MONTHYEARML24250A1072024-09-0505 September 2024 Pre-Submittal Meeting Slides for VCS COLR Relocation and WCAP-17661 LAR - 9-9-24 ML24102A0212024-04-10010 April 2024 V. C. Summer 2023 Annual Assessment Public Meeting Presentation Slides - April 22, 2024 ML24008A2112024-01-25025 January 2024 Evaluation of Seismic Risk for V. C. Summer Under the Process for Ongoing Assessment of Natural Hazard Information (Poanhi) - January 25, 2024 (Slides) ML24008A2182024-01-25025 January 2024 Seismic Data to Support Public Meeting with Dominion Regarding NRC Staff Evaluation of Seismic Risk at V.C. Summer Generating Station - January 25, 2024 (Tables) ML23313A1292023-11-0909 November 2023 Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application - November 14 Meeting Slides ML23131A4182023-05-25025 May 2023 V.C. Summer Nuclear Station 2022 Annual Assessment Meeting.Pptx ML22115A0502022-04-21021 April 2022 VC Summer, 2021 Annual Assessment Meeting ML20091G7232020-03-31031 March 2020 V.C. Summer 2019 Assessment Meeting Presentation ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML14323A4522014-11-19019 November 2014 V.C. Summer Construction Update ML14266A3912014-09-23023 September 2014 September 23, 2014, Category 1 Public Meeting with V. C. Summer - Presentation Slides ML14232A5372014-08-21021 August 2014 8-21-14 CIP Mtg Slides - FFD and ITAAC ML14219A4762014-08-0707 August 2014 Operating Experience on Initial Test Program ML14106A4762014-04-16016 April 2014 End of Cycle 2013 Public Meeting Memo ML14057A4202014-02-27027 February 2014 Public Meeting 2/27/2014 VCS Construction Update ML14028A4272014-01-23023 January 2014 Vendor Inspection Finding & ITAAC (Pdf) ML13309A8592013-11-0505 November 2013 V. C. Summer Construction Status and Lesson Learned AD Torres ML13170A1192013-06-18018 June 2013 Public Slide - Control Room Evacuation Due to Fire, Based on NFPA 805 ML13170A1302013-06-18018 June 2013 Public Slide - NFPA 805 Transient Combustible Controls ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13098A8042013-03-26026 March 2013 Combined Emergency Plan Review ML12228A6292012-08-16016 August 2012 Report ITAAC Presentation ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML11350A0902011-12-20020 December 2011 Draft VC Summer Public Meeting 20 Dec 2011 ML11242A0502011-08-30030 August 2011 Slides - Licensee Perspective on ITAAC Completion Process NRC Commission Briefing ML1120707792011-07-26026 July 2011 Enclosure 3: Presentation Slides/Handouts ML1115204732011-06-0101 June 2011 Meeting Summary - V. C. Summer - Presentation Slides ML1016705202010-06-17017 June 2010 Fire Protection Screening Criteria - V.C. Summer Nuclear Station ML1012600102010-05-0505 May 2010 Meeting Slides ML1012600092010-05-0505 May 2010 Meeting Posters ML0911000692009-04-17017 April 2009 Summary of Meeting with Public/Open House to Discuss NRC Reactor Oversight Process and the Annual Assessment of the Virgil C. Summer Nuclear Station ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 ML0811405532008-04-23023 April 2008 V. C. Summer Nuclear Station, Slides - Refuel 17 Plans ML0723400122007-08-22022 August 2007 Public Outreach Meeting South Carolina E&G Summer Nuclear Power Plant Combined License Application ML0715806282007-05-31031 May 2007 Enclosure 8 - OBE Exceedance Issues ML0713500972007-05-0202 May 2007 Meeting Handout on Alternate Safety Power Source - Summer ML0713501092007-05-0202 May 2007 Meeting Handout on Summary of HP Performance During RF16 ML0713501062007-05-0202 May 2007 Meeting Handout on CRDM Canopy Seal Clamp Installation ML0713501022007-05-0202 May 2007 Meeting Handout on RB Tendon/Iwe/Iwl Inspection ML0713500662007-05-0202 May 2007 Meeting Handout on RF16 Outage Review V.C. Summer ML0706703232007-03-0101 March 2007 (Westinghouse AP1000) ML0629904782006-10-24024 October 2006 VC Summer, Enclosure to Meeting Summary, September 13, 2006, Meeting with South Carolina Electric & Gas, on Generic Letter 96-06 (TAC M96872) ML0707202262006-06-22022 June 2006 Sce&G VC Summer Site - Site Characterization Visit (Handouts) ML0609405532006-03-20020 March 2006 Meeting Summary - Enclosure 2. Handouts for Meeting with South Carolina Electric & Gas Company Re Results of Root Cause Evaluation for the High Failure Rate on the January 10, 2006, Operator Licensing Initial Written Examination ML0600304352005-12-30030 December 2005 Rii Presentation Revised - RF-15 Outage Information IR 05000395/20050072005-03-10010 March 2005 Final Significance Determination for a Green Finding (NRC IR 05000395/2005007 Virgil C. Summer Nuclear Station) ML0409805332004-03-11011 March 2004 RIC 2004 Presentation - T11 - Alexander Marion - Emergent Technical Topics ML0404902122004-01-28028 January 2004 Handouts from 01/28/04 Management Meeting ML0328101372003-10-0606 October 2003 Presentation Slides for Post-Refueling Outage Meeting ML0327206212003-09-24024 September 2003 Examiner - Vendor Matrix with Phone Number 2024-09-05
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24250A1072024-09-0505 September 2024 Pre-Submittal Meeting Slides for VCS COLR Relocation and WCAP-17661 LAR - 9-9-24 ML24101A0642024-04-22022 April 2024 2023 Annual Public Assessment Meeting Presentation Slides ML24008A2112024-01-25025 January 2024 Evaluation of Seismic Risk for V. C. Summer Under the Process for Ongoing Assessment of Natural Hazard Information (Poanhi) - January 25, 2024 (Slides) ML24008A2182024-01-25025 January 2024 Seismic Data to Support Public Meeting with Dominion Regarding NRC Staff Evaluation of Seismic Risk at V.C. Summer Generating Station - January 25, 2024 (Tables) ML23325A2452023-11-13013 November 2023 Enclosure 2 - Dominion Slides ML23313A1292023-11-0909 November 2023 Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application - November 14 Meeting Slides ML23312A0202023-11-0808 November 2023 Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application-Virtual Meeting Slides ML23131A4182023-05-25025 May 2023 V.C. Summer Nuclear Station 2022 Annual Assessment Meeting.Pptx ML22115A0502022-04-21021 April 2022 VC Summer, 2021 Annual Assessment Meeting ML20091G7232020-03-31031 March 2020 V.C. Summer 2019 Assessment Meeting Presentation ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML18067A1212018-03-15015 March 2018 March 15, 2018, Public Meeting Presentation Regarding NFPA-805 Application ML17087A1542017-03-28028 March 2017 Response to Request for Additional Information on VC Summer Sfpli - Elevation View ML14323A4522014-11-19019 November 2014 V.C. Summer Construction Update ML14266A3912014-09-23023 September 2014 September 23, 2014, Category 1 Public Meeting with V. C. Summer - Presentation Slides ML14232A5372014-08-21021 August 2014 8-21-14 CIP Mtg Slides - FFD and ITAAC ML14219A4762014-08-0707 August 2014 Operating Experience on Initial Test Program ML14057A4202014-02-27027 February 2014 Public Meeting 2/27/2014 VCS Construction Update ML14028A4272014-01-23023 January 2014 Vendor Inspection Finding & ITAAC (Pdf) ML13309A8592013-11-0505 November 2013 V. C. Summer Construction Status and Lesson Learned AD Torres ML13170A1192013-06-18018 June 2013 Public Slide - Control Room Evacuation Due to Fire, Based on NFPA 805 ML13170A1302013-06-18018 June 2013 Public Slide - NFPA 805 Transient Combustible Controls ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13098A8042013-03-26026 March 2013 Combined Emergency Plan Review ML12228A6292012-08-16016 August 2012 Report ITAAC Presentation ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML11350A0902011-12-20020 December 2011 Draft VC Summer Public Meeting 20 Dec 2011 ML11242A0502011-08-30030 August 2011 Slides - Licensee Perspective on ITAAC Completion Process NRC Commission Briefing ML1120707792011-07-26026 July 2011 Enclosure 3: Presentation Slides/Handouts ML1115204732011-06-0101 June 2011 Meeting Summary - V. C. Summer - Presentation Slides ML1016705202010-06-17017 June 2010 Fire Protection Screening Criteria - V.C. Summer Nuclear Station ML1012600102010-05-0505 May 2010 Meeting Slides ML1012600092010-05-0505 May 2010 Meeting Posters ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 ML11216A2292008-12-0202 December 2008 0523 - R504P - Westinghouse Advanced Technology - 07.2 VC Summer Inadvertent Criticality ML0811405532008-04-23023 April 2008 V. C. Summer Nuclear Station, Slides - Refuel 17 Plans ML0723400122007-08-22022 August 2007 Public Outreach Meeting South Carolina E&G Summer Nuclear Power Plant Combined License Application IR 05000395/20075022007-07-30030 July 2007 Summary of Public Meeting - Virgil C. Summer Nuclear Station, to Discuss Significance on Apparent Violation Documented in Inspection Report 50-395-07-502 ML0715806282007-05-31031 May 2007 Enclosure 8 - OBE Exceedance Issues ML0713500972007-05-0202 May 2007 Meeting Handout on Alternate Safety Power Source - Summer ML0713500662007-05-0202 May 2007 Meeting Handout on RF16 Outage Review V.C. Summer ML0713501022007-05-0202 May 2007 Meeting Handout on RB Tendon/Iwe/Iwl Inspection ML0713501062007-05-0202 May 2007 Meeting Handout on CRDM Canopy Seal Clamp Installation ML0713501092007-05-0202 May 2007 Meeting Handout on Summary of HP Performance During RF16 ML0706703232007-03-0101 March 2007 (Westinghouse AP1000) ML0627602452006-09-27027 September 2006 V. C. Summer Nuclear Station RF-16 Outage Information ML0618002632006-09-18018 September 2006 Crack Growth Rates in a PWR Environment of Nickel-Base Alloys from Davis-Besse and V. C. Summer Plants ML0707202262006-06-22022 June 2006 Sce&G VC Summer Site - Site Characterization Visit (Handouts) ML0615106012006-05-23023 May 2006 EPRI HRA Users Group Review of Draft NUREG-1842 ML0609702982006-03-31031 March 2006 NRC Cy 2005 Annual Assessment Meeting, Virgil C. Summer Nuclear Station 2024-09-05
[Table view] |
Text
V.C. Summer Nuclear Station 2022 Annual Assessment Meeting Reactor Oversight Process Nuclear Regulatory Commission - Region 2 May 25, 2023
Meetings Purpose Discuss licensee Address Findings Information performance in and Performance Meeting with a 2022 Indicators Q&A Session
Agenda
Introductions
NRC Mission Statement and Strategic Goals NRC Resident Inspector Program Reactor Oversight Process Review Annual Assessment Summary Question and Answer Session
Introductions
V.C. Summer Resident Inspectors Carey (Mac) Read - Senior Resident Inspector Steve Janicki - Resident Inspector Regional Personnel David Dumbacher - Branch Chief
NRC Mission Statement The NRC licenses and regulates the Nations civilian use of radioactive materials, to provide reasonable assurance of adequate protection of public health and safety, to promote the common defense and security, and to protect the environment.
NRC Strategic Goals
- 1) Ensure the safe and secure use of radioactive materials
- 2) Continue to foster a healthy organization
- 3) Inspire stakeholder confidence in the NRC
Resident Inspector Program Resident inspectors live in the communities they serve Perform onsite inspections Provide daily oversight of plant activities, including the control room Routinely discuss safety concerns with plant personnel and senior management Observe emergency drills and provide support to NRC decision makers for actual emergencies or urgent issues
Reactor Oversight Process (ROP) 1 2
NRC NRC 3
4 Implemented in Involves inspection Executed by each of the NRCs and assessment regional and four regions activities resident inspectors
ROP Framework ROP Assessment Inputs Inspection Findings NRC develops findings from inspections Findings evaluated for safety significance using a significance determination process GREEN Very low safety or security significance finding WHITE Low to moderate safety or security significance finding YELLOW Substantial safety or security significance finding RED High safety or security significance finding
ROP Assessment Inputs Performance Indicators (PIs)
Licensees collect PI data (17 PIs total)
PI data reported to the NRC quarterly PI data evaluated & integrated with inspection findings to develop NRCs assessment of licensee performance GREEN Performance within an expected level WHITE Performance outside expected range YELLOW Minimal reduction in the safety margin RED Signals a significant reduction in safety margin in the area measured
Action Matrix Concept Multiple/Repetitive Licensee Regulatory Degraded Unacceptable Degraded Response Response Performance Performance Cornerstone (Column 1) (Column 2) (Column 3) (Column 5)
(Column 4)
Increasing:
Safety Significance Inspection Management Involvement Regulatory Action
NRC Annual Assessment Summary V.C. Summer Nuclear Station
NRC Annual Assessment Summary Dominion operated V.C. Summer safely and in a manner that preserved the public health and safety and protected the environment.
V.C. Summer Nuclear Station entered the Regulatory Response Column (Column 2) of the NRCs ROP Action Matrix beginning the first quarter of 2022 and remained there for the remainder of the 2022 assessment period.
In addition to ROP baseline inspections, V.C. Summer will receive increased oversight in the form of two supplemental inspections in accordance with Inspection Procedure 95001, Supplemental Inspection Response to Action Matrix Column 2 Inputs.
NRC Inspection Activities V.C. Summer for 2022 Approximately 3,800 hours0.00926 days <br />0.222 hours <br />0.00132 weeks <br />3.044e-4 months <br /> of direct inspection and related activities Resident inspectors onsite performed daily oversight activities and documented baseline inspection results on a quarterly basis Eight regional inspections, including (not all inclusive):
License Renewal Inspection Triennial Fire Protection Inspection Triennial Evaluation of Changes, Tests, and Experiments Inspection Triennial Heat Sink Performance Inspection Cyber Security Inspection
V.C. Summer PIs and Findings January 1 through December 31, 2022 All Performance Indicators were Green (no performance thresholds exceeded)
Four Green findings, one traditional enforcement severity level IV non-cited violation, one greater-than-Green finding, and one White finding
NRC Inspection Findings VC Summer 2022 Inspection Report 2022-002 Severity Level IV - NCV of 10 CFR Part 21(c)(1) for failure to evaluate and report a manufacturing defect in a basic component of a feedwater isolation valve Inspection Report 2022-004 Green finding/NCV for failure to establish adequate procedural controls to ensure that scaffolding erected near safety-related equipment would not adversely affect the performance of that equipment during a design-basis seismic event Inspection Report 2022-401 Three Green findings are documented in this report; the details contain security-related information and are not available for public disclosure.
NRC Inspection Findings VC Summer 2022 (continued)
On October 18, 2022, the NRC issued, Virgil C. Summer - Final Significance Determination of a White Finding and Notice of Violation and Assessment Follow-up Letter (ML22287A184) associated with the failure to identify and correct a condition adverse to quality which resulted in the inoperability of the B emergency diesel generator in January 2022.
On February 2, 2023, the NRC issued, Virgil C. Summer - Final Significance Determination for a Security-Related Greater than Green Finding, Notice of Violation, And Assessment Follow-Up Letter (ML23032A427) associated with an issue that occurred in the third quarter of 2022. The details contain security-related information and are not available for public disclosure.
Getting in Touch with the NRC General information or questions NRC Public Website - www.nrc.gov Region II Public Affairs 404-997-4417 l OPA2.Resource@nrc.gov Report an Emergency 301-816-5100 (collect calls accepted)
Safety Concern or Allegations 1-800-695-7403 l Allegation@nrc.gov
Questions about V.C. Summer?
Senior Resident Inspector - Carey (Mac) Read Carey.Read@nrc.gov l 404.997.5251 Main Office - 404.997.5250
NRC Social Media
https://service.govdelivery.com/accounts/USNRC/subscriber/new
Questions and Feedback Public Meeting Feedback Form:
- 1. Form available during meeting OR
- 2. Electronically https://feedback.nrc.gov/pmfs/feedback/form?meetingCode=20230XXX Nuclear Regulatory Commission l Region II May 25, 2023