MONTHYEARML20217G4461999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Pingp.With ML20216E7151999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Pingp,Units 1 & 2. with ML20210Q4891999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Pingp,Units 1 & 2. with ML20209F9811999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Prairie Island Nuclear Generating Plant,Units 1 & 2.With ML20195G5181999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Prairie Island Nuclear Generating Plant,Units 1 & 2.With . Page 3 in Final Rept of Incoming Submittal Was Not Included ML20206L6191999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Pingp,Units 1 & 2. with ML20205N1081999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Pingp,Units 1 & 2. with ML20207J6951999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Prairie Island Nuclear Generating Plant ML20207L2811999-01-31031 January 1999 Revised Monthly Operating Repts for Jan 1999 for Pingp,Units 1 & 2 ML20206P7861998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Prairie Island Nuclear Generating Plant.With ML20206N2731998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Prairie Island Nuclear Generating Plant,Units 1 & 2.With ML20155K6301998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Prairie Island Nuclear Generating Plant,Units 1 & 2.With ML20154H4061998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Prairie Island Nuclear Generating Plant.With ML20153B0761998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Prairie Island Nuclear Generating Plant.With ML20236X8531998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Prairie Island Nuclear Generating Plant ML20236R0771998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Prairie Island Nuclear Generating Plant ML20249A5751998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Prairie Island Nuclear Generating Plant ML20247G2921998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Prairie Island Nuclear Generating Plant ML20216C6361998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Prairie Nuclear Generating Plant Units 1 & 2 ML20216E2051998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Prairie Island Nuclear Generating Plant ML20216E2121998-01-31031 January 1998 Revised MOR for Jan 1998 for Prairie Island Nuclear Generating Plant for Unit 2 & Narrative Summary of Operating Experience ML20202E7761998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Prairie Island Nuclear Generating Plant ML20198P1541997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Prairie Island Nuclear Generating Plant,Unit 1 & 2 ML20203H4341997-11-30030 November 1997 Monthly Operating Repts for Nov 1996 for Prairie Island Nuclear Generating Plant,Unit 1 ML20199D0701997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Prairie Island Nuclear Generating Plant ML20198J7281997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Prairie Island Nuclear Generating Plant,Units 1 & 2 ML20210S5911997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Prairie Island Nuclear Generating Plant,Units 1 & 2 ML20217J0681997-07-31031 July 1997 Monthly Operating Repts for Jul 1997 for Prairie Island Nuclear Generating Plant ML20148K3871997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Prairie Island Nuclear Generating Plant,Units 1 & 2 ML20141A9581997-04-30030 April 1997 Monthly Operating Repts for April 1997 for Prairie Island Nuclear Plant ML20137T2891997-03-31031 March 1997 Monthly Operating Repts for March 1997 for Prairie Island Nuclear Plant ML20135F6841997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for Praire Island Nuclear Generating Plant ML20134L8831997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Praire Island Nuclear Generating Plant ML20133F8611996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Praire Island Nuclear Generating Plant ML20135E8811996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Prairie Island Nuclear Generating Plant ML20134L7091996-10-31031 October 1996 Monthly Operating Repts for Oct 1996 for Prairie Island Nuclear Generating Plant ML20128G1741996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Prairie Island Nuclear Generating Plant ML20117N1521996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Prairie Island Nuclear Generating Plant ML20116J6451996-07-31031 July 1996 Monthly Operating Rept for Jul 1996 for Prairie Island Nuclear Generating Plant ML20115A8321996-06-30030 June 1996 Monthly Operating Repts for June 1996 for Prairie Island Nuclear Generating Plant Units 1 & 2 ML20117K5811996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Prairie Island Nuclear Generating Plant ML20111B2801996-04-30030 April 1996 Monthly Operating Repts for Apr 1996 for Prairie Island Nuclear Generating Plant ML20101N8931996-03-31031 March 1996 Monthly Operating Repts for Mar 1996 for Prairie Island Nuclear Generating Plant Units 1 & 2 ML20101D0671996-02-29029 February 1996 Monthly Operating Repts for Feb 1996 for Praire Island Nuclear Generating Plant Units 1 & 2 ML20097D5411996-01-31031 January 1996 Monthly Operating Repts for Jan 1996 for Prairie Island Units 1 & 2 ML20096E9631995-12-31031 December 1995 Monthly Operating Repts for Dec 1995 for Prairie Island Nuclear Generating Plant ML20095G4371995-11-30030 November 1995 Monthly Operating Repts for Nov 1995 for Prairie Island Nuclear Generating Station ML20094L7491995-10-31031 October 1995 Monthly Operating Repts for Oct 1995 for Prairie Island Nuclear Generating Plant ML20098D0101995-09-30030 September 1995 Monthly Operating Repts for Sept 1995 for Prairie Island Nuclear Generating Plant ML20092D0091995-08-31031 August 1995 Monthly Operating Repts for Aug 1995 for Prairie Island Nuclear Plant 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217G4461999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Pingp.With ML20217A9931999-09-30030 September 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers ML20216E7151999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Pingp,Units 1 & 2. with ML20211D3981999-08-24024 August 1999 Safety Evaluation Supporting Requested Actions to Licenses DPR-42 & DPR-60,respectively ML20211C2531999-08-0404 August 1999 Unit 1 ISI Summary Rept Interval 3,Period 2 Refueling Outage Dates 990425-990526 Cycle 19 971212-990526 ML20210Q4891999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Pingp,Units 1 & 2. with ML20211B5971999-07-31031 July 1999 Cycle 20 Voltage-Based Repair Criteria 90-Day Rept ML20209J1131999-07-15015 July 1999 Safety Evaluation of Topical Rept NSPNAD-8102,rev 7 Reload Safety Evaluation Methods for Application to PI Units. Rept Acceptable for Referencing in Prairie Island Licensing Actions ML20196H8621999-06-30030 June 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data, June 1999 Rept ML20209F9811999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Prairie Island Nuclear Generating Plant,Units 1 & 2.With ML20196F4081999-06-23023 June 1999 Revised Pages 71,72 & 298 to Rev 7 of NSPNAD-8102, Prairie Island Nuclear Power Plant Reload Safety Evaluation Methods for Application to PI Units ML20195G5181999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Prairie Island Nuclear Generating Plant,Units 1 & 2.With . Page 3 in Final Rept of Incoming Submittal Was Not Included ML20207B5931999-05-26026 May 1999 SER Accepting Licensee Proposed Alternative to ASME Code for Surface Exam (PT) of Seal Welds on Threaded Caps for Unit 1 Reactor Vessel Head Penetrations for part-length CRDMs ML20196L2501999-05-13013 May 1999 Rev 0 to PINGP Unit 1 COLR Cycle 20 ML20206L6191999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Pingp,Units 1 & 2. with ML20205N1081999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Pingp,Units 1 & 2. with ML20205Q5101999-03-15015 March 1999 Inservice Insp Summary Rept Interval 3,Period 1 & 2 Refueling Outage Dates 981109-1229 Cycle 19,970327-981229 ML20207J6951999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Prairie Island Nuclear Generating Plant ML20202J7711999-02-0404 February 1999 Simulator Certification Rept for Prairie Island Plant Simulation Facility,1998 Annual Rept ML20202G3761999-01-31031 January 1999 Non-proprietary Rev 7 to NSPNAD-8102-NP, Prairie Island Nuclear Power Plant Reload SE Methods for Application to PI Units ML20207L2811999-01-31031 January 1999 Revised Monthly Operating Repts for Jan 1999 for Pingp,Units 1 & 2 ML20202J1731999-01-22022 January 1999 Safety Evaluation Concluding That NSP Proposed Alternative to Surface Exam Requirements of ASME BPV Code for CRD Mechanism Canopy Seal Welds Will Provide Acceptable Level of Quality & Safety ML20206P7861998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Prairie Island Nuclear Generating Plant.With ML20205H0561998-12-31031 December 1998 Northern States Power Co 1998 Annual Rept. with ML20198J6441998-12-17017 December 1998 Rev 0 to PINGP COLR Unit 2-Cycle 19 ML20206N2731998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Prairie Island Nuclear Generating Plant,Units 1 & 2.With ML20196D7341998-11-20020 November 1998 Third Quarter 1998 & Oct 1998 Data Rept for Prairie Island Isfsi ML20155K6301998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Prairie Island Nuclear Generating Plant,Units 1 & 2.With ML20154H4061998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Prairie Island Nuclear Generating Plant.With ML20202J7991998-09-30030 September 1998 Non-proprietary Version of Rev 3 to CEN-629-NP, Repair of W Series 44 & 51 SG Tubes Using Leaktight Sleeves,Final Rept ML20198P0571998-09-0303 September 1998 Rev 1 to 95T047, Back-up Compressed Air Supply for Cooling Water Strainer Backwash Valve Actuator ML20153B0761998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Prairie Island Nuclear Generating Plant.With ML20237A3961998-08-11011 August 1998 Safety Evaluation on Westinghouse Owners Group Proposed Insp Program for part-length CRDM Housing Issue.Insp Program for Type 309 Welds Inadequate from Statistical Point of View ML20237A8171998-08-0505 August 1998 SER Related to USI A-46 Program GL 87-02 Implementation for Prairie Island Nuclear Generating Plant,Units 1 & 2 ML20236X8531998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Prairie Island Nuclear Generating Plant ML20236R6481998-07-15015 July 1998 Metallurgical Investigation & Root Cause Assessment of Part Length CRDM Housing Motor Tube Cracking at PINGP Unit 2 - Preliminary Summary Rept ML20236R0771998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Prairie Island Nuclear Generating Plant ML20249A5751998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Prairie Island Nuclear Generating Plant ML20247G7011998-05-31031 May 1998 Metallurgical Investigation & Root Cause Assessment of Part Length CRDM Housing Motor Tube Cracking at Prairie Island Nuclear Generating Plant,Unit 2 ML20248M0561998-05-31031 May 1998 Rev 5 to CEN-620-NP, Series 44 & 51 Design SG Tube Repair Using Tube Rerolling Technique ML20247E2671998-05-0505 May 1998 Rev 0 to Pingp,Units 1 & 2,Pressure & Temp Limits Rept (Effective Until 35 Efpy) ML20247G2921998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Prairie Island Nuclear Generating Plant ML20217M6901998-04-29029 April 1998 Safety Evaluation Accepting Methodology for Relocation of Reactor Coolant Sys P/T Limit Curves & LTOP Sys Limits Proposed by NSP for Pingp,Units 1 & 2 ML20216C6361998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Prairie Nuclear Generating Plant Units 1 & 2 ML20216H0341998-03-31031 March 1998 Cycle-19 Voltage Based TSP Alternate Repair Criteria 90-Day Rept ML20217D2041998-03-13013 March 1998 Rev 1 to 28723-A, Intake Canal Liquefaction Analysis Rept for Pingp,Welch,Mn ML20236P9801998-03-12012 March 1998 Rev 0 to 97FP02-DOC-01, Compliance Review of 10CFR50,App R, Section Iii.O RCP Lube Oil Collection Sys ML20248L3931998-03-10010 March 1998 ISI Summary Rept Interval 3,Period 1 & 2 Refueling Outage Dates 971018-971212 Cycle 18,960303-971212 ML20216D0911998-03-0606 March 1998 Rev 0 to Prairie Island Generating Plant,Units 1 & 2, Pressure & Temp Limits Rept 1999-09-30
[Table view] |
Text
-
Northern States Power Company Prairie Island Nuclear Generating Plant 1717 Wakonade Dr East Welch Minnesota 55089 ,
1 April 8,1999 Technical Specifications 6.7.A.3 l
l US Nuclear Regulatory Commission l Attn: Document Control Desk Washington, DC 20555 l
PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 l Monthly Operating Report March 1999 1
l Attached is the Monthly Operating Report for March 1999 for the Prairie Island Nuclear Generating Plant.
Joel P. Sorensen Site General Manager Prairie Island Nuclear Generating Plant l c: Regional Administrator-Ill, NRC l
NRR Project Manager, NRC NRC Resident inspector State of Minnesota - Steve Minn i
/ _ '} - \
'.-~'
}-
Attachment 9904160155 990331
{DR ADOCK 05000282 PDR l
l
- PRINTED 4/2/1999 NRC MONTHLY REPORT Page1 DOCKET NO. 50-282 UNIT PRAIRIE ISLAND NO.1 DATE 4/2/1999 COMPLETED BY DALE DUGSTAD PHONE 651388-1121-4376 NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE MONTH: MARCH 1999 During the month of March, Unit 1 was base loaded. There were no shutdowns or power reductions for this month.
l I
l CURRENT CONTINUOUS OPERATING RUN OF 78 DAYS
PRINTED 4/2/1999 NRC MONTHLY REPORT Page 2 DOCKET NO. 50-282
. UNIT PRAIRIE ISLAND NO.1 DATE 4!2/1999 COMPLETED BY DALE DUGSTAD PHONE 651388-11214376 OPERATING DATA REPORT OPERATING STATUS ,
1
- 1. UNIT NAME: PRAIRIE ISLAND NO.1
- 2. REPORTING PERIOD; MARCH 1999
- 3. LICENSED THERMAL POWER (MWT): 1650 l
- 4. NAMEPLATE RATING (GROSS MWE): 593
- 5. DESIGN ELECTRICAL RATING (NET MWE); 536
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 554
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 522
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 7) SINCE LAST REPORT, GIVE REASON:
NONE
- 9. POWER LEVEL TO WHICH RESTRICTED,IF ANY (NET MWE): NONE
- 10. REASONS FOR RESTRICTIONS. IF ANY: NONE THIS MONTH YR TO_ DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD 744 2160 221688
- 12. NUMBER OF HOURS REACTOR CRITICAL 744.0 2317.3 190804.8
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.00 5571.1 l
- 14. HOURS GENERATOR ON-LINE 744.0 2003.4 188942.1
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.00 0.00
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1220400 3273723 300504073
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 426180 1143140 99413110
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 406071 1088478 93531960
- 19. UNIT SERVICE FACTOR 100.0 92.8 85.2
- 20. UNIT AVAILABILITY FACTOR 100.0 92.8 85.2
- 21. UNIT CAPACITY FACTOR ( MDC NET) 104.6 96.5 83.4
- 22. UNIT CAPACITY FACTOR ( DER NET) 101.8 94.0 79.6
- 23. UNIT FORCED OUTAGE RATE 0.0 7.3 4.8
- 24. FORCED OUTAGE HOURS 0.0 156.6 9483.8 l
I
NRC MONTHLY REPORT PRINTED 4/2/1999 Page 3 DOCKET NO. 50-282 UNIT PRAIRIE ISLAND NO.1 DATE 4/2/1999 COMPLETED BY DALE DUGSTAD PHONE 651-388-1121-4376 UNIT SHUTDOWNS AND POWER REDUCTIONS MONTH: MARCH 1999 DATE UNIT TYPE HOURS REASON METHOD LER NUMBER SYSTEM COMPONENT 3/31/1999 1 0 NOTES: None.
TYPE REASON METHOD SYSTEM CODE F-FORCED A-EQUIPMENT FAILURE 1-MAN'JAL DRAFT IEEE STD S-SCHEDULED B-MAINTENANCE OR TEST 2-MANUAL TRIP C-REFUELING 3-AUTO TRIP D-REGULATORY RESTRICTION 4-CONTINUED E-OPERATOR TRAINING AND 5-REDUCED LOAD COMPONENT CODE LICENSE EXAMINATION 9-OTHER IEEE STD 803A 1983 F-ADMINISTRATIVE G OPERATIONAL ERROR H-OTHER
- l
- PRINTED 4/2/1999 NRC MONTHLY REPORT Page 4 DOCKET NO. 50-306 '
. UNIT PRAIRIE ISLAND NO. 2 DATE 4/2/1999 COMPLETED BY DALE DUGSTAD PHONE 651-388-1121-4376 N.ARRATIVE
SUMMARY
OF OPERATING EXPERIENCE MONTH: M ARCH 1999 During the month of March, Unit 2 was base loaded. There was only one power reduction and there were no shutdowns for this month.
On the 13th at 2300, the Unit started to reduce power to perform a turbine valves test. The test was satisfactory. The Unit started a power ascension j on the 14th at 0205 and reached full power operation at 0430.
There were no other items to report.
l CURRENT CONT lNUOUS OPERATING RUN OF 52 DAYS
NRC MONTHLY REPORT PRINTED 4/2/1999 Page 5 DOCKET NO. 50 306 UNIT PRAIRIE ISLAND NO. 2 DATE 4/2/1999 COMPLETED BY DALE DUGSTAD PHONE 651-3881121-4376 OPERATING DATA REPORT OPERATING STATUS
- 1. UNIT NAME: PRAIRIE ISLAND NO. 2
- 2. REPORTING PERIOD: MARCH 1999
- 3. LICENSED THERMAL POWER (MWT): 1650
- 4. NAMEPLATE RATING (GROSS MWE): 593
- 5. DESIGN ELECTRICAL RATING (NET MWE): 536
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 554
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 522
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 - 7) SINCE LAST REPORT, GIVE REASON:
NONE
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): NONE
- 10. REASONS FOR RESTRICTIONS, IF ANY: NONE THIS MONTH YR-TO-D_ ATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD 744 2160 212806
- 12. NUMBER OF HOURS REACTOR CRITICAL 744.0 2125.8 187447.9
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 1516.1
- 14. HOURS GENERATOR ON-LINE 744.0 2090.9 185875.1
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1223757 3317561 296468642
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 424430 1147860 97183790
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 404705 1090228 91876557
- 19. UNIT SERVICE FACTOR 100.0 96.8 87.3
- 20. UNIT AVAILABILITY FACTOR 100.0 96.8 87.3
- 21. UNIT CAPACITY FACTOR ( MDC NET) 104.2 96.7 85.9
- 22. UNIT CAPACITY FACTOR ( DER NET) 101.5 94.2 81.5
- 23. UNIT FORCED OUTAGE RATE 0.0 0.0 3.0 24, FORCED OUTAGE HOURS 0.0 0.0 5662.8
l
- PRINTED 4/2/1999 NRC MONTHLY REPORT Page 6 DOCKET NO. 50 306 a
- UNIT PRAIRIE ISLAND NO. 2 DATE 4/2/1999 COMPLETED BY DALE DUGSTAD PHONE 651-388-1121-4376 l I
UNIT SHUTDOWNS AND POWER REDUCTIONS MONTH: MARCH 1999 DATE UNIT TYPE HOURS REASON METHOD LER NUMBER SYSTEM COMPONENT 3/14/1999 2 S 0 8 5 N/A N/A N/A NOTES: Turbine valves testing.
I l
TYPE REASON METHOD SYSTEM CODE F-FORCED A-EQUIPMENT FAILURE 1 MANUAL DRAFT IEEE STD
~
S-SCHEDULED B MAINTENANCE OR TEST 2-MANUAL TRIP C-REFUELING 3-AUTO TRIP D-REGULATORY RESTRICTION 4-CONTINUED E OPERATOR TRAINING AND 5-REDUCED LOAD C.OMPONENT CODE LICENSE EXAMINATION 9-OTHER IEEE STD 803A 1983 F-ADMINISTRATIVE G-OPERATIONAL ERROR H OTHER
.. -