0923803922009-08-26026 August 2009 08/11-12/2009-Summary of Meeting Re 2009 Us NRC Initial Exam Development Workshop ML0911000692009-04-17017 April 2009 Summary of Meeting with Public/Open House to Discuss NRC Reactor Oversight Process and the Annual Assessment of the Virgil C. Summer Nuclear Station ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 IR 05000395/20075022007-07-30030 July 2007 Summary of Public Meeting - Virgil C. Summer Nuclear Station, to Discuss Significance on Apparent Violation Documented in Inspection Report 50-395-07-502 ML0713500592007-05-11011 May 2007 Summary of Public Meeting with South Carolina Electric & Gas Company to Brief the Licensee'S Post Outage Review of Refueling Outage 16 at Virgil C. Summer Nuclear Station IR 05000395/20070022007-04-30030 April 2007 IR 05000395-07-002; on 01/01/2007 - 03/31/2007 for South Carolina Electric & Gas Company; Virgil C. Summer Nuclear Station, Integrated Inspection Report and Annual Assessment Meeting Summary ML0627605282006-10-24024 October 2006 September 13, 2006, Summary of Meeting with South Carolina Electric & Gas Re Generic Letter 96-06 (TAC No. M96872) ML0627800022006-10-0404 October 2006 Summary for Meeting Between NRC and South Carolina Electric & Gas Company Refueling Outage 16 at Virgil Summer ML0621305672006-08-0101 August 2006 Summary of 07/19 - 07/20/2006 Meeting - 2006 Initial Exam Development Workshop ML0609601222006-04-0303 April 2006 Summary of Meeting with South Carolina Electric & Gas Company to Discuss the Results of the Root Cause Evaluation for the High Failure Rate on the January 10, 2006, Operator Licensing Initial Written Examination ML0601705522006-01-17017 January 2006 Comment Card Responses During January 9 Through 10, 2006, NRC Public Workshop ML0600304322005-12-30030 December 2005 Public Meeting Summary - Oct. 18, 2005 Category 1 Public Meeting-Summer, Docket # 50-395 ML0509704712005-04-0707 April 2005 Meeting Summary - Public Meeting - Virgil C. Summer Nuclear Power Station ML0504901422005-02-17017 February 2005 Summary of January 13, 2005, Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Nuclear Energy Institute (NEI) on Updating the License Renewal Guidance Documents ML0331404862003-11-0606 November 2003 ,Summary of Public Meetings to Discuss the Draft Supplement 15 of the Generic Environmental Impact Statement for the Renewal of the V. C. Summer Nuclear Station Operating License ML0328101292003-10-0606 October 2003 Summary of Post-Refueling Outage Meeting ML0328002772003-10-0606 October 2003 Closed Meeting Summary Between Usnrc/South Carolina Electric & Gas Co. to Discuss Sensitive Safeguards Information ML0224601912002-08-29029 August 2002 Summary of Meeting with Virgil C. Summer Nuclear Station, Post - Refueling Outage Meeting 2023-06-20
[Table view] |
Text
October 24, 2006 LICENSEE: South Carolina Electric & Gas Company FACILITY: Virgil C. Summer Nuclear Station
SUBJECT:
SUMMARY
OF SEPTEMBER 13, 2006, MEETING WITH SOUTH CAROLINA ELECTRIC & GAS, ON GENERIC LETTER 96-06 (TAC NO. M96872)
On September 13, 2006, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of South Carolina Electric & Gas (SCE&G) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the schedule for the licensees commitments concerning the resolution of Generic Letter (GL) 96-06, Assurance of Equipment Operability and containment Integrity During Design-Basis Accident Conditions, for the V. C. Summer Nuclear Station (VCSNS). A list of attendees is provided as Enclosure 1. Members of the public were not in attendance.
The licensees slides are included in Enclosure 2. As part of the resolution of GL 96-06 for VCSNS to reduce the potential for waterhammer, the licensee had committed to implement certain modifications during the Fall 2006 refueling outage. These modifications included delaying the opening of valve 3107 A for five seconds after the start of a service water booster pump replacement of valve 3107 A with an air operated butterfly valve that fast closes and installation of a vacuum relief valve downstream of valve 3107 A. The licensee changed the schedule for these modifications for the spring 2008 refueling outage. The licensee stated that the reasons for the rescheduling included management challenges with issuance of the design change package and the requirement to use available implementation resources for other activities such as the containment sump modifications. The licensee stated that the risk of not making the modifications as previously planned is very low.
The current status of the NRC staffs assessment of GL 96-06 issues for the VCSNS is presented in its letter dated August 22, 2006, wherein certain issues are reported to be closed and the need for additional information on remaining issues is identified. The licensee stated that they would respond to that letter within 60 days of the date of the meeting.
The NRC staff present at the meeting did not identify an objection to the licensees plans to reschedule the implementation of the modifications. The NRC staff plans to continue its review of the GL 96-06 issue for VCSNS upon receipt of the licensees response to the staffs August 22, 2006, letter.
/RA/
Robert E. Martin, Senior Project Manager Plant Licensing Branch 2-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-395
Enclosures:
- 1. List of Attendees
- 2. Licensee Handout(s) cc w/encls: See next page
SUMMARY
OF SEPTEMBER 13, 2006, MEETING WITH SOUTH CAROLINA ELECTRIC & GAS, ON GENERIC LETTER 96-06 (TAC NO. M96872)
LIST OF ATTENDEES SCE&G C. Barbier A. D. Torres R. B Stokes NRC C. Gratton G. Hammer J. Tatum Enclosure 1
The NRC staff present at the meeting did not identify an objection to the licensees plans to reschedule the implementation of the modifications. The NRC staff plans to continue its review of the GL 96-06 issue for VCSNS upon receipt of the licensees response to the staffs August 22, 2006, letter.
/RA/
Robert E. Martin, Senior Project Manager Plant Licensing Branch 2-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-395
Enclosures:
- 1. List of Attendees
- 2. Licensee Handout cc w/encls: See next page DISTRIBUTION:
Public RidsAcrsAcnwMailCenter RidsRgn2MailCenter LPL2-1 R/f R. Jasinski, NRR RidsnrrDorlLPL2-1 C. Gratton RidsNrrPMRMartin G. Hammer RidsNrrLACSola J. Tatum RidsOgcRp S. Lee (EDO, Rgn II)
Package: ML062910160 Enclosure 2 (Meeting Handouts): ML062990478 Meeting Summary: ML062760528 NRC-001 OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/LPL2-1/BC NAME RMartin RSola EMarinos DATE 10/24/06 10/24/06 10/24/06 OFFICIAL RECORD
Virgil C. Summer Nuclear Station cc:
Mr. R. J. White Nuclear Coordinator S.C. Public Service Authority c/o Virgil C. Summer Nuclear Station Post Office Box 88, Mail Code 802 Jenkinsville, SC 29065 Resident Inspector/Summer NPS c/o U.S. Nuclear Regulatory Commission 576 Stairway Road Jenkinsville, SC 29065 Chairman, Fairfield County Council Drawer 60 Winnsboro, SC 29180 Mr. Henry Porter, Assistant Director Division of Waste Management Bureau of Land & Waste Management Dept. of Health & Environmental Control 2600 Bull Street Columbia, SC 29201 Mr. Thomas D. Gatlin, General Manager Nuclear Plant Operations South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Post Office Box 88, Mail Code 300 Jenkinsville, SC 29065 Mr. Robert G. Sweet, Manager Nuclear Licensing South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Post Office Box 88, Mail Code 830 Jenkinsville, SC 29065 Ms. Kathryn M. Sutton Morgan, Lewis & Bockius LLP 111 Pennsylvania Avenue, NW.