February 2003 Monthly Operating Report for University of Missouri Research Reactor
ML030720421
Person / Time
Site: University of Missouri-Columbia
Issue date: 03/06/2003
From: Foyto L
Univ of Missouri - Columbia
To: Bassett C
Office of Nuclear Reactor Regulation
References
Download: ML030720421 (6)


Text

rM Research Reactor Center Research Park Columbia, MO 65211 University of Missouri-Columbia PHONE (573) 882-4211 FAX (573) 882-6360 March 06, 2003 Mr. Craig Bassett U.S. Nuclear Regulatory Commission 61 Forsyth Street, SW Suite 23T85 Atlanta, GA 30303

SUBJECT:

Monthly Operations Summary Enclosed is a copy of MURR's Monthly Operations Summary for February 2003. If you have any questions, please contact me at (573) 882-5276.

Sincerely, Leslie Foyto Interim Reactor Manager LM/Imcg Enclosure 2 f AN EQUAL OPPORTUN-Tm/ADA INSTITUTION

ffv-IS sumJIVAado

hgyatvdaAL Eooz' "hAVIIAgaf huwwwns figifimow SMOZLb-y3;(Lo YO'LDw3;yj-cDyw3;s3;y I-YllOSSIW SO ALISIff 3;AJMTL

INTRODUCTION The reactor operated continuously in February with the following exceptions: three shutdowns for scheduled maintenance and refueling; one unscheduled shutdown.

MAINTENANCE ACTIVITIES 2/3/03 Refueled - removed core 03-04, loaded core 03-05.

Removed and inspected level controller LC965 (Anti-siphon System Rod Run-in).

2/10/03 Refueled - removed core 03-05, loaded core 03-06.

Repaired an air leak on level controller LC965 (Anti-siphon System Rod Run-in).

2/16/03 Refueled - removed core 03-06, loaded core 03-07.

2/17/03 Replaced Primary Temperature Control Valve (S-1) motor.

Replaced Inner Airlock Door motor and gearbox.

2/18/03 Loaded new pool de-ionization bed 'W'.

2/24/03 Refueled - removed core 03-07, loaded core 03-08.

Installed flow gauges in the P-Tube system in accordance with Modification Record 03-1.

Completed Reactor Console upgrade in accordance with Modification Record 01-2.

Replaced Charging Pump Relief Valve (557A).

Repaired broken wire and replaced Intermediate Level Display Board (A4) on Nuclear Instrument Drawer #1.

UNSCHEDULED SHUTDOWNS Date No. Type Cause 2/16/03 1157 Scram Primary Temperature Control Valve (S-i) motor shorted.

On February 16, a Reactor Scram was automatically initiated when the Primary Temperature Control Valve (S-1) motor shorted resulting in an overload condition on Breaker #9 on UPS Panel No. 2. This breaker provides power to the process instrumentation. The loss of power resulted in trip signals from all of the protective system channels. The motor for valve S-1 was replaced and tested satisractorily. The UPS Inverter oscillator board was adjusted to remove an "Out of Sync" alarm resulting from the overload condition. The reactor protective system was verified operable as part of pre-startup checks and the reactor was subsequently returned to operation.

OPERATION

SUMMARY

FOR MONTH OF University of Missour Research Reactor Center (MURR)

HOURS OPERATED THIS PERIOD S 585.19 TOTAL HOURS OPERATED, REACTOR 248,63311 HOURS OPERATED AT FULL POWER, THIS PERIOD I 583.70 TOTAL HOURS AT FULL POWER, REACTOR I 24,35530 INTEGRATED POWER THIS PERIOD I243.28 MWD TOTAL INTEGRATED POWER, REACTOR I ,988 MWD Submitted by /U~A~

MWD Custodian/Reactor Physicist Date. /1 3/ 03-f I

N INTRODUCTION The reactor operated continuously in February with the following exceptions: three shutdowns for scheduled maintenance and refueling; one unscheduled shutdown.

MAINTENANCE ACTIVITIES 2/3/03 Refueled - removed core 03-04, loaded core 03-05.

Replacedlzaking-level controller LC965 (Anti-siphon System Rod Run-in).

2/10/03 Refueled - removed core 03-05, loaded core 03-06.

A4 AIA Repairedleak on level controller LC965 (Anti-siphon System Rod Run-in).

2/16/03 Refueled - removed core 03-06, loaded core 03-07.

2/17/03 Replaced Primary Temperature Control Valve (S-1) motor.

Replaced Inner Airlock Door motor and gearbox.

2/18/03 Loaded new pool de-ionization bed 'W'.

2/24/03 Refueled - removed core 03-07, loaded core 03-08.

Installed flow gauges in the P-Tube system in accordance with Modification Record 03-1.

Completed Reactor Console upgrade in accordance with Modification Record 01-2.

Replaced Charging Pump Relief Valve (557A).

Repaired broken wire and replaced Intermediate Level Display Board (A4) on Nuclear Instrument Drawer #1.