ML13309A859

From kanterella
Jump to navigation Jump to search
V. C. Summer Construction Status and Lesson Learned AD Torres
ML13309A859
Person / Time
Site: Summer  South Carolina Electric & Gas Company icon.png
Issue date: 11/05/2013
From:
South Carolina Electric & Gas Co
To:
Office of New Reactors
Bloom S, NRO/DCIP/IGCB, 415-2431
References
Download: ML13309A859 (26)


Text

V C Summer Construction Status and Lesson Learned AD Torres

Unit 2 & 3 Construction Status Majorj Milestones il

  • Completed Unit 2 Concrete Basemat
  • Unit 2 Pouring of Major Auxiliary Building Walls
  • Set U2 containment vessel bottom head
  • F bi Fabricatedd and d SSet U2 C Condensers d andd TTurbine bi Bld Steel S l
  • Fabricated and Set Reactor Cavity Module
  • Received Unit 2 Reactor vessel on site
  • Installed Unit 3 basemat rebar and completed Basemat Pour

Unit i 2 First i Nuclear l Concrete ((FNC))

  • First safety-related nuclear concrete placed in over 30 years
  • 7,000 yds3 of continuously placed concrete
  • Placement began on March 9, 2011 and l t d approximately lasted i t l 52 hours6.018519e-4 days <br />0.0144 hours <br />8.597884e-5 weeks <br />1.9786e-5 months <br />

Setting of U2 CR10 Settingg of Unit2 Containment Vessel Bottom Head (CVBH)

  • Set Date: 05/22/13
  • Design Weight: 936 Tons
  • Linear Feet of Weld: 2,253
  • Linear Li FFeett off R Repaired i dW Weld:

ld 22

  • Weld Acceptance Rate: 99.02%

Settingg of U2 CVBH U2 Containment Vessel (CV) Rings CV Lower Ring is made up of:

  • Four F C Courses
  • A lower and an Upper Equipment Hatch
  • A lower and an Upper Personnel Hatch
  • An external Stiffener ff CV Lower Ring CV Middle Ring is made up of:
  • Four Courses

U2 Containment Vessel Ringg 1 Coatings g Steel surface preparation for inorganic zinc application Inorganic zinc application in progress on U2 CV Ring 1

Unit 3 Containment Vessel Bottom Head (CVBH)

June 2013 October 2013

Inside Containment CB65 - R t C Reactor l tD Coolant i TTankk R Drain Room CB66 - RCDT/ R t C Reactor t tP Compartment Passageway CB65 CA04 CB66

Unit 2 CA04 Module

  • Reactor Vessel Cavity
  • Dimensions: 21-0 W x 26-6 H
  • Approx. Design Weight: 90,000 lbs.
  • Approx. 7,661 linear feet of weld
  • Installed 1 1,436 436 shear studs

Unit 2 CA04 Module

  • Lift and set with the Heavy Lift Derrick (HLD)
  • Date: 09/27/13

U i 2 Auxiliary Unit A ili W Wallll Pl Placements

  • 16 feet tall, tall 3 feet thick
  • Top Elevation is 826
  • Line I, Area 5 completed 8/24/13
  • Line I, Area 2-3 completed 9/28/13
  • Line I, Area 4-7 completed 10/17/13

Unit 2 Aux Building Rebar Installation Column Lines I, 2, 4, 5, 11, and Q, up to El 82 6 is substantially complete Column Line Q Column Line 11, 11 looking east to west.

west

U2 TB Major j Component p Installation Condenser B Lower Shell July 2013 700 Tons South TG Support CH80 August 2013 650 Tons

U2 TB Major j Component p Installation Center TG Support CH81A Center C t TG SSupportt CH81B October 2013 October 2013 220 Tons 220 Tons

U2 TB Major j Equipment q p Deliveries Deaerator MSR LP Turbine Rotor

Unit 3 Basemat Unit 3 Basemat in June 2013 Unit 3 Basemat in Oct 2013

U i 3 Basemat Unit B Rebar R b IInstallation ll i Shield Building Rebar, looking Battery Room Rebar , looking North to South west to east

U i 3 Base Unit B mat pour

Unit 2 CA20 Module

  • Approx. 85% of sub-modules have been delivered d li d
  • Assembly is ongoing within the Module Assembly Building (MAB)
  • To date 11 wall sub-modules have been erected on the platen

Toshiba Main Step Up Transformers - 230/26kV Assembly weight with oil - 529,800lbs each Main Tanks Conservator Tanks

  • 3 in service, 1 spare
  • Oil reservoir
  • 12,720 gallons each
  • 730 gallons each
  • Stored Air Filled
  • Stored Air Filled

VC Summer Units 2 and 3 Switchyard

  • Online February 12, 2013
  • Connection of 230kV transmission lines for SCE&G, and Santee Cooper

L Lesson LLearned d

  • C Coordination di ti off groups tto h help l understand d t d ITAAC
  • Strengthening the procedural controls of ITAAC programs

- Roles and responsibilities for groups

- Stakeholder buy in

  • Review of corrective action programs

L Lesson LLearned d

  • U Understanding d t di and d coordination di ti off ITAAC iissues away from site.

- Vendor inspections(NRC and Consortium)

- Vendor corrective actions that have a material effect ff ITAAC

  • Development of a common understanding of what is meant by material effects on an ITAACs acceptance criteria.