RF16 Outage Review V. C. SUMMER NUCLEAR STATION Jeff Archie Vice President, Nuclear Operations

RF16 Post Outage Review V. C. SUMMER NUCLEAR STATION Don Shue Outage Manager

Outage Overview:

3/4Outage Began October 13, 2006 3/4Duration - 39 Days, 16 Hours 3/4Outage Goals Focus On:

Nuclear Safety Radiological Safety Industrial Safety

Outage Goal Status:

3/4Nuclear Safety Significant Events:

Goal: < 0 Actual: 0 3/4Human Performance Events:

Goal: < 1 Actual: 1 3/4Recordable Injuries:

Goal: < 1 Actual: 0 3/4Dose:

Goal: < 65 R Actual: 64.1R (11.9 Emergent)

Outage Goal Status:

3/4Post Outage Capacity Factor:

Goal: 96% Actual: 98.3%

3/4Outage Cost:

Goal: < $25.2M Actual: $25.2M

Outage Scope:

3/42430 Preventative Maintenance Tasks 3/41359 Technical Specification Surveillances 3/41665 Corrective and Elective Work Requests 3/4410 Modification Related Work Documents Total: 5864 Work Documents (8834 Work Steps)

3000 Refueling Outage Activities:

2610 2426 2455 2430 2500 2402 2291 1938 1843 2000 1665 1500 1359 1216 1244 1083 1109 1057 976 1000 1000 943 942 923 539 560 500 386 410 338 270 141 66 0

R R R R R R R R R R R R R R R R R R R R R R R R R R R R F F F F F F F F F F F F F F F F F F F F F F F F F F F F 0 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1 9 0 1 3 4 5 6 9 0 1 3 4 5 6 9 0 1 3 4 5 6 9 0 1 3 4 5 6 Preventative Surveillance Corrective & Elective Modification

RF-16 Major Projects RB Recirculation Sumps:

3/4 Completed Reconfiguration of RHR and Spray Sumps 3/4 Added RB Debris Interceptors Large Gates Toe Plates 3/4 Replaced Safety Injection Throttle Valves 3/4 Rebalanced Safety Injection System