MONTHYEARML0535500332005-12-12012 December 2005 November 2005 Operating Report for University of Missouri-Columbia Research Reactor ML0532900992005-11-14014 November 2005 October 2005 Monthly Operating Report for University of Missouri - Columbia Research Reactor ML0529902852005-10-14014 October 2005 September 2005 Monthly Operating Report for University of Missouri ML0526303392005-09-0909 September 2005 August 2005 Monthly Operating Report for University of Missouri Research Reactor ML0522902712005-08-0808 August 2005 July 2005 Monthly Operations Summary for University of Missouri Columbia Research Reactor ML0520200662005-07-0808 July 2005 June 2005 Monthly Operating Report for University of Missouri - Columbia Research Reactor ML0518703492005-06-20020 June 2005 May 2005 Monthly Operating Report for University of Missouri- Columbia Research Reactor ML0514502802005-05-13013 May 2005 April 2005 Monthly Operating Report for University of Missouri- Columbia Research Reactor ML0511703642005-04-18018 April 2005 March 2005 Monthly Operating Report for University of Missouri Research Reactor ML0505503112005-02-15015 February 2005 January 2005 Monthly Operating Report for University of Missouri Research Reactor Facility ML0502101962005-01-0707 January 2005 December 2004 Monthly Operating Report for University of Missouri Research Reactor Facility ML0435802382004-12-10010 December 2004 November 2004 Monthly Operating Report for University of Missouri Research Reactor Facility ML0432702102004-11-11011 November 2004 October 2004 Monthly Operating Report for University of Missouri Research Reactor Facility ML0429904612004-10-12012 October 2004 September 2004 Monthly Operations Report for University of Missouri Research Reactor Facility ML0428206152004-09-24024 September 2004 August 2004 Monthly Operating Report for the University of Missouri-Columbia Research Reactor Facility ML0423900832004-08-18018 August 2004 July 2004 Monthly Operating Report for University of Missouri Research Reactor Facility ML0420302892004-07-13013 July 2004 June 2004 Monthly Operating Report for University of Missouri Research Reactor Facility ML0414801392004-05-13013 May 2004 April 2004 Monthly Operating Report for University of Missouri-Columbia Research Reactor Center ML0407902462004-03-11011 March 2004 February 2004 Monthly Operating Report for University of Missouri Research Reactor ML0407803072004-03-0202 March 2004 January 2004 Monthly Operating Report for Univ of Missouri Research Reactor ML0402307052004-01-12012 January 2004 December 2003 Monthly Operating Report for University of Missouri-Columbia Research Reactor Center ML0400606252003-12-22022 December 2003 November 2003 Monthly Operating Report for the University of Missouri-Columbia Research Reactor Center ML0335806022003-11-17017 November 2003 October 2003 Monthly Operating Report for Univ of Missouri Research Reactor Center ML0330304522003-10-17017 October 2003 September 2003 Monthly Operating Report for Univ of Missouri-Columbia ML0325213632003-08-19019 August 2003 July 2003 Monthly Operating Report for University of Missouri Research Reactor ML0317004812003-06-11011 June 2003 May 2003 Monthly Operating Report for University of Missouri Research Reactor ML0314302682003-05-15015 May 2003 April 2003 Monthly Operating Report for University of Missouri ML0311206212003-04-0707 April 2003 March 2003 Monthly Operating Report for University of Missouri-Columbia Research Reactor ML0307204212003-03-0606 March 2003 February 2003 Monthly Operating Report for University of Missouri Research Reactor ML0305702842003-02-0707 February 2003 January 2003 Monthly Operating Report for Univ of Missouri-Columbia ML0302402732003-01-10010 January 2003 December 2002 Monthly Operating Report for University of Missouri Reseach Reactor ML0300900982002-12-30030 December 2002 November 2002 Monthly Operating Report for MURR ML0232303492002-11-0505 November 2002 September 2002 Monthly Operating Report for University of Missouri - Columbia Reactor ML0224902142002-08-29029 August 2002 July 2002 Monthly Operating Report for Univ of Missouri Research Reactor ML0222002252002-07-23023 July 2002 June 2002 Monthly Operating Report for University of Missouri Research Reactor ML0217600242002-06-10010 June 2002 April 2002 Monthly Operating Report for Univ of Missouri-Columbia, Research Reactor Center ML0214104282002-04-29029 April 2002 March 2002 Monthly Operating Report for University of Missouri-Columbia Research Reactor Center ML0209502952002-03-15015 March 2002 February 2002 Monthly Operating Report for University of Missouri Research Reactor ML0202901932002-01-22022 January 2002 December 2001 Monthly Operating Report for the University of Missouri-Columbia 2005-09-09
[Table view] |
Text
9 Research Park Research Reactor Center Columbia, MO 65211 University of Missouri-Columbia PHONE (573) 882-4211 FAx (573) 882-6360 50 February 07, 2003 Mr. Alexander Adams, Jr.
U.S. Nuclear Regulatory Commission Mail Stop 012-G13 Washington, DC 20555-0001
SUBJECT:
Monthly Operations Summary Enclosed is a copy of MURR's Monthly Operations Summary for January, 2003. If you have any questions, please contact me at (573) 882-5276.
Sincerely, Leslie Foyto Interim Reactor Manager LM/lmcg cc. Craig Bassett Enclosure AC-m EQUAL OPPOrTUNrY/ADA INST'fflON
l :ý lid
INTRODUCTION The reactor operated continuously in January with the following exceptions: four shutdowns for scheduled maintenance and refueling; no unscheduled shutdowns.
MAINTENANCE ACTIVITIES 1/6/03 Refueled - removed core 02-67, loaded core 03-01.
1/13/03 Refueled - removed core 03-01, loaded core 03-02.
1/20/03 Refueled - removed core 03-02, loaded core 03-03.
1/23/03 Inspected two end-of-life fuel elements in accordance with Technical Specification 5.5.
1/27/03 Refueled - removed core 03-03, loaded core 03-04.
OPERATION
SUMMARY
FOR MONTH OF University of Missour Research Reactor Center (MURR)
HOURS OPERATED THIS PERIOD M90.34 TOTAL HOURS OPERATED, REACTOR 248,047.92 HOURS OPERATED AT FULL POWER, THIS PERIOD I 687.02 I TOTAL HOURS AT FULL POWER, REACTOR INTEGRATED POWER THIS PERIOD 286.35 MWD TOTAL INTEGRATED POWER, REACTOR I ,l.e.6o IMWD Submitted by: j w9s 'K MWD Custodian/Reactor Physicist Date: _/L / 0-3