Construction Status Update Ryder Thompson South Carolina Electric & Gas

VCS Units 2 & 3 Safely Construct VCS Units 2 & 3 in accordance with the Approved Design and License Requirements.

VCS Units 2 & 3 Construction Milestones - Completed

  • Unit 2 FNC, 3/11/13
  • Unit 2 CR10 set
  • Unit 2 Turbine Building 4/3/13 Basemat & Basement Walls
  • Unit 2 Containment Vessel placed Bottom Head placed,
  • Unit 2 Condensers set 5/22/13 12/30/13
  • Unit 3 FNC, 11/4/13
  • Unit 2 CH80 & CH82 steel set

VCS Units 2 & 3 Construction Milestones - Upcoming

  • 2014 First Quarter

- Set Unit 2 CA20 Auxiliary Building Module

- Complete Unit 3 CR10 CVBH Support Module

- Set Unit 2 Containment Vessel Ring 1

- Begin Backfill Adjacent to Aux. Building

  • 2014 Second Quarter

- Set Unit 3 Containment Vessel Bottom Head

- Set CA05 Module

VCS Units 2 & 3 - Site Overview Site Overview

VCS Unit 3 FNC Pour Site Overview

VCS Unit 3 CR 10 Installation Site Overview

VCS Unit 2 Auxiliary Building Wall Construction Site Overview

VCS Unit 2 Containment Vessel Ring 1 Site Overview

VCS Unit 3 Containment Vessel Bottom Head Site Overview

VCS Unit 3 Containment Vessel Ring 1 Site Overview

Unit 3 Core Makeup Tanks Units 2 & 3 Accumulator Tanks Unit 2 Turbine Stator Units 2 Turbine Waterbox 12

VCS Unit 2 Turbine Building Condensers Set 13

Construction Inspection Lessons

  • Share Lessons Learned with Vogtle
  • Open Communication with Vogtle, WEC and CB&I
  • Robust Construction Oversight with Focus on ITAAC