Email - from: Williams, Charles R. to: Lake, Louis, Thomas, George, Dated Sunday, January 17, 2010 9:28 Am, FW: 01-18-10 Containment Repair Prokect Level 3 Schedule, Attachments: 01-18-10 Level 3 Rev D - 11x17.pdf
ML102880509
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 01/17/2010
From: Williams C R
Progress Energy Co
To: Lake L F, George Thomas
Office of New Reactors, NRC/RGN-II
References
FOIA/PA-2010-0116
Download: ML102880509 (12)


Text

.1 Senglupta, Abhijit From: Sent: To:

Subject:

Attachments:

Williams, Charles R. [Charles.Williams@pgnmail.com]

Sunday, January 17, 2010 9:28 AM Lake, Louis; Thomas, George FW: 01-18-10 Containment Repair Project Level 3 schedule 01-18-10 Level 3 Rev D -11x17.pdf fyi From: Goering, Calvin Sent: Friday, January 15, 2010 4:00 PM To: Fagan, Paul; Dyksterhouse, Don; Williams, Charles R.; Ortalan, Emin; Miller, Garry; Bell, Robert; Tobin, Larry; Pugh, C-Glenn; Mallner, Aaron; McEwan, Ken

Subject:

01-18-10 Containment Repair Project Level 3 schedule Please find attached a copy of the Containment Repair Project Level 3 schedule as of this morning for your information.

Also, please note that this schedule is now in Progress Reporter and that progress should be reported each day prior to 14:00. If you need to make significant changes or changes that will impact a deliverable, please let Paul Fagan know so he can be prepared to discuss them at the morning schedule review meeting with the Project team.Please notify me of any changes that need to be made as soon they are determined, thanks.Cal Goering CR3 CRT Project Scheduler 352-563-2943 Ext 4186 I P/ýLl CR3 NPC Outage Containment Repair Project -Level 3 Schedule C Decrpon EaryStart ly Rem Dur i Jan Feb Mar Apr t De Parkingtin TM P aine04 1 25 01 08 15 22 01 08 15 22 29 05 Co ntaneiRepaiL gistics~.2 R e gin the DELLOG023 10 3 Lt0 070/9/07 10 2001/18/10 07 01/29/10 17" Continen Repir Root Caus An~alysis-PE Develop Root ..ose DELRCA058 -PE Develop Root Cause Document (AR 10812007*2,0/10 0120113 Docune A"R 372 ) __...... .____________:

)10121/0907 02101/100 S-PIt Develop SupporORefute DELRCA060 -Pit Develop Support/Refute Root Cause 10/25/0907 01/2011002 0 1414 R .......Aveysin Documentation 10/25/0907 01/20/1002 6 -P Analyze Develop &Issue Final Root Cause-Pi1 Analyze, Develop& ssue FinalRoot 1111/0916 01/29/10 60 1413 I I0/Cause Analysis Report 11/15/09 16 01/29/1008 PIt Tone Abaqus Model w" PiI Tune Abaqus Model wC Creep Test Results Creep DELRCA086

~ ueAau oe /CepTS t 12/23/09 14 01/18/10 02 60 2822 Results, Creep Gradient, ASR 12/23/09 14 01/18/1002

~:8 Pit Load Expand Mod, I on )

=DELRCA084 PII Load Expand Model on Abaqus 01/15/10 14 01/17/10 14 48 2705) / ~ ~~-PiI Analyze, Anal isis of ii)* (MPR Detension S mpe & Se DELRCA057 -PIc Analyze, Analysis of MPR Dete.sion 01/17/1014 01/26/1014 109 1349 Scope & Sequence 11101 1261 4 18 14 P ed ) ) ) (91117/10 14 01/26 10 14 ) ) : 10 P Crass Check kbaqus &) i~erlin Models : DELRCA088 PII Cross Check Abaqus & Merlin Models 01/18/10 02 01120110 02 48 2823 10 M Model) ) J i~~0118/10 02 01/20/110 02: 1E Perform Owners Review PPf OwrRioF.Rof Final Root Cause Analysis]DELRO56C Cuase AnalysisRert 01/29/100 01/31/1006 24 1475 Repo01/29/1008 01/31/1008 12 PNSC Review & Approve RoCause De~terona PNSC Review & Approve Root Cause 02/01/1008 02/04/100 36 1463ination Determination 02/01/1008 02/04/1006 Rt13 Rt Canoe Analysis Root Cause Analysis Complete/Approved 38 Complete/Approved MILEST 2 : DELRCAO59M MILESTONE 02/04/1000 02/04/1008 0 2923 02/04/i0 08 02/04/1008

,9oý4 imrentRepair Design gs 1rly 16is~ assAayi'MILESTONE~Cotioet 02/10/10 IE020 /0104 0/0J1 Design Basis Analysis Complete 0211014 02/10/10 14f C2.3et MIETN..Early R.m.04 1: 18 25 01 08 15 22 01 08 15 22 29 05 ACT Descriptlon Early Start Finish Jan Feb Ma Apr Legend: Milestones In-Progress Activity Page 1 of 11 January 15, 2010 03:50:22 PM Containment Repair Project -Level 3 Schedule DELDBA-0016-Detensioning Caic-Finite Element Model 12/27/09 07 01/16/10 14 Description(MPR Calc 0102-0135-04) 24 2581 DELDBA-0018 Detensioning Catc-Conduit Local Stress 12J27i0007 0IiI710 14 48 Analysis (MPR Calc 0102-0135-05)

DELDBA-0012 Detensioning Calc-Concrete Strength & 12127/09 07 01/16/10 16 26 2579 Elastic Modulus (MPR Calc 0102-0135-02)

DELDBA-0014 Detensioning Caic-Tendon Tension (MPR 12127/09 07 01117/10 14 48 2557 Calculation 0102-0135-03)

DELDBA-0020 -Detensioning Calc-Tendon Detensioning 01/00/10 08 01/20/10 14 120 2509 Evaluation (MPR Calc 0102-0135-06)

DELDBA-0005 -Detensioning Calc -Approve Calc 01/18/10 14 01/20/10 14 48 2509 DELDBA-1M Detensioning Calculation Complete 01/20/10 14 01/20/10 14 0 2509 MILESTONE DELDBA-0104 -Containment Bldg CaIc -Incorp Eq Htch 01/08/10 08 01/22/10 08 162 2857 Model Details DELDBA-0100 -Containment Bldg Calc -Finalize 01/20/10 14 01/27/10 14 168 2509 Computer Analysis DELDBA-0101 -Containment Bldg Calc -Compile Calc to 01/27110 14 02/03/10 14 168 2509 be Ready for ReviewNe e2ficat/on DELDBA-0102 -Containment Bldg Calc -Owners 02103110 14 02108/10 14 120 2563 ReviewNenfication DELDBA-0103 -Containment Bldg Calc -Incorporate 02108/10 14 02110/10 14 48 2563 Review Comments & Approve D Jan Feb Mar Apr 04 11 18 25 01 08 15 22 01 08 15 22 29 05 1-Detensionimg Element Model 12127/0907 01/16/10 14 17 Detensioning Cal-onduit I Local Stress Analysis (MPR 12/27/0907 01/17/1014 1 18 Detenionmg Cain-Concrete, Strength & Elastic Modulus 12/27/0907 01/16/1016 1 n Detessionmn Calc-Tendon , Tension (MPR Calcalation 0 12/27/0907 01/17/1014 20 -Detensioning Calc-Tendon iDetenson n ,i n.g Evaluation 01/09/10 08 0.1/20/10 14 21 -Detensioning C alc- q Approve Calc 01/1811014 01/10/10 14 2 Detensioni g Calculation 2 Complete IILESTONE 41/2011014 01/20/1)0 14 2 -Containment Bldg Cain -23 nIho Eq Hnch Model Details 01/08/10 08 01/2211008-Containme it Bldg Calc -Finali7e Coi npler Analysis 01/20/10 14 01/27/10 14-Containment Bldg Calc -Co leCalc to be Ready 1127/10:14 02103/1014-Containment Bldg Caic Owners ReviewNeniifcation 02/03110.14 02/08/1014-Containment Bldg Cain-Incorporate Review 02108/1014 02110/1014 20 Containment Bldg dalc t Compi MILESTON11 2/10/10:14 02/10/1/0 14 04 11 18 25 01 08 15 22 01 08 15 22 29 05 0 Jan Feb Mar Apr DELDBA-2M Containment Bldg Calc Compl MILESTONE 02110/10 14 02110/10 14 0 2563 Legend: Milestones In-Progress Activity Page 2 of 11 January 15, 2010 03:50:22 PM CR3 NPC Outage Containment Repair Project -Level 3 Schedule ACT / 04 11 Early1 25 01 D I Jan Feb Mar Apr Finish~ :14 1 18 25 01 .08 15 F2 01 08 15 22 .j 29 05 DELDESLIM EC Implementation Design Complete MILESTONE 03/0611006 03/0611006 0 2747 DELDES2111M -EC 75218 PH 2 Detension:

Develop Final 01/13110 07 01120/10 14 120 2648 EC "Pkg for final DRB" DELDES2120 -EC 75218 PH 2 Detension:

Inter-Departmental Reviews 01/14/1 07 01118/10 14 72 2672 DELDES2115M -EC 75218 PH 2 Detension:

Mech / Struc -01/14110 07 01/19/10 14 96 2648 Dv DELDES2123 -EC 75218 PH 2 Detension:

Incorp Review 01118/10 14 01/19/10 14 24 2672 Comments DELDES2117 -EC 75218 PH 2 Detension:

Incorp 01/19/10 14 01120/10 14 24 2648 Verification Comments DELDES2125 EC 75218 PH 2 Detension:

Supv Review 01120/10 14 01/20110 18 4 2648 Prior to Final ORB DELDES21250 EC 75218 PH 2 Detension:

Distrib Final 01/20/1018 01/20110 1 26 DRB Pkg for Review DELDES2125R -EC 75218 PH 2 Detension:

Review Final 01/20/10 19 01/24/1019 96 2649 DRS Pkg DELDES2120S EC 75218 PH 2 Detension:

Final DRS 01/24/1019 01/2411021 2 2648 Meeting DELDES21215 -EC 75218 PH 2 Detension:

Incorporate 01124/10 21 01/25/10 09 12 2648 Final DRB Comments DELDES213OZ EC 75218 PH 2 Detension:

MILESTONE-01/25/1009 01/25/1009 0 2648 All Reviews Complete 31 75219 PH 2 Detensior 3 e1l inal EC "Pkg for 0111W10 07 01/20/1014 32 -EQ 75218 PH 2 Detens Inter-Departmental Revii 0 1/ 14/1 07 01/18/1014 3 -EC 75218 PH 2 Detens Mech / StIuc -DV 01/14/10 07 01/19/1014 34 -EC 75218 PH Incorp Review 01/18/10 14 01/-EC 75218 P Incorp Verfic 01/19/1014 0 6 EC 752181 Supv Revie 01/2011014 EC 75218 Distrib Fin;01/20/10 18-38 EC 75218 Review Fir 01/20/1019 E(Fii 01/24/40 -In V01/24/41 E 42 '0 1/2!Defensive:

ýommehts 9/1014 I12 Defensive:

ition Comment 1/20/10.14 H 2 Detension:

oPoior to Final D 01/20/1018 1H 2 Detension:

DRB Pkg for Re 01/20/1019 PH 2 Detensivon 3t ORB Prig 01/24/1019 75218 PH 2 Detensiob:

at ORBqMeening 019 01/24/1021 70219 PH 2 Defensive:

orporatie Final ORB Com 021 01/20/10 09 Z:75216 PH 2 Defensive:

ILESTQNE -All Reviews C 1009 01/25/10 09: 79218l PH 2 Defensive bfain Sopervisor Approval 1009 01/25/10 11: 30o CC Implementatlion DesignomltM0ETN

!~ omplete MLEzSTONE 3106106/1000 0/06/1006 P DELDES21220 EC 75218 PH 2 Detension:

Obtain Supervisor Approval 01/25/10 09 01/25/10 11 2 2648 Carty, Rj 04 11 18 25 01 08 15 22 01 08 15 22 29 05 L eg en d E r S t a rt F in is h R e r u r T F D J a n F e b M a r A p r Legend: Milestones In-Progress Activity_______ _ __ +Page 3 of 11 January 15, 2010 03:50:22 PM CR3 NPC Outage Containment Repair Project -Level 3 Schedule ACT Description

-Early Start Early Re Jan FeTMrFp__________

.Fi, :, :: : 04 11 18 25 01 08 15 22 01 08 15 22 29 05 Finish m r I T I i F , , I I I DELDES21225-EC 75218 PH 2 Detension:

Obtain PGM Approval 01/25/10 11 01/25/10 19 8 2648 DELDES214OZ EC 75218 PH 2 Detension:

MILESTONE 01125110 19 01/25/10 19 0 2648-OK to Start Field Work DELDES21710 EC 75218 PH 2 Detension:

Planning 01/25110 19 01/28/10 19 72 2648 Prepare SC Work Packages DELDES3111M -EC 75219 PH 3 Removal: Develop Final 01/11110 07 01/22/10 15 41 1413 EC Pkg for final Review'EELDES3517M -SC 75497 PH 3 Removal: Review T-Mod 01/12/1014 01/15/1022 8 3173 EC 75497 Conduit Removal EC 75497 PH 3 Removal: Issue T-Mod EC DELDES3519M FrPMApal01/15/10 22 01/17/10 22 46 3173 75497 PGM Approved EC DELDES3521M 754.7 PGM Approved vEC 0171 20/71 2 0. 37 DELDES3115M -EC75219 PH3RemovatMacStSuc-01122/10 15 01/26110 15 96 2829 DEDS10 -EC 75219 PH 3 Removal: 0ELDES3120 -S 51 H3Rmvl01/22110 19 01/26/10 15 96 2629 Inter-Departmental Reviews DELDES3190Z EC 75219 PH 3 Removal: Milestone

-01/22/1019 01/2211015 0 2939 Issued for Final Review DELDES3123 -EC 75219 PH 3 Removal: Incorp Review 01/26/10 15 01/27/10 17 26 2839 Comments DELDES3117 -EC 75219 PH 3 Removal: Incorp 01/26/1016 01/26/10 03 36 2929 Verification Comments 43 -SC 75219 PH 2 Detension:

Obtain POM Approval 0125I1011 01/25/1019 C ,c 75218 PH 2 Detenston:

i -OK to Start'id1/2 i10196 01/25/101?

45 C 75218 PH 2 Detenoon: Itanning Prepare EC Work P 01/2 10 19. 01/2811016 4-EC 75219 PH 3 Removal: r Deveo n ESC "Pkg for 01/1111007 i01/2210 15 S-C 75497 PH 3 Removal: Review T-Mod EC 75497 01/1211014 01/15/1022 SC 75497 PH 3 Rem oal: I4 ssue T-Mod EC 754 7 For.01/15/10 22 01/1711022 s49 ;C 75497 PH 3 ve-o C 5497 1/17/1022 " 01117/1022 EC 75 19 PH 3 Removal Mech / Itruc -oV 01/22/10 1, 01,26/10 15 51 -EC 75 19 PH 3 Removal: Inter-D partmettal Reviews 01/22/10 1 01/26/10 15.E2 SC 75ý 19 PH Removal.Midesto ie -Issed for Final R;i 22/10 1. 01422/10 15 53 -EC 76219 PH 3 Removal sncorp Review Comments ca i i0112z6110 01127/10,.17 54 -EC 75219 PH 3 Removal sIncorpl eVfncation Comment 01) 6/1015 01/20110 03-SEC 75219 PH 3 Removal: Supv Review Prior to Final D 01/2110 03 01/28/10 07 04 11 18 25 01 08 DELDES3125 EC 75219 PH 3 Removal: Supv Review 01/28/1003 01/28/1007 Prior to Final DRB 4 2829 15 22 01 08 15 22 29 05 Jan Feb Mar Apr Legend: Milestones

-0 In-Progress Activity Page 4 of 1V January 15, 2010 03:50:22 PM CR3 NPC Outage Containment Repair Project -Level 3 Schedule#spr TACT Description Early StartFinis.

RemF urs :TF D Jan Feb Mar Apr 04 11 18 25 01 08 15 22 01 08 15 22 29 05[ I r I I r [ r I I I I I ? I I I r r , 1 1 1 1 ; r l i i i i i i i i ....i ............... ..............L ....DELDES3125D EC 75219 PH 3 Removal: Distdb Final I DRB Pkg for Review 2829 01128110 07 01/28/10 08 DELDES3125R -EC 75219 PH 3 Removal: Review Final 01/28110 08 01130/10 02 42 2829 DRB Pkg DELDES31205 EC 75219 PH 3 Removal: Final DRB 01/30/1002 01/30/1004 2 2828 Meeting DELDES31215 -EC 75219 PH 3 Removal: Incorporate 01/30/10 04 01/31/10 04 24 2829 Final DRB Comments DELDES313OZ EC 75219 PH 3 Removal: MILESTONE

-01/31/10 04 01/31110 04 0 2829 All Reviews Complete EC 75219 PH 3 Removal: Obtain 01/31/10 04 01/31/10 06 2 2829 DELDES31220 Supervisor Approval DELDES31225 -EC 75219 PH 3 Removal: Obtain PGM 01/31/10 06 02/01/10 06 24 2829 Approval EC 75219 PH 3 Removal: MILESTONE

-02/01/10 06 02/01/10 06 0 2829 DELDES3140Z PGM Approval-EC 75219 PH 3 Removal: Planning 02/01/10 06 02/04/10 06 72 2829 DELDES31710 Prepare EC Work Packages-EC 75220 PH 4 Replacement:

Develop 01/13/1010 01/27/1018 104 2708 DELDES4111M 70% EC "Pkg for Design Challenge DELDES4-0006 -EC 75220 PH 4 Replacement:

AREVA 01/1/10 11 02/04/10 14 480 2806 Design Radial Reinforcement-EC 75220 PH 4 Replacement:

AREVA DELDES4-0008 Design Additional Reinforcement for Delan 01/15/10 12 02/07/10 14 552 2734 Area 58 EC 75219 PH 3 Removal: Dintnb Final DRB Pkg for Re 01/28/1907 01/28/10 08 07 -EC 75219 PH 3 Review Final DRB Pkg 01/28/l1 08 01/30010 02 58 !EC 75219 PH l3 Removal: i Final ORB Meeting 01/30/1002 01/30/1004 09 -EC 75219 PH 3 Removal.Incorporate Final DRB Coin 01/01/10 04 01/31110 04 68 BC 75219 PH 3 Removal: MILESTONE "All Reviews C 04 01/31/1004 6 EC 75219 PH 3 Removal-8 Obtain Supelrvisor Approval 0*11/10 04 01/31/1006-EC 75219 PH 3 Removal:.T Obtain PGM Approval 11/31/110 06 02/01/10 068 83 EC 75219 PH 3 Removal: 6 MILESTONE

-PGM Approv 2/01/10 06 02/01/10 08i-EC 75219 PH 3 Removal: Planning Prepare EC Work P 02/01/1006 02/04/10 086 n o4 i AI i o050 , 65 _-EC 75220 PH 4 01/13/10 i10 01/27/10 18 48 -C75220 PH 4 Re lacement:

AREV, 15/111o 11 021040 i01/10/1012 02/07/10 88.EC 75220 PH 4:68 'EC 7S220 PH 4 Re lacement:

AREV.DELDIES4-0009-EC 75220 PH 4 Replacement:

AREVA Revise Existing & Create New Reinforcement Dwg 01/15/10 12 02/07/10 14 552 2734 ACT ...... .. Early Start r TF 04 11 18 25 01 08 15 22 01 08 15 22 29 05Dscriptlonie.

Start ;:. : :Rem Our-T ~, j Finish Jan Feb Mar Apr Legend: Milestones In-Progress Activity Page 5 of 11 January 15, 2010 03:50:22 PM CR3 NPC Outage Containment Repair Project -Level 3 Schedule D Jan Feb Mar Apr ACT Decito al tr Early ie bu TP 04 11 18 25 01 08 15 22 01 08 15 22 29 05_____04 ll 25 0,,1 22 01*. , ,, , ., , DELDES4-0002-EC 75220 PH 4 Replacement:

SGT Revise Formwork Spec CR3-C-0002 01/15/10 12 02102/10 02 420 2745 DELDES4-0001 -EC 75220 PH 4 Replacement:

SGT 01115/10 12 0210311002 444 2721 Revise Formwork Calc SOB-0021-EC 75220 PH 4 Replacement:

AREVA DELDES4-0004 Revise Concrete Spec CR3-C-0003&Veri%

01/15/10 12 02/04110 14 480 2205 Mix Dsn EC 75220 PH 4 Replacement:

AREVA DELDES4-0011 Review & Revise Calc S06-0007 for Liner 01/15110 12 02/01/10 04 398 2743 Plate DELDES4-0010 EC 75220 PH 4 Replacement:

AREVA 01115/10 12 02101110 04 398 2743 Issue Reinforcement CaIlcJDwgs EC 75220 PH 4 Replacement:

Owner DELDES4-0005 Accept Revised Concrete Spec 01/15/10 13 02125/10 14 504 2205 CR3-C-0O03 DELDES411IM3 EC 75220 PH 4 Replacement:

Receive 01/27/1014 01/27/1016 2 2700 Preliminary MPR Analysis Input DELDEI1 SM -EC 75220 PH 4 Replacement:

Mech / 01/27/10 16 02101/10 14 110 2076 Struc -70% DV DELDES4120 -ECr75220 PH 4IReplacementa s 01027/10 16 02101/10 14 118 2876 DELDES4-0000 EC 75220 PH 4 Replacement:

Receive 01/29/10 08 01/29/10 10 2 3041 Desge Input from Pi1 Rent Ceause Anralysis012/00 12/010 2 34 EC 75220 PH 4 Replacement:

Owner DELDES4-0012 Accept Revised Calc S06-0007 for Liner 02/01/10 04 02103/10 04 48 2743 Plate DEDS-07 EC 75220 PH 4 Replacement:

Owner DELDES4-OO07 Accept New Reinforcement DesionCaIc 02/01/10 04 02f03/10 04 48 2743 F^^ -,EC 7520P 60 Re ý laeet: ST R w'ise;=01/15/1 12e 02/021012'70 75220 PH 4 Relacement:

sr S PT Rin 01/10/10 12 02.03110 2 71 EC 75220 PH4 S Re laement AREVA 01/15/10 12 02104110 4 i01/15/tO 12 73 EOC 75220 PH 4 Re Owne 4 02'2/1 4 EC 4 Repfacement:

Receive 1/2711014 01/27/1016 06-EC 70220 PH 4 i e 2ce .mevt: Mach I/ Struc -(1/27/10.16 02101/10 14 L7-EC 75220 PHd4 Re lacement: 1/27/10,16 02101/1014 78 EC 75220 PH 4 Replacement:

Receive 01/2/10 08 01/29/10 10 EC 75220 PH 4 Replacement Owner Accept:02101/1004 02/03/10041 00 EC 75220 PH 4 Replacement:

Owner Accept 102/01/1004 1 02/03/10041 01 -EC 75220 PH 4 Replacement:

Incorp 70%02/01/1014 02102110 14 DELDES4117-EC 75220 PH 4 Replacement:

Incorp 7094 02/01/10 14 021O2110 14 Verflcation Comments 24 2878 A D il.ry 0 11 18 25 01 08 15 22 01 08 15 22 29 05 ACT Description Early'Start .Pr'l Rem Dur "rTF.a.l..tart Finish.m..r.T...

D Jan Feb Mar Apr Legend: Milestones In-Progress Activity Page 6 of 11 January 15, 2010 03:50:22 PM CR3 NPC Outaqe Containment Repair Project -Level 3 Schedule-o arlyStartE ,OR uF , Jan Feb Mar Apr ACT Remsce'tTF>

Ea4. Star 18s 25, 01 08 1 22 01 08 15 22 29 0 DELDES41207 EC 75220 PH 4 Replacement:

70% Desigr 02J01/10 14 02/01/10 16 Challenge Meeting 2 2876 EC 75220 PH 4 Replacement:

Owner DELDES4-0003 Accept Formwork Spec CR3-C-0002

& 02/03/1002 02/04/1002 24 2721 Calc S0O-0021 DELDES4123 -EC 75220 PH 4 Replacement:

Incerp 7094 02107/1014 02100/1014 24 2734 Review Comments DELDES4190Z EC 75220 PH 4 Replacement:

Milestone

-02107/10 14 02107/10 14 0 2734 Issued for 70% Review DELDES4I11M1 EC 75220 PH 4 Replacement:

Receive 02110/1014 02110/1016 2 2063 Approved MPR Analysis nput DELDES4111M2 -EC 75220 PH 4 Replacement:

Develop 02/17/10 13 02125/10 14 193 2205 Final EC "Pkg for final ORB" DELDES4120A -EC 75220 PH 4 Replacement:

Final 02125/10 14 03/01/10 15 97 2209 Inter-Departmental Reviews DELDES4115M1 -EC 75220 PH 4 Replacement:

Final Mech 02/25/10 14 03/01/10 15 97 2205/ Struc -DV DELDES4123A -EC 75220 PH 4 Replacement:

Incorp Fina 03/01/10 15 03/02/10 10 24 2209 Review Comments DELDES4117F -EC 75220 PH 4 Replacement:

Incorp FinE 03/01/10 15 02102110 15 24 2205 Verification Comments DELDE54125 EC 75220 PH 4 Replacement:

Supv 03102/10 15 03102/10 19 4 2205 Review Prior to Final DRB DELDES4125D EC 75220 PH 4 Replacement:

Distrib Final 03102/10 19 03/02/10 20 1 2205 DRB Pkg for Review 82 EC 75220 PH 4 i : i Replacement:

70% DesIgn 02101/1014 02/01/1016 EC 70220 PH 4 Replacement:

Owner Accept 0210311002 02/04/1002 e -EC 752201PH 4 Replacement:

lncerp 701W-02/07110 14 02108/10 14 60 SC 75220 PH 4 i Replacement:

Milestone 42/07/1014

02107/1014 1 EC 75220 PH 4 96 Replacement:

Receive 02/10110:14 0210/10 16 2 -EC 75220 PH 44 r Repaemee Develop Final 0 7/1 0I 02/25/10 14 88 EC 75220 PH 4 Replacem.ent:

Final 02125/10 14 03101/1015 6 SC 70230 PH 4 Relacement n Final Mech /02125/1014 03/01/1015 90 -EC 75220 PH 4 Replacement:

Incorp Final 03/01/10 15 03/02110 15 91-SC 75220 PH 4 1Replacement:

Incemp, Final 03101/1015 03/021101 92 EC 75220 PH 4 Replacement:

Supv Review 03102/1015 03/02110.19 93 EC75220PPH 4 Replacement:

Distab Final 03/0211019 02102/1020 94 EC 75220 PH 4 Replacement:

Review Final 03/0211020 03/03/10'20 DELDES4125R-EC 75220 PH 4 Replacement:

Review 03/02/10 20 03/03/10 20 Final ORB Pkg 24 2205 AtEarly<K' Ru 18 0425 01 08 15 22 01 08 15 22 29 05-:;:: Early Stare : F.inish Rem Dur~i~" Finish D' Jan Feb Mar Apr Legend: Milestones In-Progress Activity Page 7 of 11 January 15, 2010 03:50:22 PM CR3 NPC Outage Containment Repair Project -Level 3 Schedule De a Jan Feb Mar Apr AC Dý-. rptro, Ealyttar Earl Rem T'F I....-Early Remi ur TF 04 11 18 25 01 08 15 22 01 08 15 22 29 05__________i______________i__i____I_*_______i r rr i__.______ii________

i __ri_____*______

L I DELDES41205 EC 75220 PH 4 Replacement:

Final DRB 03/03/10 20 03103/10 22 Meeting 2 2205 DELDES41215 -EC 75220 PH 4 Replacement:

IncorporatE 03103/10 22 03104/10 22 24 2205 Final DRB Comments DELDES413OZ EC 75220 PH 4 Replacement:

MILESTONE

-All Reviews Complete 03/04/1022 03104/1023 0 2200 DELDES41220 EC 75220 PH 4 Replacement:

Obtain 03104110 22 03105/10 06 8 2205 Supervisor Approval DELDES41225 -EC 75220 PH 4 Replacement:

Obtain 03/05/10 06 03/06/10 06 24 2205 PGM Approval DELDES41710 EC 75220 PH 4 Replacement:

Planning 03106110 06 03/09/10 06 72 2205 Prepare EC Work Packages DELDES4140Z EC 75220 Replacement MILESTONE

-03/06/1006 03/06/1006 0 2205 PGM Approval DELDES51005 EC 75221 PH 5 Retension:

Prep / Cplt 01/1/10 07 01119110 09 2 3234 Validabon Plan w/Supv DELDES51OZ EC 75221 PH 5 Retension:

MILESTONE 01/19/10 07 01/19/10 07 0 3234"Start Project DELDES51008 EC 75221 PH 5 Retension:

Develop 01/19/10 09 01/19/10 11 2 3234 Project Tm / Kick-Off Mtg DELDES51020M -EC 75221 PH 5 Retension:

Develop Draft 01/19/10 11 01/23/10 17 102 3234 Pkg for Conceptual DRB DELDES51025 EC 75221 PH 5 Retension:

Distribute 01/23/10 17 01/23/10 18 1 3327 Conceptual 70% Pkg for Review EC 75220 PH 4 Replacement:

Final DRB Me 03/03/1020 03/03/1022 96 -EC75220 PH 4 Replacement Incorporate 03/03/1022 03/04/1022 97 EC 75220 PH4 1 i Replacement:

MILESTONE

-t3104110 22 03/04/1022 98 EC 75220 PH 4 Replacement:

Obtain 03/04/10 22 03/05/1006 99 -EC 75220 PH 4 Replacement:

Obtain PGM A 03/05/10 06 03/06/10 06 0, EC 75220 PH 4 o Replacement:

Planning 0310611006 03/09/1006 101 EC 75220 Replacement MILESTONE-PGM Approv 1%/06/10 06 03/0/10 06 C1020 75221 PH 5 Reterwion:

Prep / Cplt Validation Plan w/01/19/1007 01/19/10 99 1030 75221 PH 5 Retermsion:

i MILESTONE

-Start Projct 1/19/1007 01/19/1007 104 EC 75221 PH 5 Retertsion:

Develop Project Tm /01/19/1009 01/19/1011 105 E-c 75221 PH 5 Retehsion:

Develop Draft Pkg for: 01119/1011 01/23/1017 1060075221 PH 5 Retension:

Distribute Conceptual 70%01/23/1017 01/23/1018 107 -EC 75221 PH-5 Retension:

Develop 70% EC "Pkg" 01/23/1017 01/26/1017 DELDES5111M

-0EC75221 PH 5 Retension:

Develop 70% 01/23/10 17 01/26/10 17 E1 "Pkg" 72 3234...............

_ __. ..................

_ __, _ __...........

__..............

... .........

........... , , , ' i ......'... ..............

i'.. .l '.. ...' l..... ; ...... ...... ;..... .....i ......; ..ACT * :Description Early Start Early 04 1 18 25 01 08 15 22 01 08 15 22 29 05 Fiis Rem Du TI D Jan Feb Mar Apr Legend: Milestones In-Progress Activity Page 8 of 11 January 15, 2010 03:50:22 PM CR3 NPC Outage Containment Repair Project -Level 3 Schedule:at F:37 Jan Feb I Mar Apr ACT Description Early Start Fin;ish R~em r TF~04 11 18 25 01 08 15 22 01 08 15 22 29 05 DELDES51027-EC 75221 PH 5 Retension:

Review Conceptual 70% Pkg 01/23/10 18 01/26/10 18 72 3327 EC 75221 PH 5 Retension:

Conceptual 01/26110 16 01/26/10 18 2 3320 DELDES51030 DRB Meeting DELDES5I20 -EC 75221 PH 5 Retension:

01/26/10 17 01130/10 17 96 3234 Inter-Departmental Reviews DELDES5115M -EC 75221 PH 5 Retension:

Mech/Struc-01/26/10 17 01/30/10 17 96 3234 DV DELDES5190Z EC 75221 PH 5 Retension:

Milestone

-01/26/10 18 01/26/10 18 0 3329 Issued for 70% Review EC 75221 PH 5 Retension:

MILESTONE

-3329 DELDES5120Z Conceptual ORB Mtg CpltI Waived 01/26/1018 01/26/1018 0 DELDES5122 EC 75221 PH 5 Retension:

70% Design 01/26/10 18 01/26/10 20 2 3327 Challenge Mgt DELDES5123 -EC 75221 PH 5 Retension:

Incorp Review 01/30/10 17 02/02/10 18 73 3234 Comments DELDES5117 -EC 75221 PH 5 Retension:

Incorp 70% 01/30110 17 02/02/10 18 73 3234 Comments DELDES5125 EC 75221 PH 5 Retension:

Sup, Review 02/02/1010 02/02/1022 4 3234 Prior to Final DRB DELDES51250 EC 75221 PH 5 Retension:

Distrib Final 02/02/1022 02/02/1023 1 3234 DRB Pkg for Review DELDES5125R -EC 75221 PH 5 Retension:

Review Final 02/02/10 23 02/08/10 13 134 3234 ORB Pkg 108 -EC 75221 PH 5 Retension' Review ConCeptual 70% PKq 01/23/1018 01/2611018 EC 75221 PH 5 Retension:

Conceptual ORB Meeting 01/26/1010 01/26/1018 1 1 0 -EC 70221 PH 5 Retrnsion:

Inter-nepartmental Reviews 01/26/10 12 01/30/1017 E-C 70221 PH 5 Retqnsion:

Mech 4 Struc -DV 01/26/10 17 01/30110.17 EC112 C75221 PH 5 Retension:

Milestone

-Issued tor 70% R Sl/26/10 16 01/26/1018 E113 C 75221 PH 5 Retension:

  • MILESTONE

-Conceptual 1/26/10 18 01/26/10,18 E114 C 75221 PH 5 Retepsion:

70% Design Challenge Mgt 01/26/1010 01026/10:20 EC 75221 PH 5 Retension ncorp Review Comments 01,30/10 17 02/02/1018-EC 75221 PH 5 Retension:

116 ,ncorp 70% Comments 01V30/10 17 02/02/10 18 EC 75221 PH 5 Retension:

Supv Review Prior toiFinal D 02/02/10 10 02/02/1022 E116 C 75221 PH 5 Retension:

Distrib Final ORB Pkg for Re 02/02/1022 02/02/1023 E11 -SC 75221 PH 5 Retension:

Review Final ORB Pkg 02J02/1023 02/0a/1013 E1 SC 75221 PH 5 Retensibn:

Final ORB Meeting 02/08/1013 02/06/1010 DELDES51205 EC 75221 PH 5 Retension:

Final ORB D Meeting 02/08/10 13 02/08/110 15 2 3234 I -----------

ACT Description Early Start Early' Rem Our :TF Fints h 04 11 18 25 01 08 15 22 D Jan Feb I 01 08 15 22 29 05 Mar Apr Legend: Milestones In-Progress Activity January 15, 2010 03:50:22 PM Page 9 of 11 CR3 NPC Outage Containment Repair Project -Level 3 Schedule D Jan Feb Mar Apr Decrpton Ealystrt Early Rem urT A F T i snisho m Er 04 11 18 25 01 08 15 22 01 08 15 22 29 05 121 -EC 75221 PH 5 Retension:

DELOES51215 -EC 75221 PH 5 Retension:

Incorporate 02/0810 15 02109/10 15 24 3234 Incorporate Final ORB Corn Final ORB Comments 02/08/10 15 02/09/10 1$2 EC 75221 PH 5 Retension:

DELDES5130Z EC 75221 PH 5 Retension:

MILESTONE-0209101 02091015 0 3234 MILESTONE -All Reviews C All Reviews Complete 02/0911015 02/09/1 0i15 EC 75221 PH 5 Retension:

Obtain Supemrvsor Approval DELDES51220 EC 75221 PH 5 Retension:

Obtain 02/09/10 15 02/09/10 23 0 3234 p Supervisor Approval 02/09/1015 0209/1023 124-EC 75221 PH 5 Retbnsion:

Obtain POM Approval ELDES51225 -EC 75221 PH 5 Retension:

Obtain PGM 02/09/10 23 0211010 23 24 3234 Approval 02109/1023 02110/1Q23 125 EC 75221 PH 5 Retension:

MILESTONE

-PGM Appron, ELDES5140Z SEC 75221 PH 5 Retension:

MILESTONE

-02110/10 23L02110t1023 0p3234 PGM Approval 0212/10/10 23 02.010/310 23 3 126 SC 75221 PH 5 Retension:

DELDES51710 SC 75221 PH 5 Retension:

Planning 0211011023 02113/1023 72 3234 Planning Prepare EC Work P Prepare SC Work Packages 02/10/1023 02113/1023 Containment Repair Contracting ISubcontracting IProcurntent T 128 Contracting/Sulbcontrading/

DELCONL Contracting/Subcontracbng/Proc.rement 02/08/1017 02108/1017 0 3360 Pr.c.rementComplete MILE.pa te MILESTONE

-12/0/10 17 02108/1011 Containment Repair Subiontractin-Award Hydro-Demotiron 130 Contract DELCON09 -Award Hydro-Demolition Contract 12104/09 19 01/16/10 14 24 3277 mim 12/04109 19 01/16/1014 01 Award Hydro-Demolition 1.Contract Comp! MILESTON!DELCON09M Award Hydro-Demolition Contract Compl 01/16/1014c01/16/1014O0 3277 MILESTONE 0116/10 14 0111610 14 0 32771/16/1014 132 -Award Batch Plant Contract DELCON11 -Award Batch Plant Contract 12104/09 19 02108/10 17 579 3082 i 12/0410919 02/08/1017 1 3 Award Batch Plant Contract DELCON11M Award Batch Plant Contract Compl 0 1 3 133 Compl MILESTONE MILESTONE 02/08/10 17 0208/10 17 0 308220/10 17 F P DELTST06 Perform Concrete Scan / Bo/ng 04/06/10 20 04/08/10 20 48 2205 13e 04/06-, -"El" 04 11 18 25 01 08 15 22 01 08 15 22 29 0 ACT -Description Early Start Early 0em4u 111T81F2 010 s2 90-a F D Jan Feb Mar Apr Legend: Milestones In-Progress Activity Page 10 of1V January 15, 2010 03:50:22 PM CR3 NPC Outage Containment Repair Project -Level 3 Schedule ACT D E S El.r D Jan Feb Mar Apr Finish, 04 11 18 25 01 08 15 22 01 08 15 22 29 05 i i j136, DELTST03 Interface Perform ILRT Test 04/06/10 20 04/08110 20 48 2205 0 a 04106, Interface Testing/ILRT Complete 04/08/1020 04100/1020 0 2373 DELTSTL1M MILESTONE 0 2 0 DELCLOL12M Interface Plant Start-up Complete 4 20 04/10/1020 0 2320 MILESTONE C entea r Plant Startup &est ni DELIMP2-0000 Interface Startup to Mode 4 04/08/10 20 04/10/10 20 48 2205 0 DELCLOO-0000 Interface Startup to Mode 1/On-line 04/10/10 20 04/15/10 20 120 2205 ATDobcripflan

~ Early Start Ealy Rem Du F04 11 18 25 0 08 15 22 01 08 15 22 29 05: Finish D Jan Feb Mar Apr Legend: Milestones In-Progress Activity_____.____-____.__....