Forwards Insp Rept 50-443/96-11 on 961130-970113.No Violations Noted
ML20147E469
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 03/07/1997
From: Rogge J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Feigenbaum T
NORTH ATLANTIC ENERGY SERVICE CORP. (NAESCO)
Shared Package
ML20147E475 List:
References
NUDOCS 9703140002
Download: ML20147E469 (3)


See also: IR 05000443/1996011

Text

. _ _, , _ _ . _. . _ , _ _ _ . _ . _ _ _ . _ _ . _ _ . _ . _ .

l 4

..

.

,.-

1

March 7,1997 1

!

Mr. Ted C. Feigenbaum .

Executive Vice President and Chief Nuclear Officer

. North Atlantic Energy Service Corporation

Post Office Box 300

Seabrook,- New Hampshire 03874

. SUBJECT: NRC INTEGRATED INSPECTION REPORT NO. 50-443/96-11

Dear Mr. Feigenbaum: l

l On January 13,1997, the NRC completed an inspection at Seabrook Station. The

l enclosed report presents the results of that inspection.-

{

During the 7-week period covered by this inspection report, your conduct of activities was

L . generally characterized by safety-conscious operations, sound engineering efforts that

!

identified two deign-bases discrepancies in the description of the emergency feedwater ,

system design, and good maintenance and radiological work controls.  !

!'

L However, the NRC was unable to close its review of the Seabrook Generic Letter (GL) 89-

l

10, " Safety-Related Motor-Operated Valve Testing and Surveillance," program,' because of

I insufficient engineering justification for certain design inputs pertaining to motor-operated .j

valve (MOV) performance.  ;

We noted'that your staff committed: (1) to perform dynamic testing of fifteen additional

.

' motor-operated valves during the next two refueling outages as part of your periodic

[ verification program in order to obtain additional site-specific performance data; and (2) to

revise by January 31,1997, your governing GL 89-10 program procedure to strengthen

certain administrative controls for engineering evaluations and dynamic test acceptance

criteria. Our resident inspectors have indicated that as of the date of this letter, your staff

l has not completed the program revision. We request that you submit to us the reasons

that.you did not achieve the program revision by the commitment date as well as your i

updated projected completion date for our review and consideration. Any future regulatory l

action will be based upon staff review of your response letter.

i

i,

,

i

l

9703140002 970307

PDR ADOCK 05000443 g

  • *** i
IRER Q Q q ,

fi'

.

0

1

.. - . . . . . -. -. .

.. ~ . . _ - _ - . . =. ..-

,.

l.- i

-

.

l

,.-

Mr. Ted C. Feigenbaum 2

I

t in accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter, ,

! its enclosure, and your response will be placed in the NRC Public Document Room (PDR). I

l

l Sincerely,

l

Original Signed By: i

l

John F. Rogge, Chief

l f Projects Branch 8  ;

j Division of Reactor Projects

Docket No. 50-443

l License No: NPF-86

Enclosure: NRC Inspection Report No. 50-443/96-11

cc w/encis:

B. D. Kenyon, President - Nuclear Group

i D. M. Goebel, Vice President - Nuclear Oversight

F. C. Rothen, Vice President - Work Services

l J. K. Thayer, Vice President - Recovery Officer, Nuclear Engineering & Support Officer

l

H. F. Haynes, Director - Nuclear Training

B. L. Drawbridge, Executive Director - Services & Senior Site Officer l

A. M. Callendrello, Licensing Manager - Seabrook Station

W. A. DiProfio, Nuclear Unit Director - Seabrook Station

R. E. Hickok, Nuclear Training Manager - Seabrook Station

L.- M. Cuoco, Senior Nuclear Counsel

W. D. Meinert, Nuclear Engineer

D. C. McEihinney, RAC Chairman, FEMA RI, Boston, Mass.

R. Backus, Esquire, Backus, Meyer and Solomon, New Hampshire

S. Choi, Director, Nuclear Safety, Massachusetts Emergency

Management Agency

F. W. Getman, Jr., Vice President and General Counsel - Great Bay Power

Corporation

Commonwealth of Massachusetts, SLO Designee

R. Hallisey, Director, Dept. of Public Health, Commonwealth of Massachusetts

Seacoast Anti-Pollution League

State of New Hampshire, SLO

D. Tefft, Administrator, Bureau of Radiological Health, State of New Hampshire

S. Comley, Executive Director, We the People of the United States

!

l

l

l

!

.

_

, . - - . . ~ . . . - - . . - - . - . ~ . . .

1

,

,

e

.

Mr. Ted C. Feigenbaum 3

Distribution w/encls:

-

i

Region i Docket Room (with concurrences) l

PUBLIC

NRC Resident inspector

Nuclear Safety Information Center (NSIC)

l

W. Axelson, DRA

{

D. Screnci, PAO '

J. Rogge, DRP

E. Conner, DRP

C. O'Daniell, DRP

E. Kelly, DRS

' L. Prividy, DRS .

1

'

i

!

Distribution w/encls (VIA E MAIL):

W. Dean, OEDO i

P. Milano, PD l-3, NRR I

A. DeAgazio, PD l-3, NRR

l R. Correia, NRR

l D. Taylor, NRR

!

T. Scarbrough,EMEB/NRR (Section Ill)

D. Screnci, PAO, ORA

l Inspection Program Branch, NRR (IPAS) l

l

)

l

l

i

!

l

r

DOCUMENT NAME: G:\ BRANCH 8\9611. SEA

To receive a copy of this document, indicate in the box: "C' = Copy without attachment /enclosu,e "E" = Copy with attachment / enclosure

'N" = No copy j f A

OFFICE Rl/DRP //l/ Rl/DRP/////

NAME JMacdonald JRoggel/'

DATE q y/9i q r)/97

OFFICIAL RECORD COPY

l

,

l

l