Submits site-specific Cost Estimate for Saxton Nuclear Experimental Corp Facility as Required by 10CFR50.82(a)(8)(ii) & Satisfies Commitment to Have an Approved Quality Assurance Plan,Per 10CFR71.101
ML20134L731
Person / Time
Site: Saxton File:GPU Nuclear icon.png
Issue date: 11/08/1996
From: Kuehn G
GENERAL PUBLIC UTILITIES CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20134L733 List:
References
C301-96-2051, NUDOCS 9611210186
Download: ML20134L731 (4)


Text

. .

l

{ GPU Nuclear. Inc. l'

( Route 441 South nucuan  % L;&, ,

Tel717 944 7621 November 08, 1996 C301-96-2051 U. S. Nuclear Regu~latory Commission Attn: Document Control Desk Washington, D.C. 20555 Gentlemen, l

Subject:

Saxton Nuclear Experimental Corporation Operating License No. DPR-4 Docket No. 50-146 SNEC Decommissioning The purpose of this letter is to submit a site-specific cost estimate for the Saxton Nuclear Experimental Corporation (SNEC) facility as required by 10 CFR 50.82(a)(8)(ii) and satisfy a commitment to have an approved quality assurance plan which meets the requirements of 10 CFR Part 71.101.

Submittal of a site-specific cost estimate is required prior to the use of funding from the decommissioning trust in excess of 23 percent. Attachment I is a summary of amounts as identified by the Decommissioning Cost Estimate for the Saxton Nuclear Experimantal Facility required to complete decommissioning of the SNEC facility.

In a submittal dated July 18,1996 GPU Nuclear provided a response to Question 19 of the NRC's request for additionalinformation dated June 6,1996. That response committed to developing / revising and implementing an approved quality assurance plan during the decommissioning phase which meets the requirements of Part 71.101 prior to the performance of 10 CFR 71 activities. GPU Nuclear has satisfied the commitment by issuing the Saxton Nuclear Experimental Corporation Facility Decommissioning Quality Assurance Plan on October 29, 1996. The plan commits to continued compliance to theNRC approved "GPU Nuclear Operational Quality Assurance Plan",1000-PLN-7200.01 and 10 CFR Part 71. The Saxton Nuclear Experimental Corporation Facility Decommissioning Quality Assurance Plan is included as Attachment 2.

Smcerely, G. A. Kuehn Jr.

9611210i PDR ADO $ h ooO$46 PDR Vice President SNEC

,j

$i/

C301-96-2051 l Page 2 of 2 l

l WGli l Attachments l l

cc: Administrator, NRC Region I I NRC Project h1anager NRR l NRC Project Scientist, Region I

---. - . _ - _ . _ . . - ~ . - . - . . - . . - . - - . - . - . . - . - . . - - . - - . _ . .

!

  • C301-96-2051

_ Attachment 1 SAXTON DECOMMISSIONING PROJECT

) COST MUMMARY -

Page 1 of 2 i, ,

Cost Contingency (%) Contingency ($'s)

Category f DOC (Utility) staff i $2,037,726 15%- $305,659 i Preparations Phase 15% $687,823

$4,585,483 j ~ Operations Phase 15% $133,527

$890,177 l Survey Phase 15% $132,704

$884,696 Restoration Phase $1,259,712 Sub(otal DOC $8,398,082 Activity Dependent staff 30 i Preparations Phase ,

25% $334,003

$1,336,013 l- Operations Phase $620,040 15% $93,006 Survey Phase $189,011 15 % $28,m Restoration Phase $408,5i.~

' Subtotal Activity $2,145,064

! Radwaste Disposal / Processing $316,823

' 4633,645' 50 %

Reactor Vessel (Bamwell) $61,352 8245,407 25%

l ' Steam Generator (Bamwell) $547,491 -25% $136,873

! Metal (SEG) $343,640 . 25% $85,910 i Asbestos (Bamwell) $27,357 15% $4,104 Shipping Containers (Asbestos) 25% $16,146 l- $64,586

Dry Active Waste (SEG) $18,192 25% $4,548 Lead (SEG) $508,440 25% $127,110 Concrete (Envirocare) $752,865 l

Subtotal Radwaste $2,388,758 I ,

i Shipping Costs .$116,094 25% $29,024 i Reactor Vessel / Steam Generator $2,624 15% S394 2

' Asbestos (Bamwell) $11,022 15% $1,653 f' Metal (SEG)~ $1,837 .15% $27t>

, Lead (SEG) $1,837 15% $276 Dry Active Waste (SEG) $174,356 15% $26,153 l Concrete (Envirocare) $307,770 $57,775 Subtotal Radwaste

' Specialty Contractor Services $1,246,708 25% $311,677 RPV/SG Packaging .

$39,892 i $159,568 25%

! RPV/SG Heavy Lift 15% $49,425

$329,500 '

NRC Review & Subcontractors $500,000 15% $75,000

' Decommissioning Consulting $475,994 I Subtotal Specialty $1,735,776 Installation 9f Support Facilities /Systents 25% $97,125

$388,500 Design / Construction Support Bldg. $11,669 l - $46,674 25%

i Design / Construction RPV laydown area $5,213 __

$20,852 25%

Potable water and septic system $114,007 i $456,026 Subtotal Facility / Systems k

i C 1,

. _ . . . . . . . . - . - - . - - . - - - - -- --_--.~ _. . -. ... ...

I

, . C301- 96-2051

. Attachment 1 j SAXTON DECOMMIS810NING PROJECT Page 2 of 2 COST

SUMMARY

. l Category Cost Contingency (%) Contingency ($'s)

Materials and Equipment Heavy Equipment Rental $664,048 25% . $166,012 Capital Equipment Year 1 $200,000 25% $50,000 Capital Equipment Year 2 $105,000 25% $31,250 Capital Equipment Year 3 475,000 25%. Gt 9,750 1 Capital Equipment Year 4 $75,000 25% U 2,750 Activity Dependent Collateral Costs $216,045 25% $54,011 Period Dependent Collateral Costs $1,413,824 25% $353.456  ;

Subtotal Materials & Equipment $2,768,917 $692,229 '

Subtotal Project $18,200,393- $3,807,943 Average Contingency '

17%

Total Project $22.008,M6 I

i l

l i