Letter Sequence Draft Other |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: 3F0112-11, Corrections to the Extended Power Uprate LAR 309 Vendor Affidavit and Technical Report, 3F0113-08, Attachment D: ANP-3195(NP), Revision 0, Response for Crystal River Unit 3, EPU Licensing Amendment Report NRC Reactor Systems Branch Requests for Additional Information (Non-Proprietary) and Attachment E: Location of Reactor Systems RAI Re, 3F0712-03, Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip, 3F0912-01, ANP-3156 Np, Crystal River 3 EPU Boric Acid Precipitation RAI Responses, Attachment C, 3F1011-08, ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip, 3F1112-02, 17877-0001-100, Rev. 1, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment, Task 1, Page 174 of 250 Through Page 250 of 250, ML11259A012, ML11300A226, ML11342A195, ML12031A032, ML12053A231, ML12107A068, ML12202A734, ML12205A357, ML12205A358, ML12240A119, ML12255A409, ML12262A385, ML12314A391, ML12314A392, ML12314A393, ML13032A540, ML13170A215
|
MONTHYEARML11167A1072011-05-0606 May 2011 Request for Additional Information Required for the Development of Confirmatory LOCA and non-LOCA Models for the CR-3 Extended Power Uprate Project stage: Request 3F0611-02, Attachments 1, 2 & 3, 4 & 6 Crystal River Unit 3, License Amendment Request 309, Revision 0 Attachment 1, Description of Proposed Change, Background, Justification for the Request, Determination of No Significant Hazards Considerations2011-06-15015 June 2011 Attachments 1, 2 & 3, 4 & 6 Crystal River Unit 3, License Amendment Request 309, Revision 0 Attachment 1, Description of Proposed Change, Background, Justification for the Request, Determination of No Significant Hazards Considerations Project stage: Request 3F0711-07, Clarifications for Trace Confirmatory Model Development for Extended Power Uprate2011-07-0505 July 2011 Clarifications for Trace Confirmatory Model Development for Extended Power Uprate Project stage: Request 3F0811-04, Response to Request for Additional Information to Support NRC Probabilistic Risk Assessment Licensing Branch Acceptance Review of the CR-3 Extended Power Uprate LAR2011-08-11011 August 2011 Response to Request for Additional Information to Support NRC Probabilistic Risk Assessment Licensing Branch Acceptance Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0811-02, Response to Request for Additional Information to Support NRC Balance of Plant Branch Acceptance Review of the CR-3 Extended Power Uprate LAR2011-08-11011 August 2011 Response to Request for Additional Information to Support NRC Balance of Plant Branch Acceptance Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0811-01, Response to Request for Additional Information to Support NRC Instrumentation and Controls Branch Acceptance Review of the CR-3 Extended Power Uprate LAR2011-08-18018 August 2011 Response to Request for Additional Information to Support NRC Instrumentation and Controls Branch Acceptance Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0811-03, Response to Request for Additional Information to Support NRC Mechanical and Civil Branch Acceptance Review of the CR-3 Extended Power Uprate LAR2011-08-25025 August 2011 Response to Request for Additional Information to Support NRC Mechanical and Civil Branch Acceptance Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML11259A0122011-09-14014 September 2011 NRR E-mail Capture - Clarification for August 25 Emcb RAI Acceptance Review Letter Project stage: Other ML11286A0922011-10-11011 October 2011 Response to Request for Additional Information to Support NRC Reactor Systems Branch Acceptance Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML11300A2262011-10-25025 October 2011 Feedwater Line Break Overpressure Protection Analysis to Support NRC Reactor Systems Branch Acceptance Review of the CR-3 Extended Power Update LAR and LAR Approval Schedule Project stage: Other 3F1011-08, ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip2011-10-25025 October 2011 ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip Project stage: Other ML11286A0842011-11-21021 November 2011 Acceptance for Review of License Amendment Request for Extended Power Uprate Project stage: Acceptance Review ML11326A2312011-12-0707 December 2011 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI 3F1211-05, Response to Request for Additional Information to Support NRC Health Physics and Human Performance Branch Technical Review of the CR-3 Extended Power Uprate LAR2011-12-15015 December 2011 Response to Request for Additional Information to Support NRC Health Physics and Human Performance Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML12205A3572011-12-15015 December 2011 Attachment a to 3F0712-03, CR-3 LOCA Summary Report - EPU/ROTSG/Mark-B-HTP, Revision 4 Project stage: Other 3F1211-06, Response to Request for Additional Information to Support NRC Vessels and Internals Integrity Branch Technical Review of the CR-3 Extended Power Uprate LAR2011-12-15015 December 2011 Response to Request for Additional Information to Support NRC Vessels and Internals Integrity Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F1211-10, Response to Request for Additional Information to Support NRC Fire Protection Branch Technical Review of the CR-3 Extended Power Uprate LAR2011-12-21021 December 2011 Response to Request for Additional Information to Support NRC Fire Protection Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML12030A2092012-01-0505 January 2012 Response to Request for Additional Information to Support NRC Instrumentation and Control Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0112-04, Response to Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch Technical Review of the CR-3 Extended Power Uprate LAR2012-01-0505 January 2012 Response to Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML11342A1952012-01-0606 January 2012 Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing and Order Imposing Procedures for Document Access to Sensitive Unclassified Non-safeguards Information Project stage: Other ML12024A3002012-01-19019 January 2012 Response to Request for Additional Information to Support NRC Component Performance and Testing Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0112-06, Response to Request for Additional Information to Support NRC Piping and NDE Branch Technical Review of the CR-3 Extended Power Uprate LAR2012-01-19019 January 2012 Response to Request for Additional Information to Support NRC Piping and NDE Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0112-11, Corrections to the Extended Power Uprate LAR 309 Vendor Affidavit and Technical Report2012-01-31031 January 2012 Corrections to the Extended Power Uprate LAR 309 Vendor Affidavit and Technical Report Project stage: Other ML12003A2172012-02-0808 February 2012 Nuclear Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI 3F0212-01, Complex - Environmental Protection Plan Report 2011 Sea Turtle Rescue and Recovery Summary Report2012-02-0808 February 2012 Complex - Environmental Protection Plan Report 2011 Sea Turtle Rescue and Recovery Summary Report Project stage: Request ML1205505612012-03-0202 March 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12053A2312012-03-0202 March 2012 Request for Withholding Proprietary Information from Public Disclosure Related Extended Power Uprate Technical Report Project stage: Other ML12052A1302012-03-0202 March 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI 3F0312-02, Response to Second Request for Additional Information to Support NRC Instrumentation and Controls Branch (Eicb) Technical Review of the CR-3 Extended Power Uprate LAR2012-03-19019 March 2012 Response to Second Request for Additional Information to Support NRC Instrumentation and Controls Branch (Eicb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Request 3F0312-01, Response to Request for Additional Information to Support NRC PRA Licensing Branch Technical Review of the CR-3 Extended Power Uprate LAR2012-03-22022 March 2012 Response to Request for Additional Information to Support NRC PRA Licensing Branch Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML12031A0322012-03-26026 March 2012 Request for Withholding Proprietary Information from Public Disclosure Related to Extended Power Uprate Technical Report Project stage: Other ML1208300282012-04-0202 April 2012 Nuclear Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI 3F0412-05, Response to Second Request for Additional Information to Support NRC Health Physics and Human Performance Branch (Ahpb) Technical Review of the CR-3 Extended Power Uprate LAR2012-04-0404 April 2012 Response to Second Request for Additional Information to Support NRC Health Physics and Human Performance Branch (Ahpb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Request 3F0412-04, Response to Request for Additional Information to Support NRC Mechanical and Civil Engineering Branch (Emcb) Technical Review of the CR-3 Extended Power Uprate LAR2012-04-0404 April 2012 Response to Request for Additional Information to Support NRC Mechanical and Civil Engineering Branch (Emcb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML12107A0682012-04-0404 April 2012 NRR E-mail Capture - Crystal River, Unit 3 EPU LAR - Clarifications for Component Performance & Testing Branch (Eptb) Project stage: Other 3F0412-07, Response to Request for Additional Information to Support NRC Containment and Ventilation Branch (Scvb) Technical Review of the CR-3 Extended Power Uprate LAR2012-04-12012 April 2012 Response to Request for Additional Information to Support NRC Containment and Ventilation Branch (Scvb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0412-06, Response to Request for Additional Information to Support NRC Electrical Systems Branch (Eeeb) Technical Review of the CR-3 Extended Power Uprate LAR2012-04-16016 April 2012 Response to Request for Additional Information to Support NRC Electrical Systems Branch (Eeeb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI 3F0412-09, Response to Request for Additional Information to Support NRC Accident Dose Branch (Aadb) Technical Review of the CR-3 Extended Power Uprate LAR2012-04-26026 April 2012 Response to Request for Additional Information to Support NRC Accident Dose Branch (Aadb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML1208300382012-05-0404 May 2012 Nuclear Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12102A0442012-05-0404 May 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12205A3582012-05-31031 May 2012 Attachment D to 3F0712-03, Technical Report, ANP-3114(NP), Rev. 0, CR-3 EPU - Feedwater Line Break Analysis Sensitivity Studies Project stage: Other ML12314A3912012-05-31031 May 2012 17877-0002-100, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment 2 Project stage: Other 3F0612-05, Response to Request for Additional Information to Support NRC Nuclear Performance and Code Review Branch (Snpb) Technical Review of the CR-3 Extended Power Uprate LAR2012-06-18018 June 2012 Response to Request for Additional Information to Support NRC Nuclear Performance and Code Review Branch (Snpb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Response to RAI ML12206A3372012-06-29029 June 2012 Response to Second Request for Additional Information to Support NRC Accident Dose Branch (Aadb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Request 3F0712-03, Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip2012-06-30030 June 2012 Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip Project stage: Other ML12184A3442012-07-0202 July 2012 NRR E-mail Capture - Crystal River, Unit 3 EPU LAR - Discussion/Clarification of Emcb Draft RAIs Project stage: Draft Other ML12171A3472012-07-0505 July 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12174A2922012-07-0505 July 2012 Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI ML12194A4172012-07-17017 July 2012 Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment Request Project stage: RAI 3F0712-06, Response to Second Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch (Esgb) Technical Review of the CR-3 Extended Power Uprate LAR2012-07-17017 July 2012 Response to Second Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch (Esgb) Technical Review of the CR-3 Extended Power Uprate LAR Project stage: Request 2012-02-08
[Table View] |
Text
1 NRR-PMDAPEm Resource From:
Westcott, Daniel [Daniel.Westcott@pgnmail.com]
Sent:
Monday, July 02, 2012 8:24 AM To:
Lingam, Siva Cc:
Broaddus, Doug; Murphy, Martin; Jessup, William
Subject:
RE: Crystal River, Unit 3 EPU LAR - Discussion/Clarification of EMCB Draft RAIs (TAC No.
ME6527)
CR-3 concurs with the conference call summary.
From: Lingam, Siva [1]
Sent: Friday, June 29, 2012 10:09 PM To: Westcott, Daniel Cc: Broaddus, Doug; Murphy, Martin; Jessup, William
Subject:
Crystal River, Unit 3 EPU LAR - Discussion/Clarification of EMCB Draft RAIs (TAC No. ME6527)
Please concur on the following summary of the conference call held on June 28, 2012 regarding the subject matter.
RAI 1
In response to the NRC staffs request for clarification regarding the design code(s) used in the evaluation of the reactor vessel internals (RVIs) at EPU conditions, the licensee indicated that the RVIs had been evaluated in accordance with the provisions of Section III, Subsection NG of the ASME Boiler and Pressure Vessel Code, either the 1998 Edition with 2000 Addenda or the 2001 Edition with 2003 Addenda. The licensee confirmed that Subsection NG was not used in the original analysis to qualify the RVIs due to the fact that this subsection of the ASME Code was not available for use (i.e.,
had not been issued by ASME) during the licensing of Crystal River Unit 3. However, since the original licensing of the facility, subsequent reconciliations of the design basis analyses of the RVIs have utilized the design provisions prescribed by Subsection NG. The licensee also confirmed that the allowable stresses used in the evaluations were derived from the minimum specified material strengths of the standards to which the materials were purchased and the margins defined in the design provisions.
RAI 2
In response to the NRC staffs request for clarification regarding the period of operation assumed for fatigue evaluations, the licensee confirmed that it had only considered the 40-year license period for which CR-3 is currently licensed. The licensee acknowledged that CR-3 was also currently seeking approval for a renewed operating license, but indicated that any changes to the licensing basis resulting from EPU approval which affect its license renewal application would be submitted per the requirements of 10 CFR 54.21(b). As such, the impact of EPU on the facility for the period of extended operation will be addressed in the review of the license renewal application and not considered in the NRC staffs review of the EPU license amendment request.
Hearing Identifier:
NRR_PMDA Email Number:
402 Mail Envelope Properties (66C0930ED750B74E80B0F51A1F24D99A1A569C6334)
Subject:
RE: Crystal River, Unit 3 EPU LAR - Discussion/Clarification of EMCB Draft RAIs (TAC No. ME6527)
Sent Date:
7/2/2012 8:24:11 AM Received Date:
7/2/2012 8:24:19 AM From:
Westcott, Daniel Created By:
Daniel.Westcott@pgnmail.com Recipients:
"Broaddus, Doug" <Doug.Broaddus@nrc.gov>
Tracking Status: None "Murphy, Martin" <Martin.Murphy@nrc.gov>
Tracking Status: None "Jessup, William" <William.Jessup@nrc.gov>
Tracking Status: None "Lingam, Siva" <Siva.Lingam@nrc.gov>
Tracking Status: None Post Office:
WN000074.oak.zone1.progress-energy.com Files Size Date & Time MESSAGE 2344 7/2/2012 8:24:19 AM Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received: