Forwards Rev 0 to Procedure 6575-PLN-4542.09, SNEC Facility Process Control Program, for Review & Approval.Activities Will Be Initiated Starting W/Item 1.2.2.3 of Figure 2.2-4 of Decommissioning Plan When Approval of Tscr 59 Is Obtained
ML20211C237
Person / Time
Site: Saxton File:GPU Nuclear icon.png
Issue date: 09/16/1997
From: Kuehn G
GENERAL PUBLIC UTILITIES CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20211C241 List:
References
C301-97-2031, NUDOCS 9709260150
Download: ML20211C237 (1)


Text

___- -_-_ _ _ - _ _ _ _ _ _ - _ _

e

=

?

{

GPU Nuclear,Inc

(

Route 441 south Pc css,ee Box 4so NUCLEAR Middletown. PA 17057 0480 Tel717 944 7621 C301-97-2031 September 16, 1997 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555 Gentlemen:

Subject:

Saxton Nuclear Experimental Corporation Facility Operating License No. DPR-4 Docket No. 50-146 SNEC Facility Procesa Control Program The purpose of this letter is twofold. First, it submits for review and approval the SNEC Facility Process Control Program. It is being submitted for inclusion with documentation previously submitted to support Technical Specification Change Request (TSCR) 59 which addresses the active decommissioning and dismantlement of the SNEC facility.

Second, GPU Nuclear Inc. will be initiating activities starting with Item 1.2.2.3 of Figure 2.2-4 of the SNEC Facility Decommissioning Plan when approval of TSCR 59 is obtained. The remainder of the schedule will be adjusted forward from the quarter that work is initiated.

For additional information regarding this submittal, contact William Heysek of the TMl Nuclear Safety and Licensing Department at 717-948-8191.

Sincerely, i

0h p

G. A. Kuehn Vice President SNEC WGH Attachment cc: NRC Project Manager, Alexander X. Adams j

t NRC Project Scientist-Thomas F. Dragoun 9709260150 970916 PDR ADOCK 05C30146 p

PM

_