Document Title or Accession No. E-Mail Dated 3/6/2019 from John Hickman, NRC, to Phyllis Dixon, Duke Energy Florida, LLC, Regarding NRC Acceptance Review of Partial Site Release Request for Crystal River Unit 3
ML19070A311
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/06/2019
From: John Hickman
Division of Decommissioning, Uranium Recovery and Waste Programs
To: Dixon P
Duke Energy Corp
J HICKMAN DUWP
References
Download: ML19070A311 (1)


Text

Manley, Eileen From: Hickman, John Sent: Wednesday, March 06, 2019 10:21 AM To: Dixon, Phyllis Cc: Vansicklen, Mark E. (Mark.Vansicklen@duke-energy.com); Philip.Rose@duke-energy.com

Subject:

Partial Site Release Acceptance Review Ms. Dixon:

By letter dated January 22, 2019 (ML19022A076), Duke Energy Florida, LLC submitted a request for a Partial Site Release at Crystal River Unit 3 Nuclear Generating Plant.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed partial site release in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

The NRC staff expects to complete this review in approximately 8 months, which is September 2019. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

If you have any questions, please contact me.

John B. Hickman, Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery, and Waste Programs Office of Nuclear Material Safety and Safeguards 1