MONTHYEARML24311A1872024-11-0707 November 2024 V.C. Summer EDG SDP for Nextera RUG Meeting - 11.7.2024 - Rev. 0 ML24250A1072024-09-0505 September 2024 Pre-Submittal Meeting Slides for VCS COLR Relocation and WCAP-17661 LAR - 9-9-24 ML24102A0212024-04-10010 April 2024 V. C. Summer 2023 Annual Assessment Public Meeting Presentation Slides - April 22, 2024 ML24008A2112024-01-25025 January 2024 Evaluation of Seismic Risk for V. C. Summer Under the Process for Ongoing Assessment of Natural Hazard Information (Poanhi) - January 25, 2024 (Slides) ML24008A2182024-01-25025 January 2024 Seismic Data to Support Public Meeting with Dominion Regarding NRC Staff Evaluation of Seismic Risk at V.C. Summer Generating Station - January 25, 2024 (Tables) ML23313A1292023-11-0909 November 2023 Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application - November 14 Meeting Slides ML23131A4182023-05-25025 May 2023 V.C. Summer Nuclear Station 2022 Annual Assessment Meeting.Pptx ML22115A0502022-04-21021 April 2022 VC Summer, 2021 Annual Assessment Meeting ML20091G7232020-03-31031 March 2020 V.C. Summer 2019 Assessment Meeting Presentation ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML14323A4522014-11-19019 November 2014 V.C. Summer Construction Update ML14266A3912014-09-23023 September 2014 September 23, 2014, Category 1 Public Meeting with V. C. Summer - Presentation Slides ML14232A5372014-08-21021 August 2014 8-21-14 CIP Mtg Slides - FFD and ITAAC ML14219A4762014-08-0707 August 2014 Operating Experience on Initial Test Program ML14106A4762014-04-16016 April 2014 End of Cycle 2013 Public Meeting Memo ML14057A4202014-02-27027 February 2014 Public Meeting 2/27/2014 VCS Construction Update ML14028A4272014-01-23023 January 2014 Vendor Inspection Finding & ITAAC (Pdf) ML13309A8592013-11-0505 November 2013 V. C. Summer Construction Status and Lesson Learned AD Torres ML13170A1302013-06-18018 June 2013 Public Slide - NFPA 805 Transient Combustible Controls ML13170A1192013-06-18018 June 2013 Public Slide - Control Room Evacuation Due to Fire, Based on NFPA 805 ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13098A8042013-03-26026 March 2013 Combined Emergency Plan Review ML12228A6292012-08-16016 August 2012 Report ITAAC Presentation ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML11350A0902011-12-20020 December 2011 Draft VC Summer Public Meeting 20 Dec 2011 ML11242A0502011-08-30030 August 2011 Slides - Licensee Perspective on ITAAC Completion Process NRC Commission Briefing ML1120707792011-07-26026 July 2011 Enclosure 3: Presentation Slides/Handouts ML1115204732011-06-0101 June 2011 Meeting Summary - V. C. Summer - Presentation Slides ML1016705202010-06-17017 June 2010 Fire Protection Screening Criteria - V.C. Summer Nuclear Station ML1012600092010-05-0505 May 2010 Meeting Posters ML1012600102010-05-0505 May 2010 Meeting Slides ML0911000692009-04-17017 April 2009 Summary of Meeting with Public/Open House to Discuss NRC Reactor Oversight Process and the Annual Assessment of the Virgil C. Summer Nuclear Station ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 ML0811405532008-04-23023 April 2008 V. C. Summer Nuclear Station, Slides - Refuel 17 Plans ML0723400122007-08-22022 August 2007 Public Outreach Meeting South Carolina E&G Summer Nuclear Power Plant Combined License Application ML0715806282007-05-31031 May 2007 Enclosure 8 - OBE Exceedance Issues ML0713500662007-05-0202 May 2007 Meeting Handout on RF16 Outage Review V.C. Summer ML0713501092007-05-0202 May 2007 Meeting Handout on Summary of HP Performance During RF16 ML0713501062007-05-0202 May 2007 Meeting Handout on CRDM Canopy Seal Clamp Installation ML0713501022007-05-0202 May 2007 Meeting Handout on RB Tendon/Iwe/Iwl Inspection ML0713500972007-05-0202 May 2007 Meeting Handout on Alternate Safety Power Source - Summer ML0706703232007-03-0101 March 2007 (Westinghouse AP1000) ML0629904782006-10-24024 October 2006 VC Summer, Enclosure to Meeting Summary, September 13, 2006, Meeting with South Carolina Electric & Gas, on Generic Letter 96-06 (TAC M96872) ML0707202262006-06-22022 June 2006 Sce&G VC Summer Site - Site Characterization Visit (Handouts) ML0609405532006-03-20020 March 2006 Meeting Summary - Enclosure 2. Handouts for Meeting with South Carolina Electric & Gas Company Re Results of Root Cause Evaluation for the High Failure Rate on the January 10, 2006, Operator Licensing Initial Written Examination ML0600304352005-12-30030 December 2005 Rii Presentation Revised - RF-15 Outage Information IR 05000395/20050072005-03-10010 March 2005 Final Significance Determination for a Green Finding (NRC IR 05000395/2005007 Virgil C. Summer Nuclear Station) ML0409805332004-03-11011 March 2004 RIC 2004 Presentation - T11 - Alexander Marion - Emergent Technical Topics ML0404902122004-01-28028 January 2004 Handouts from 01/28/04 Management Meeting ML0328101372003-10-0606 October 2003 Presentation Slides for Post-Refueling Outage Meeting 2024-09-05
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24311A1872024-11-0707 November 2024 V.C. Summer EDG SDP for Nextera RUG Meeting - 11.7.2024 - Rev. 0 ML24250A1072024-09-0505 September 2024 Pre-Submittal Meeting Slides for VCS COLR Relocation and WCAP-17661 LAR - 9-9-24 ML24101A0642024-04-22022 April 2024 2023 Annual Public Assessment Meeting Presentation Slides ML24008A2112024-01-25025 January 2024 Evaluation of Seismic Risk for V. C. Summer Under the Process for Ongoing Assessment of Natural Hazard Information (Poanhi) - January 25, 2024 (Slides) ML24008A2182024-01-25025 January 2024 Seismic Data to Support Public Meeting with Dominion Regarding NRC Staff Evaluation of Seismic Risk at V.C. Summer Generating Station - January 25, 2024 (Tables) ML23325A2452023-11-13013 November 2023 Enclosure 2 - Dominion Slides ML23313A1292023-11-0909 November 2023 Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application - November 14 Meeting Slides ML23312A0202023-11-0808 November 2023 Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application-Virtual Meeting Slides ML23131A4182023-05-25025 May 2023 V.C. Summer Nuclear Station 2022 Annual Assessment Meeting.Pptx ML22115A0502022-04-21021 April 2022 VC Summer, 2021 Annual Assessment Meeting ML20091G7232020-03-31031 March 2020 V.C. Summer 2019 Assessment Meeting Presentation ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML18067A1212018-03-15015 March 2018 March 15, 2018, Public Meeting Presentation Regarding NFPA-805 Application ML17087A1542017-03-28028 March 2017 Response to Request for Additional Information on VC Summer Sfpli - Elevation View ML14323A4522014-11-19019 November 2014 V.C. Summer Construction Update ML14266A3912014-09-23023 September 2014 September 23, 2014, Category 1 Public Meeting with V. C. Summer - Presentation Slides ML14232A5372014-08-21021 August 2014 8-21-14 CIP Mtg Slides - FFD and ITAAC ML14219A4762014-08-0707 August 2014 Operating Experience on Initial Test Program ML14057A4202014-02-27027 February 2014 Public Meeting 2/27/2014 VCS Construction Update ML14028A4272014-01-23023 January 2014 Vendor Inspection Finding & ITAAC (Pdf) ML13309A8592013-11-0505 November 2013 V. C. Summer Construction Status and Lesson Learned AD Torres ML13170A1302013-06-18018 June 2013 Public Slide - NFPA 805 Transient Combustible Controls ML13170A1192013-06-18018 June 2013 Public Slide - Control Room Evacuation Due to Fire, Based on NFPA 805 ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13098A8042013-03-26026 March 2013 Combined Emergency Plan Review ML12228A6292012-08-16016 August 2012 Report ITAAC Presentation ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML11350A0902011-12-20020 December 2011 Draft VC Summer Public Meeting 20 Dec 2011 ML11242A0502011-08-30030 August 2011 Slides - Licensee Perspective on ITAAC Completion Process NRC Commission Briefing ML1120707792011-07-26026 July 2011 Enclosure 3: Presentation Slides/Handouts ML1115204732011-06-0101 June 2011 Meeting Summary - V. C. Summer - Presentation Slides ML1016705202010-06-17017 June 2010 Fire Protection Screening Criteria - V.C. Summer Nuclear Station ML1012600102010-05-0505 May 2010 Meeting Slides ML1012600092010-05-0505 May 2010 Meeting Posters ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 ML11216A2292008-12-0202 December 2008 0523 - R504P - Westinghouse Advanced Technology - 07.2 VC Summer Inadvertent Criticality ML0811405532008-04-23023 April 2008 V. C. Summer Nuclear Station, Slides - Refuel 17 Plans ML0723400122007-08-22022 August 2007 Public Outreach Meeting South Carolina E&G Summer Nuclear Power Plant Combined License Application IR 05000395/20075022007-07-30030 July 2007 Summary of Public Meeting - Virgil C. Summer Nuclear Station, to Discuss Significance on Apparent Violation Documented in Inspection Report 50-395-07-502 ML0715806282007-05-31031 May 2007 Enclosure 8 - OBE Exceedance Issues ML0713500662007-05-0202 May 2007 Meeting Handout on RF16 Outage Review V.C. Summer ML0713500972007-05-0202 May 2007 Meeting Handout on Alternate Safety Power Source - Summer ML0713501022007-05-0202 May 2007 Meeting Handout on RB Tendon/Iwe/Iwl Inspection ML0713501062007-05-0202 May 2007 Meeting Handout on CRDM Canopy Seal Clamp Installation ML0713501092007-05-0202 May 2007 Meeting Handout on Summary of HP Performance During RF16 ML0706703232007-03-0101 March 2007 (Westinghouse AP1000) ML0627602452006-09-27027 September 2006 V. C. Summer Nuclear Station RF-16 Outage Information ML0618002632006-09-18018 September 2006 Crack Growth Rates in a PWR Environment of Nickel-Base Alloys from Davis-Besse and V. C. Summer Plants ML0707202262006-06-22022 June 2006 Sce&G VC Summer Site - Site Characterization Visit (Handouts) ML0615106012006-05-23023 May 2006 EPRI HRA Users Group Review of Draft NUREG-1842 2024-09-05
[Table view] |
Text
RF-15 Outage Information Alan Torres Planning and Scheduling
Refuel-15 Goals
- Duration: 35 Days/ Actual 39
- Human Performance Events: < 1/Actual 2
- Recordable Injuries: < 1/Actual 2
Refuel-15 Goals (Continued)
- Significant/Noteworthy Events: 0/1
- Post 100% - 90 Day Capacity: 95.5%
- Dose: 110 REM (to be adjusted based on source term)
- Actual 82rem
Refuel-15 Major Modifications
- RWST Automatic Swapover Logic
- B RHR Pump Improved Shaft Design
- CCW Crosstrain Relief Valve
Refuel-15 Major Modifications
- Install New 115KV Safety Power Feed to XSW-1DX (Initial Work) *
- To Provide for Decreased Core Damage Frequency
Refuel-15 Items of Interest
- Reactor Vessel Visual Inspection
- Pressurizer Nozzle Inspection
- Emergency Feed Piping Cleaning and Inspection
Refuel-15 Items of Interest
- Vendor Completed Root Cause
- Cause was found to be improper chiller operation
- More than one leak was found in one pin
- Flow Validation
- Enhanced Visual Inspection
Main Generator Rewind
Close-fitting slot wedges, with radial filler strips and conforming strips, are used to anchor the bar in place.
The wedges butt end-to-end in the slot. Side ripple springs are provided to suppress bar movement in the core slots.
The side ripple springs exert a sideways force on the bars, while the wedges, fillers and top ripple springs exert a radial force on the bars.
Photo 7 shows the new windings fully installed and painted.
Reactor Coolant Pump Flange Gasket Replacement
Main Flange Leakage during RF14 Main Flange Leakage on B RCP located just below CCW inlet line. Not considered pressure boundary leakage, but is RCS leakage.
Main Flange Bolts are carbon steel and susceptible to Boric Acid corrosion; all other RCP materials are stainless steel.
RCP Internal Components Te eliminate main flange leakage, pump internals must be removed and two gaskets must be replaced.
Main Flange Gasket Locations Thermal Barrier Turning Vane Diffuser Diffuser Adapter
B RHR Pump Modification Brief Overview of RHR Project
- B RHR Pump Modification (RF-15)
- Spacer coupling
- Upper & lower Hub Assembly
- ALARA estimate 2.75 R, Actual 1.246 R
- ALARA estimate 1 R, Actual 416 MR
The Spacer Coupling Upper (Driver)
Hub Assembly Lower (Pump)
Hub Assembly
Steam Generator Inspections
Steam Generators
- No pluggable indications
- No significant wear
- Total sludge removed
- Overall health of generators is excellent
Program Enhancements Refuel-15 Program Enhancements
- ISP-27, Electrical Safety
- FME Controls
- Confined Space Program
- Contractor Controls
RF-15 Performance Improvements
- Operating Experience Books
- Rewarded Behaviors Program Utilize Human Performance Error Reduction Tools
Questions?
V.C. Summer Station Recirculation Sump Design Changes Brad Stokes Design Engineering
Overview
RF-15 Activities
Analysis Results
- ~1400 ft2 Strainer for Each Train
- 9.5 ft3 Fiber Load on the sump
- 2.8 ft3 TempMat
- 6.7 ft3 Latent Fiber (105 lbs latent debris)
- 190 ft2 Unqualified Tape, Placards, Stickers
- Add 30% for Chemical Effects
- Marinite Insulation is not a problem
Analysis Results
- ~900 ft3 RMI (Mirror Insulation) Debris
- ~600 ft3 Transports to the Sump
- Recirculation Sump could completely fill with RMI Debris
- Effectively alters flow patterns in the sump reducing effectiveness of strainer surface area
- ~500 ft3 must be stopped before the sump
CFD Model Break At S/G Cross-over nozzle in Charlie Loop Red Areas will transport Mirror Insulation Foils
Ongoing Analysis Work
- Cumulative Effects Programs
- Placement of RMI Debris Interceptors
- Analysis to determine current position
- Evaluation of Replacement
- Sump Level for break inside the Primary Shield
Refuel 16 Modifications
- Complete Recirculation Sump Strainer Replacement
- 2000 ft2 per train (or more)
- RHR and Spray Pump Strainers Cross-tie
- Replace Pressurizer Cubicle Door
- Block Southern Stairwell of 436 ft
- Remove Toe-Kick Plate on 436 ft
AECL Strainer Designs
RMI Debris Interceptor Water Level 2 ft Perforate Plate or Heavy Screen FLOW 2 ft FLOOR
Preliminary Sketch For Interceptors
Outstanding Issues
- Carbon/Graphite Pump Seals
Summary
- All Modifications, Analyses and Programmatic Changes must be in place before December 31, 2007
- GL 2004-02 response makes NRC commitments to address the issues
- Major Modification planned for RF16
- On going analysis of HHSI throttle valves potentially will result in RF16 modification and SI rebalance
Questions?