Category:Meeting Briefing Package/Handouts
MONTHYEARML24311A1872024-11-0707 November 2024 V.C. Summer EDG SDP for Nextera RUG Meeting - 11.7.2024 - Rev. 0 ML24250A1072024-09-0505 September 2024 Pre-Submittal Meeting Slides for VCS COLR Relocation and WCAP-17661 LAR - 9-9-24 ML24102A0212024-04-10010 April 2024 V. C. Summer 2023 Annual Assessment Public Meeting Presentation Slides - April 22, 2024 ML24008A2112024-01-25025 January 2024 Evaluation of Seismic Risk for V. C. Summer Under the Process for Ongoing Assessment of Natural Hazard Information (Poanhi) - January 25, 2024 (Slides) ML24008A2182024-01-25025 January 2024 Seismic Data to Support Public Meeting with Dominion Regarding NRC Staff Evaluation of Seismic Risk at V.C. Summer Generating Station - January 25, 2024 (Tables) ML23313A1292023-11-0909 November 2023 Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application - November 14 Meeting Slides ML23131A4182023-05-25025 May 2023 V.C. Summer Nuclear Station 2022 Annual Assessment Meeting.Pptx ML22115A0502022-04-21021 April 2022 VC Summer, 2021 Annual Assessment Meeting ML20091G7232020-03-31031 March 2020 V.C. Summer 2019 Assessment Meeting Presentation ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML14323A4522014-11-19019 November 2014 V.C. Summer Construction Update ML14266A3912014-09-23023 September 2014 September 23, 2014, Category 1 Public Meeting with V. C. Summer - Presentation Slides ML14232A5372014-08-21021 August 2014 8-21-14 CIP Mtg Slides - FFD and ITAAC ML14219A4762014-08-0707 August 2014 Operating Experience on Initial Test Program ML14106A4762014-04-16016 April 2014 End of Cycle 2013 Public Meeting Memo ML14057A4202014-02-27027 February 2014 Public Meeting 2/27/2014 VCS Construction Update ML14028A4272014-01-23023 January 2014 Vendor Inspection Finding & ITAAC (Pdf) ML13309A8592013-11-0505 November 2013 V. C. Summer Construction Status and Lesson Learned AD Torres ML13170A1302013-06-18018 June 2013 Public Slide - NFPA 805 Transient Combustible Controls ML13170A1192013-06-18018 June 2013 Public Slide - Control Room Evacuation Due to Fire, Based on NFPA 805 ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13098A8042013-03-26026 March 2013 Combined Emergency Plan Review ML12228A6292012-08-16016 August 2012 Report ITAAC Presentation ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML11350A0902011-12-20020 December 2011 Draft VC Summer Public Meeting 20 Dec 2011 ML11242A0502011-08-30030 August 2011 Slides - Licensee Perspective on ITAAC Completion Process NRC Commission Briefing ML1120707792011-07-26026 July 2011 Enclosure 3: Presentation Slides/Handouts ML1115204732011-06-0101 June 2011 Meeting Summary - V. C. Summer - Presentation Slides ML1016705202010-06-17017 June 2010 Fire Protection Screening Criteria - V.C. Summer Nuclear Station ML1012600092010-05-0505 May 2010 Meeting Posters ML1012600102010-05-0505 May 2010 Meeting Slides ML0911000692009-04-17017 April 2009 Summary of Meeting with Public/Open House to Discuss NRC Reactor Oversight Process and the Annual Assessment of the Virgil C. Summer Nuclear Station ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 ML0811405532008-04-23023 April 2008 V. C. Summer Nuclear Station, Slides - Refuel 17 Plans ML0723400122007-08-22022 August 2007 Public Outreach Meeting South Carolina E&G Summer Nuclear Power Plant Combined License Application ML0715806282007-05-31031 May 2007 Enclosure 8 - OBE Exceedance Issues ML0713500662007-05-0202 May 2007 Meeting Handout on RF16 Outage Review V.C. Summer ML0713501092007-05-0202 May 2007 Meeting Handout on Summary of HP Performance During RF16 ML0713501062007-05-0202 May 2007 Meeting Handout on CRDM Canopy Seal Clamp Installation ML0713501022007-05-0202 May 2007 Meeting Handout on RB Tendon/Iwe/Iwl Inspection ML0713500972007-05-0202 May 2007 Meeting Handout on Alternate Safety Power Source - Summer ML0706703232007-03-0101 March 2007 (Westinghouse AP1000) ML0629904782006-10-24024 October 2006 VC Summer, Enclosure to Meeting Summary, September 13, 2006, Meeting with South Carolina Electric & Gas, on Generic Letter 96-06 (TAC M96872) ML0707202262006-06-22022 June 2006 Sce&G VC Summer Site - Site Characterization Visit (Handouts) ML0609405532006-03-20020 March 2006 Meeting Summary - Enclosure 2. Handouts for Meeting with South Carolina Electric & Gas Company Re Results of Root Cause Evaluation for the High Failure Rate on the January 10, 2006, Operator Licensing Initial Written Examination ML0600304352005-12-30030 December 2005 Rii Presentation Revised - RF-15 Outage Information IR 05000395/20050072005-03-10010 March 2005 Final Significance Determination for a Green Finding (NRC IR 05000395/2005007 Virgil C. Summer Nuclear Station) ML0409805332004-03-11011 March 2004 RIC 2004 Presentation - T11 - Alexander Marion - Emergent Technical Topics ML0404902122004-01-28028 January 2004 Handouts from 01/28/04 Management Meeting ML0328101372003-10-0606 October 2003 Presentation Slides for Post-Refueling Outage Meeting 2024-09-05
[Table view] Category:Meeting Summary
MONTHYEARML24262A1082024-10-11011 October 2024 September 9, 2024, Summary of Public Meeting Regarding Potential License Amendment Request Change to Core Operating Limits Report and Implement WCAP-17661 for V.C. Summer Nuclear Station, Unit No. 1 ML24222A6992024-08-16016 August 2024 August 6, 2024, Summary of Regarding Potential License Amendment Request Change to Surveillance Requirements for Moderator Temperature Coefficient for Millstone, Unit No. 3, North Anna, Unit Nos. 1 and 2, and Summer, Unit No. 1 - ML24124A1272024-05-0606 May 2024 April 22, 2024 Public Meeting Summary - 2023 Annual Assessment Meeting Re Virgil C. Summer Nuclear Station ML24036A2942024-02-13013 February 2024 Virgil. C. Summer Nuclear Station, Unit No. 1 - Summary of January 25, 2024, Public Meeting with Dominion Energy South Carolina, Inc. Concerning Review of New Seismic Hazard Information ML23325A2432023-11-13013 November 2023 Regulatory Conference Summary ML23325A2452023-11-13013 November 2023 Enclosure 2 - Dominion Slides ML23325A2442023-11-13013 November 2023 Enclosure 1 - Attendance List ML23331A7892023-11-0909 November 2023 Nov. 2023 Enviro Scoping Meetings Related to the V.C. Summer Subsequent License Renewal Application Meeting Summary ML23171A9172023-06-20020 June 2023 Summary of Meeting Concerning the V.C. Summer Nuclear Station, to Discuss Annual Assessment for Period Jan 1, 2022 Through December 31, 2022 ML22270A2042022-09-30030 September 2022 Summary of Meeting Regarding a Potential Request to Modify the Reactor Vessel Surveillance Capsule Withdrawal Schedule for VC Summer ML22151A3332022-05-31031 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting Regarding the V.C. Summer Nuclear Station, Docket No. 50-395, Meeting Number 20220449 ML21131A1612021-05-11011 May 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Virgil C. Summer Nuclear Station, Docket No. 50-395; North Anna Power Station, Docket Nos. 50-338 and 50-339; and Surry Power Station, Docket Nos. 50-280 and 50-281, Meeting ML20213B1672020-08-13013 August 2020 July 23, 2020, Summary Regarding Second Pre-Application Meeting to Discuss Proposed Technical Specification Task Force-425 License Amendment Request ML20181A0052020-07-13013 July 2020 June 24, 2020, Summary Regarding Pre-Application Meeting to Discuss Proposed Technical Specification Task Force-425 License Amendment Request (EPID-L-2020-LRM-0049) ML20105A1482020-04-10010 April 2020 Public Meeting Summary Virgil C. Summer Nuclear Station ML19196A2112019-08-0202 August 2019 July 23, 2019, Meeting Summary Regarding National Fire Protection Association 805 Supplement License Amendment Request ML19123A1332019-05-0101 May 2019 Public Meeting Summary - V.C. Summer Nuclear Station, Docket No. 50-395 to Provide Opportunities to Discuss Annual Assessment of V.C Summer Nuclear Station with the Public for Period of January 01, 20018 - December 31-2018 ML19086A0272019-04-12012 April 2019 April 4, 2019, Meeting Summary Regarding Pre-application Meeting to Discuss Two Proposed Relief Requests ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML18068A0272018-03-22022 March 2018 Summary of March 15, 2018, Pre-Application Meeting with South Carolina Electric and Gas Company to Discuss a Future NFPA-805 Amendment (EPID-L-2018-LRM-0015) ML17103A5222017-04-12012 April 2017 Annual Assessment Meeting Summary 2017 ML15126A1962015-05-0505 May 2015 April 16, 2015 Public Meeting Summary - Category 1 - Virgil C. Summer Nuclear Station Units 2 and 3 Annual Assessment ML15119A5102015-04-29029 April 2015 Meeting Summary with Members of the Public Concerning the Annual Assessment of of Virgil C. Summer Nuclear Station, Unit 1, in Blair, S.C ML14106A4762014-04-16016 April 2014 End of Cycle 2013 Public Meeting Memo ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13199A1772013-07-31031 July 2013 Summary, June 20, 2013 Category 1 Meeting with South Carolina Electric and Gas Company, to Discuss Voluntary Fire Protection Risk Initiative Self-Assessment ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13119A4112013-04-29029 April 2013 Summary of Category 3 Public Meeting, Virgil C. Summer Nuclear Station, Unit 1, Annual Assessment ML13098A8442013-04-11011 April 2013 Summary of Meeting with South Carolina Electric & Gas to Discuss Proposed Emergency Plan Changes ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML1120707482011-07-26026 July 2011 July 20, 2011, Meeting Summary Pre-Application Meeting with South Carolina Electric and Gas Regarding General License Independent Spent Fuel Storage Installation Plans (TAC No. L24544) ML11152A0802011-06-14014 June 2011 Summary of March 31, 2011, Meeting with South Carolina Electric and Gas Company to Discuss NFPA-805 License Amendment ML1115204542011-06-0101 June 2011 Summary of Public Meeting with South Carolina Electric & Gas Co., V. C. Summer to Discuss the NRC Reactor Oversight Process and Annual Assessment ML1023804682010-08-26026 August 2010 08/18/10 Summary of Meeting NRC Initial Exam Writer'S Workshop ML1016704282010-06-17017 June 2010 Meeting Summary Notice ML0930005732009-11-0505 November 2009 Summary of September 14, 2009, Public Conference Call to Discuss Responses to Generic Letter 2004-02 Requests for Additional Information ML0923803922009-08-26026 August 2009 08/11-12/2009-Summary of Meeting Re 2009 Us NRC Initial Exam Development Workshop ML0911000692009-04-17017 April 2009 Summary of Meeting with Public/Open House to Discuss NRC Reactor Oversight Process and the Annual Assessment of the Virgil C. Summer Nuclear Station ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 IR 05000395/20075022007-07-30030 July 2007 Summary of Public Meeting - Virgil C. Summer Nuclear Station, to Discuss Significance on Apparent Violation Documented in Inspection Report 50-395-07-502 ML0713500592007-05-11011 May 2007 Summary of Public Meeting with South Carolina Electric & Gas Company to Brief the Licensee'S Post Outage Review of Refueling Outage 16 at Virgil C. Summer Nuclear Station IR 05000395/20070022007-04-30030 April 2007 IR 05000395-07-002; on 01/01/2007 - 03/31/2007 for South Carolina Electric & Gas Company; Virgil C. Summer Nuclear Station, Integrated Inspection Report and Annual Assessment Meeting Summary ML0627605282006-10-24024 October 2006 September 13, 2006, Summary of Meeting with South Carolina Electric & Gas Re Generic Letter 96-06 (TAC No. M96872) ML0627800022006-10-0404 October 2006 Summary for Meeting Between NRC and South Carolina Electric & Gas Company Refueling Outage 16 at Virgil Summer ML0621305672006-08-0101 August 2006 Summary of 07/19 - 07/20/2006 Meeting - 2006 Initial Exam Development Workshop ML0609601222006-04-0303 April 2006 Summary of Meeting with South Carolina Electric & Gas Company to Discuss the Results of the Root Cause Evaluation for the High Failure Rate on the January 10, 2006, Operator Licensing Initial Written Examination ML0601705522006-01-17017 January 2006 Comment Card Responses During January 9 Through 10, 2006, NRC Public Workshop ML0600304322005-12-30030 December 2005 Public Meeting Summary - Oct. 18, 2005 Category 1 Public Meeting-Summer, Docket # 50-395 ML0509704712005-04-0707 April 2005 Meeting Summary - Public Meeting - Virgil C. Summer Nuclear Power Station ML0504901422005-02-17017 February 2005 Summary of January 13, 2005, Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Nuclear Energy Institute (NEI) on Updating the License Renewal Guidance Documents 2024-08-16
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24311A1872024-11-0707 November 2024 V.C. Summer EDG SDP for Nextera RUG Meeting - 11.7.2024 - Rev. 0 ML24250A1072024-09-0505 September 2024 Pre-Submittal Meeting Slides for VCS COLR Relocation and WCAP-17661 LAR - 9-9-24 ML24101A0642024-04-22022 April 2024 2023 Annual Public Assessment Meeting Presentation Slides ML24008A2112024-01-25025 January 2024 Evaluation of Seismic Risk for V. C. Summer Under the Process for Ongoing Assessment of Natural Hazard Information (Poanhi) - January 25, 2024 (Slides) ML24008A2182024-01-25025 January 2024 Seismic Data to Support Public Meeting with Dominion Regarding NRC Staff Evaluation of Seismic Risk at V.C. Summer Generating Station - January 25, 2024 (Tables) ML23325A2452023-11-13013 November 2023 Enclosure 2 - Dominion Slides ML23313A1292023-11-0909 November 2023 Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application - November 14 Meeting Slides ML23312A0202023-11-0808 November 2023 Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application-Virtual Meeting Slides ML23131A4182023-05-25025 May 2023 V.C. Summer Nuclear Station 2022 Annual Assessment Meeting.Pptx ML22115A0502022-04-21021 April 2022 VC Summer, 2021 Annual Assessment Meeting ML20091G7232020-03-31031 March 2020 V.C. Summer 2019 Assessment Meeting Presentation ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML18067A1212018-03-15015 March 2018 March 15, 2018, Public Meeting Presentation Regarding NFPA-805 Application ML17087A1542017-03-28028 March 2017 Response to Request for Additional Information on VC Summer Sfpli - Elevation View ML14323A4522014-11-19019 November 2014 V.C. Summer Construction Update ML14266A3912014-09-23023 September 2014 September 23, 2014, Category 1 Public Meeting with V. C. Summer - Presentation Slides ML14232A5372014-08-21021 August 2014 8-21-14 CIP Mtg Slides - FFD and ITAAC ML14219A4762014-08-0707 August 2014 Operating Experience on Initial Test Program ML14057A4202014-02-27027 February 2014 Public Meeting 2/27/2014 VCS Construction Update ML14028A4272014-01-23023 January 2014 Vendor Inspection Finding & ITAAC (Pdf) ML13309A8592013-11-0505 November 2013 V. C. Summer Construction Status and Lesson Learned AD Torres ML13170A1302013-06-18018 June 2013 Public Slide - NFPA 805 Transient Combustible Controls ML13170A1192013-06-18018 June 2013 Public Slide - Control Room Evacuation Due to Fire, Based on NFPA 805 ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13098A8042013-03-26026 March 2013 Combined Emergency Plan Review ML12228A6292012-08-16016 August 2012 Report ITAAC Presentation ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML11350A0902011-12-20020 December 2011 Draft VC Summer Public Meeting 20 Dec 2011 ML11242A0502011-08-30030 August 2011 Slides - Licensee Perspective on ITAAC Completion Process NRC Commission Briefing ML1120707792011-07-26026 July 2011 Enclosure 3: Presentation Slides/Handouts ML1115204732011-06-0101 June 2011 Meeting Summary - V. C. Summer - Presentation Slides ML1016705202010-06-17017 June 2010 Fire Protection Screening Criteria - V.C. Summer Nuclear Station ML1012600102010-05-0505 May 2010 Meeting Slides ML1012600092010-05-0505 May 2010 Meeting Posters ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 ML11216A2292008-12-0202 December 2008 0523 - R504P - Westinghouse Advanced Technology - 07.2 VC Summer Inadvertent Criticality ML0811405532008-04-23023 April 2008 V. C. Summer Nuclear Station, Slides - Refuel 17 Plans ML0723400122007-08-22022 August 2007 Public Outreach Meeting South Carolina E&G Summer Nuclear Power Plant Combined License Application IR 05000395/20075022007-07-30030 July 2007 Summary of Public Meeting - Virgil C. Summer Nuclear Station, to Discuss Significance on Apparent Violation Documented in Inspection Report 50-395-07-502 ML0715806282007-05-31031 May 2007 Enclosure 8 - OBE Exceedance Issues ML0713500662007-05-0202 May 2007 Meeting Handout on RF16 Outage Review V.C. Summer ML0713500972007-05-0202 May 2007 Meeting Handout on Alternate Safety Power Source - Summer ML0713501022007-05-0202 May 2007 Meeting Handout on RB Tendon/Iwe/Iwl Inspection ML0713501062007-05-0202 May 2007 Meeting Handout on CRDM Canopy Seal Clamp Installation ML0713501092007-05-0202 May 2007 Meeting Handout on Summary of HP Performance During RF16 ML0706703232007-03-0101 March 2007 (Westinghouse AP1000) ML0627602452006-09-27027 September 2006 V. C. Summer Nuclear Station RF-16 Outage Information ML0618002632006-09-18018 September 2006 Crack Growth Rates in a PWR Environment of Nickel-Base Alloys from Davis-Besse and V. C. Summer Plants ML0707202262006-06-22022 June 2006 Sce&G VC Summer Site - Site Characterization Visit (Handouts) ML0615106012006-05-23023 May 2006 EPRI HRA Users Group Review of Draft NUREG-1842 2024-09-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 June 4, 2012 South Carolina Electric & Gas Company ATTN: Mr. Thomas D. Gatlin Vice President, Nuclear Operations P.O. Box 88 Jenkinsville, SC 29065
SUBJECT:
PUBLIC MEETING
SUMMARY
- CATEGORY 3 - VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 ANNUAL ASSESSMENT AND NRC CONSTRUCTION OVERSIGHT OF UNITS 2 AND 3 COMBINED LICENSES
Dear Mr. Gatlin:
On May 24, 2012, the Nuclear Regulatory Commission (NRC) staff met representatives from South Carolina Electric and Gas and members of the public in Blair, South Carolina. The purpose of the meeting/open house session was to discuss the initiation of the construction inspection program of the Virgil C. Summer Nuclear Station, Units 2 and 3 with the public. In addition, the NRC discussed the annual assessment of Virgil C. Summer Nuclear Station, Unit 1 with the public for the period of January 1, 2011 - December 31, 2011.
A public meeting notice was issued on May 8, 2012, and was posted on the NRCs external (public) web page (ML12129A383). The notice included the meeting agenda, which was also available as a handout at the meeting. Attached is a list of attendees and the construction inspection slides presented during the meeting. Copies of the posters used during the Unit 1 discussion are available from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS) at ML12153A177. Copies of the slides presented during the discussion of the construction inspection program are available in ADAMS at ML12152A015 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosures will be made available electronically for public inspection in the NRC Public Document Room or from ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (Public Electronic Reading Room).
T. Gatlin 2 Should you have any questions concerning this meeting, please contact me at (404) 997-4551.
Sincerely,
/RA/
Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos.: 50-395,52-027 and 52-028 License Nos.: NPF-12, NPF-93 and NPF-94
Enclosures:
- 1. List of Attendees
- 2. Construction Inspection Presentation Slides
__ ML12157A045______________ X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRP RII:DRS RII:DCP HQ RII:DRP SIGNATURE /RA By GMcCoy/ /VIA E-Mail/ /VIA E-Mail/ /VIA E-Mail/ /RA?
NAME SNinh NErnestes TSteadham JGaslevic GMcCoy DATE 6/1/2012 6/1/2012 6/4/2012 6/4/2012 6/4/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO T. Gatlin 3 cc w/encl:
J. B. Archie Bruce L. Thompson Senior Vice President Manager Nuclear Operations and Chief Nuclear Nuclear Licensing (Mail Code 830)
Officer South Carolina Electric & Gas Company South Carolina Electric & Gas Company Electronic Mail Distribution Electronic Mail Distribution Donna W. Railey George A. Lippard, III Licensing Technician General Manager Nuclear Licensing Nuclear Plant Operations South Carolina Electric & Gas Company South Carolina Electric & Gas Company Electronic Mail Distribution Electronic Mail Distribution Robin J. White Andy T. Barbee Nuclear Coordinator Director S.C. Public Service Authority Mail Code 802 Nuclear Training Electronic Mail Distribution South Carolina Electric & Gas Company Electronic Mail Distribution Susan E. Jenkins SC Department of Health & Environmental Wayne D. Stuart Control (Acting) General Manager Bureau of Land and Waste Management Engineering Services Electronic Mail Distribution South Carolina Electric & Gas Company Electronic Mail Distribution Sandra Threatt, Manager Nuclear Response and Emergency Robin R. Haselden Environmental Surveillance General Manager Bureau of Land and Waste Management Organizational Development & Department of Health and Environmental Effectiveness Control South Carolina Electric & Gas Company Electronic Mail Distribution Electronic Mail Distribution Kathryn M. Sutton, Esq.
Shaun M. Zarandi Morgan, Lewis & Bockius LLP General Manager Electronic Mail Distribution Nuclear Support Services South Carolina Electric & Gas Company Division of Radiological Health Electronic Mail Distribution TN Dept. of Environment & Conservation 401 Church Street Robert L. Justice Nashville, TN 37243-1532 Manager Nuclear Operations Senior Resident Inspector South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Electronic Mail Distribution U.S. NRC 576 Stairway Road Jenkinsville, SC 29065
T. Gatlin 4 Letter to Thomas D. Gatlin from Gerald J. McCoy dated June 4, 2012
SUBJECT:
PUBLIC MEETING
SUMMARY
- CATEGORY 3 - VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 ANNUAL ASSESSMENT AND NRC CONSTRUCTION OVERSIGHT OF UNITS 2 AND 3 COMBINED LICENSES Distribution w/encl:
C. Evans, RII EICS L. Douglas, RII EICS OE Mail (email address if applicable)
RIDSNRRDIRS PUBLIC RidsNrrPMSummer Resource
CONSTRUCTION INSPECTION PRESENTATION SLIDES MEETING REGARDING THE INITIATION OF THE CONSTRUCTION INSPECTION PROGRAM OF THE VIRGIL C. SUMMER NUCLEAR STATION, UNITS 2 AND 3 THURSDAY, MAY 24, 2012 SLIDE 1 Virgil C. Summer Nuclear Plant Units 2&3 May 24, 2012 1
Enclosure 2
SLIDE 2 Construction Inspection Organization Region II Division Division of Of Construction Inspection Construction Projects Construction Inspection Construction Projects Branches Branch 4 Senior Project Inspector/
Construction Inspectors Project Inspectors Senior Resident Inspector/
Resident Inspectors 2
SLIDE 3
Background
- March 2008; SCE&G Submits Application for VCS 2&3
- March 30, 2012; Combined License (COL)
Issued 3
SLIDE 4 Inspection Program Structure
- Inspections, Tests, Analysis and Acceptance Criteria Inspections (ITAAC) (IMC 2503)
- Verifies that sampled design commitments associated with the license are met prior to fuel load
- Construction Program Inspections (IMC 2504)
- Verifies that programs associated with construction and operation are effective and meet the regulations 4
SLIDE 5 ITAAC Inspections (examples)
- Containment Vessel Bottom Head Welding
- Basemat Concrete Pour 5
SLIDE 6 Construction Program Inspections (examples)
SLIDE 7 2012 Inspections
- Containment Vessel Fabrication
- Nuclear Island Work
- Structural and Mechanical Module Assembly
- Miscellaneous ITAAC and Design Acceptance Criteria Activities
- Type Tests
- ITAAC Related Activities at Vendors
- Reporting of Defects and Non-Compliance
- Corrective Action Program Implementation
- Commercial Grade Dedication Program Review
- Construction QA Implementation 7
SLIDE 8 Inspection Reports
- Contain the results of the inspections
8 SLIDE 9 QUESTIONS?
9