ML111320302

From kanterella
Revision as of 23:45, 12 November 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
IR 05000315-11-011, on 05000316/2011011, 03/23/2011 - 04/29/2011; D. C. Cook Nuclear Power Plant Temporary Instruction 2515/183 - Followup to the Fukushima Daiichi Nuclear Station Fuel Damage Event
ML111320302
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 05/13/2011
From: Jamnes Cameron
NRC/RGN-III/DRP/B6
To: Weber L
Nuclear Generation Group, Indiana Michigan Power Co
References
IR-11-011
Download: ML111320302 (23)


See also: IR 05000315/2011011

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210

LISLE, IL 60532-4352

May 13, 2011

Mr. Larry Weber

Senior Vice President and

Chief Nuclear Officer

Indiana Michigan Power Company

Nuclear Generation Group

One Cook Place

Bridgman, MI 49106

SUBJECT: D. C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 - NRC TEMPORARY

INSTRUCTION 2515/183 INSPECTION REPORT 05000315/2011011;

05000316/2011011

Dear Mr. Weber:

On April 29, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

your D. C. Cook Nuclear Power Plant, Units 1 and 2, using Temporary Instruction (TI) 2515/183,

Followup to the Fukushima Daiichi Nuclear Station Fuel Damage Event. The enclosed

inspection report documents the inspection results which were discussed on April 29, 2011,

with Mr. J. Gebbie, and other members of your staff.

The objective of this inspection was to promptly assess the capabilities of the D. C. Cook

Nuclear Power Plant to respond to extraordinary consequences similar to those that have

recently occurred at the Japanese Fukushima Daiichi Nuclear Station. The results from this

inspection, along with the results from this inspection performed at other operating commercial

nuclear plants in the United States will be used to evaluate the U.S. nuclear industrys readiness

to safely respond to similar events. These results will also help the NRC to determine if

additional regulatory actions are warranted.

All of the potential issues and observations identified by this inspection are contained in this

report. The NRCs Reactor Oversight Process will further evaluate any issues to determine if

they are regulatory findings or violations. Any resulting findings or violations will be documented

by the NRC in a separate report. You are not required to respond to this letter.

L. Weber -2-

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter

and its enclosure will be made available electronically for public inspection in the NRC

Public Document Room or from the Publicly Available Records (PARS) component of

NRCs document system (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Jamnes L. Cameron, Chief

Branch 6

Division of Reactor Projects

Docket Nos. 50-315; 50-316

License Nos. DPR-58; DPR-74

Enclosure: Inspection Report 05000315/2011011; 05000316/2011011

cc w/encl: Distribution via ListServ

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket Nos: 05000315; 05000316

License Nos: DPR-58; DPR-74

Report No: 05000315/2011011; 05000316/2011011

Licensee: Indiana Michigan Power Company

Facility: D. C. Cook Nuclear Power Plant, Units 1 and 2

Location: Bridgman, MI

Dates: March 23, 2011, through April 29, 2011

Inspectors: J. Lennartz, Senior Resident Inspector

P. LaFlamme, Resident Inspector

Approved by: Jamnes L. Cameron, Chief

Branch 6

Division of Reactor Projects

Enclosure

INSPECTION SCOPE

IR 05000315/2011011; 05000316/2011011, 03/23/2011 - 04/29/2011; D. C. Cook Nuclear

Power Plant Temporary Instruction 2515/183 - Followup to the Fukushima Daiichi Nuclear

Station Fuel Damage Event.

This report covers an announced Temporary Instruction inspection. The inspection was

conducted by resident inspectors. The NRCs program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 4, dated December 2006.

INSPECTION SCOPE

The intent of the TI is to provide a broad overview of the industrys preparedness for events

that may exceed the current design basis for a plant. The focus of the TI was on (1) assessing

the licensees capability to mitigate consequences from large fires or explosions on site,

(2) assessing the licensees capability to mitigate station blackout (SBO) conditions,

(3) assessing the licensees capability to mitigate internal and external flooding events

accounted for by the stations design, and (4) assessing the thoroughness of the licensees walk

downs and inspections of important equipment needed to mitigate fire and flood events to

identify the potential that the equipments function could be lost during seismic events possible

for the site. If necessary, a more specific follow-up inspection will be performed at a later date.

INSPECTION RESULTS

All of the potential issues and observations identified by this inspection are contained in this

report. The NRCs Reactor Oversight Process will further evaluate any issues to determine if

they are regulatory findings or violations. Any resulting findings or violations will be documented

by the NRC in a separate report.

1 Enclosure

03.01 Assess the licensees capability to mitigate conditions that result from beyond design basis events, typically bounded

by security threats, committed to as part of NRC Security Order Section B.5.b issued February 25, 2002, and severe accident

management guidelines and as required by Title 10 of the Code of Federal Regulations (10 CFR) 50.54(hh). Use Inspection

Procedure (IP) 71111.05T, Fire Protection (Triennial), Section 02.03 and 03.03 as a guideline. If IP 71111.05T was recently

performed at the facility the inspector should review the inspection results and findings to identify any other potential areas of

inspection. Particular emphasis should be placed on strategies related to the spent fuel pool. The inspection should include,

but not be limited to, an assessment of any licensee actions to:

Licensee Action Describe what the licensee did to test or inspect equipment.

a. Verify through test or Licensee actions included identifying the equipment (active and passive) as directed

inspection that equipment is by the Extensive Damage Mitigation Guidelines (EDMGs) utilized for implementing

available and functional. Active B.5.b actions and the Severe Accident Management Guidelines (SAMGs). The

equipment shall be tested and scope was defined as that equipment specifically designated for B.5.b or SAMG

passive equipment shall be mitigation (i.e., special hoses, fittings, onsite fire truck, etc.). All equipment,

walked down and inspected. It permanent and temporary, that is used to perform the EDMGs was walked down to

is not expected that verify the equipment was in the correct physical location, and properly labeled. All

permanently installed procedures were reviewed and, based on the in-plant walkdowns, credited equipment

equipment that is tested under was verified to be able to meet the EDMGs functional requirements. Licensee

an existing regulatory testing personnel then identified surveillances/tests and performance frequencies for the

program be retested. identified equipment and reviewed the results of recent tests. Also, active equipment

within the scope defined above that was not permanently installed was tested (i.e.,

This review should be done for plant fire truck was tested to verify the capability to meet specified pressure and

a reasonable sample of flow).

mitigating

strategies/equipment.

2 Enclosure

Describe inspector actions taken to confirm equipment readiness

(e.g., observed a test, reviewed test results, discussed actions, reviewed

records, etc.).

The inspectors assessed the licensees capabilities by reviewing the licensees

walkdown activities and previously performed surveillance tests. In addition, the

inspectors independently walked down and inspected all major B.5.b contingency

response equipment staged throughout the site and verified that required testing had

been completed satisfactorily. This included verifying that hoses, fittings, the onsite

fire truck, tool boxes, ladders, quick identifiers/ tags and labels were accounted for,

properly staged and in adequate material condition as specified by plant procedures.

Discuss general results including corrective actions by licensee.

Licensee personnel identified that components used for implementing the loss of

spent fuel pool procedure required enhanced labeling. The inspectors verified this

issue was entered into the licensees corrective action program.

The inspectors did not identify any issues of concern.

Describe the licensees actions to verify that procedures are in place and can

Licensee Action

be executed (e.g. walkdowns, demonstrations, tests, etc.)

b. Verify through walkdowns or The licensee performed walkdowns and demonstrations using their Abnormal

demonstration that procedures Operating Procedures, EDMG, and SAMG procedures credited for B.5.b strategy

to implement the strategies actions. The licensees walkdowns included using Auxiliary Equipment Operators to

associated with B.5.b and lay out hoses required to provide water as credited in their B.5.b analysis, and

10 CFR 50.54(hh) are in place verifying valve lineups using drawings for credited flow paths. The licensee

and are executable. Licensees evaluated their ability to perform the procedures, as well as a review of equipment

may choose not to connect or and plant accessibility needed to perform proceduralized actions.

operate permanently installed

equipment during this

verification.

3 Enclosure

This review should be done for Describe inspector actions and the sample strategies reviewed. Assess

a reasonable sample of whether procedures were in place and could be used as intended.

mitigating

strategies/equipment. The inspectors assessed the licensees capabilities by reviewing the licensees

walkdown activities. In addition, the inspectors walked down several procedure

sections that were walked down by the licensee to independently verify the licensees

conclusions. These walkdowns included verifying actions required by operators to

mitigate a loss of spent fuel pool inventory and/or cooling; to mitigate a large fire; to

establish alternate refueling water storage tank makeup; to support steam generator

depressurization; to flood containment for core cooling; and to establish an alternate

supply to the turbine driven auxiliary feedwater pump, could be accomplished as

specified by the procedures.

Discuss general results including corrective actions by licensee.

The licensee identified that the procedure for a loss of spent fuel pool cooling should

be enhanced to include instructions for closing the weir gate, which separates the

fuel transfer canal from the spent fuel pool. The inspectors verified that this condition

was entered into the licensees corrective action program.

The inspectors did not identify any issues of concern.

Describe the licensees actions and conclusions regarding training and

Licensee Action

qualifications of operators and support staff.

c. Verify the training and The licensee reviewed the required training and qualifications of staff needed for

qualifications of operators and activities related to B.5.b and SAMG procedures to verify that they were current,

the support staff needed to which included qualification requirements for the fire brigade, operations personnel,

implement the procedures and and the emergency response organization. Additionally, the licensee reviewed the

work instructions are current number of individuals qualified for each of the positions in each department to ensure

for activities related to Security credited actions could be performed.

Order Section B.5.b and Describe inspector actions and the sample strategies reviewed to assess

severe accident management training and qualifications of operators and support staff

guidelines as required by

10 CFR 50.54 (hh). The inspectors assessed the licensees training and qualification activities by

reviewing training and qualification materials, and records related to B.5.b and SAMG

event response training. Additionally, the inspectors verified that the training was

documented and current. Specifically, the inspectors reviewed a sample of training

lesson plans, attendance verification sheets, and training slides.

4 Enclosure

Discuss general results including corrective actions by licensee.

Licensee personnel identified that continuing training on SAMG and B.5.b strategies

for the emergency response organization decision makers had not been done in

2010. The inspectors verified that this condition was entered into the licensees

corrective action program.

The inspectors did not identify any issues of concern.

Describe the licensees actions and conclusions regarding applicable

Licensee Action

agreements and contracts that are in place.

d. Verify that any applicable The licensee reviewed their procedures and commitments to determine what

agreements and contracts are agreements or contracts would be needed to support necessary B.5.b and SAMG

in place and are capable of actions. The licensee verified that applicable agreements and contracts were in

meeting the conditions needed place and current, and that they were capable of meeting the conditions needed to

to mitigate the consequences mitigate the consequences of events related to B.5.b and SAMG actions.

of these events. For a sample of mitigating strategies involving contracts or agreements with

offsite entities, describe inspector actions to confirm agreements and

This review should be done for contracts are in place and current (e.g., confirm that offsite fire assistance

a reasonable sample of agreement is in place and current).

mitigating

The inspectors reviewed the licensees B.5.b commitments and that verified the

strategies/equipment.

licensee had the appropriate letters of agreement and contracts in place. The

inspectors sampled the letters of agreement and contracts to verify that they were

current and that they could reasonably meet the conditions needed to mitigate the

consequences of these events. The sample included agreements with state and

local officials, the local health care provider, and local offsite fire departments.

Discuss general results including corrective actions by licensee.

The inspectors did not identify any issues of concern or any conditions requiring

corrective actions.

5 Enclosure

Document the corrective action report number and briefly summarize problems

Licensee Action noted by the licensee that have significant potential to prevent the success of

any existing mitigating strategy.

e. Review any open corrective The following Action Requests (AR) were entered into the licensees Corrective

action documents to assess Action Program in response to issues identified in Section 03.01:

problems with mitigating

strategy implementation AR 2011-3416 - Enhance 12-OHP-4021-018-001, Loss Of Spent Fuel Pit Cooling.

identified by the licensee. AR 2011-4027 - SAMG, EDM, B.5.6 Training Not Given as Required by TPD-600-

Assess the impact of the EPT, Emergency Preparedness Training Program Description.

problem on the mitigating

capability and the remaining The inspectors reviewed each AR and did not identify any significant potential to

capability that is not impacted. impact the licensees mitigation strategy.

03.02 Assess the licensees capability to mitigate station blackout (SBO) conditions, as required by 10 CFR 50.63, Loss of

All Alternating Current Power, and station design, is functional and valid. Refer to TI 2515/120, Inspection of

Implementation of Station Blackout Rule Multi-Plant Action Item A-22 as a guideline. It is not intended that TI 2515/120 be

completely reinspected. The inspection should include, but not be limited to, an assessment of any licensee actions to:

Describe the licensees actions to verify the adequacy of equipment needed to

Licensee Action

mitigate an SBO event.

a. Verify through walkdowns and Licensee actions included identifying equipment utilized/required to mitigate an SBO

inspection that all required and conducting walkdowns to ensure that the equipment was in adequate material

materials are adequate and condition and properly staged.

properly staged, tested, and Describe inspector actions to verify equipment is available and useable.

maintained. The inspectors assessed the licensees capability to mitigate SBO conditions by

reviewing the licensees walkdown activities. In addition, the inspectors selected a

sample of equipment utilized/required to mitigate an SBO and independently walked

down that equipment to verify that the equipment was properly aligned and staged.

The sample of equipment selected by the inspectors included tool boxes, ladders,

and hoses that were staged in the 765 kilovolt (KV), 345 KV and 69 KV switchyards,

the 4 KV switchgear rooms, the emergency diesel generator rooms and the auxiliary

building.

6 Enclosure

Discuss general results including corrective actions by licensee.

The licensee identified during material staging walk downs that hoses for aligning

demineralized water to the spent fuel pool during a loss of inventory needed to be

designated and staged in closer proximity to the spent fuel pool. Additionally, the

licensee identified that specified materials required to repair or reduce spent fuel pool

leakage are currently stored off site and need to be stored on site. The inspectors

verified these conditions were entered into the licensees corrective action program.

The inspectors did not identify any issues of concern.

Licensee Action Describe the licensees actions to verify the capability to mitigate an SBO event.

b. Demonstrate through Licensee actions included identifying the time critical operator actions associated with

walkdowns that procedures for an SBO. These actions were then walked down and validated during the

response to an SBO are performance of a simulator scenario on April 8, 2011, consisting of a dual unit loss of

executable. offsite power and an SBO in Unit 1.

Describe inspector actions to assess whether procedures were in place and

could be used as intended.

The inspectors reviewed the procedure actions associated with the loss of all

Alternating Current (AC) power, restoration of 4KV power and supplemental diesel

generators, loss of component cooling water, and steam generator level and power

operated relief valve control. The inspectors also observed the simulator scenario on

April 8, 2011, to compare the procedure actions with the time critical actions

implemented during the simulator scenario.

Discuss general results including corrective actions by licensee.

The inspectors concluded that the time critical operator actions were executable and

reasonable and did not identify any conditions requiring corrective actions.

7 Enclosure

03.03 Assess the licensees capability to mitigate internal and external flooding events required by station design. Refer to

IP 71111.01, Adverse Weather Protection, Section 02.04, Evaluate Readiness to Cope with External Flooding as a

guideline. The inspection should include, but not be limited to, an assessment of any licensee actions to verify through

walkdowns and inspections that all required materials and equipment are adequate and properly staged. These walkdowns

and inspections shall include verification that accessible doors, barriers, and penetration seals are functional.

Describe the licensees actions to verify the capability to mitigate existing

Licensee Action

design basis flooding events.

a. Verify through walkdowns and Licensee actions included identifying equipment, structures and penetration seals

inspection that all required utilized/required to mitigate internal and external flooding. The licensee then

materials are adequate and walked down the equipment to ensure that it was adequate and properly staged.

properly staged, tested, and Doors, barriers, sumps, berms and penetration seals that were utilized to mitigate

maintained. flooding were identified and inspected. In addition, the licensee reviewed

maintenance and surveillance testing history for the Structures, Systems, and

Components (SSCs) credited to mitigate internal and external flooding events.

Describe inspector actions to verify equipment is available and useable.

Assess whether procedures were in place and could be used as intended.

The inspectors assessed the licensees capabilities to mitigate flooding by

reviewing the licensees walkdown activities. In several instances, these reviews

involved the inspectors accompanying licensee engineering personnel during in-

field walkdowns. In addition, the inspectors independently walked down selected

flood mitigation equipment to further assess the licensees flood mitigating

capabilities. Licensee flood mitigation procedures and flooding analysis were also

reviewed to verify usability and accuracy.

Discuss general results including corrective actions by licensee.

The licensee identified that the turbine building sump vault hatch did not have a

periodic maintenance activity to inspect/repair the hatch. The inspectors verified

that this condition was entered into the licensees corrective action program.

The inspectors concluded that useable procedures and equipment were in place

and available to mitigate the most limiting flooding events, which was a circulating

water pipe expansion joint rupture or turbine building sump check valve failure

during a postulated 11 foot seiche coupled with an historical high lake level of

583.6 feet above sea level.

8 Enclosure

Describe the licensees actions to assess the potential impact of seismic events

Licensee Action

on the availability of equipment used in fire and flooding mitigation strategies.

b. Verify through walkdowns that Licensee actions included identifying equipment utilized/required to mitigate fire and

all required materials are flood events. Plant walkdowns were performed to assess functionality of important

adequate and properly equipment needed to mitigate a flood or fire following a design basis earthquake.

staged, tested, and Walk downs included external visual inspections of associated pumps, diesels,

maintained. motors, breakers, pipes, valves, tanks, intake structures, hoses, and fittings. The

material condition of surrounding equipment and structures, including the structure

that houses the credited equipment, were also inspected. Non-seismic equipment and

structures were visually inspected to determine if any surrounding SSCs could be

adversely impacted due to seismic interaction.

Describe inspector actions to verify equipment is available and useable.

Assess whether procedures were in place and could be used as intended.

The inspectors accompanied licensee personnel on selected walkdowns to verify the

licensees actions and assess their adequacy. Additionally, the inspectors

independently walked down fire piping, fire mitigating components, the B.5.b fire truck,

B.5.b related equipment, flooding barriers, and areas susceptible to flooding. The

walkdown included the residual heat removal and containment spray pump rooms,

emergency diesel generator rooms, fire water storage tank yard and the screen house

intake structure. The inspectors assessment was consistent with the licensees

conclusions that there were a few potential seismic vulnerabilities that need to be

evaluated, as described below.

Discuss general results including corrective actions by licensee. Briefly

summarize any new mitigating strategies identified by the licensee as a result of

their reviews.

The licensee identified four potential deficiencies as summarized below:

1) The licensee noted that the alarms in the condenser pits and the auxiliary

building sump that are credited to alert operators to take action to mitigate

internally flooding are both non safety-related and non-seismic. Therefore,

seismic response procedures will be enhanced to have Auxiliary Equipment

Operators check the turbine and auxiliary buildings for internal flooding as

soon as possible in order to assist control room operators in taking action to

mitigate/terminate the event.

9 Enclosure

2) The licensee identified that during an external flooding event due to a seiche,

the west wall of the turbine building is credited for preventing flooding on the

turbine building 591 foot elevation. However, documentation could not be

found to verify that the turbine building west wall that extends beyond the

screenhouse was Seismic Class I. Therefore, structural design engineering

will evaluate if the wall can be analyzed to be seismically qualified, or if it has

to be modified.

3) The license identified that although the plant is designed with diverse sources

of fire protection equipment and water sources to supply fire mitigation

equipment, this equipment and its associated water sources are not designed

and installed to Seismic Class I requirements. Therefore, the licensee will

evaluate the need to develop mitigating strategies to provide additional means

of mitigating a fire following a seismic event.

4) The licensee identified that the plant fire truck is currently housed in a structure

on site that is not designed to Seismic Class I requirements. Therefore, the

licensee will evaluate the need to relocate the fire truck to a Seismic Class I

structure or to a location that would not present a seismic hazard to the

equipment.

The inspectors verified that all of these issues were entered into the licensees

corrective action program.

The inspectors did not identify any issues of concern.

10 Enclosure

03.04 Assess the thoroughness of the licensees walkdowns and inspections of important equipment needed to mitigate fire

and flood events to identify the potential that the equipments function could be lost during seismic events possible for the

site. Assess the licensees development of any new mitigating strategies for identified vulnerabilities (e.g., entered it in to the

corrective action program and any immediate actions taken). As a minimum, the licensee should have performed walkdowns

and inspections of important equipment (permanent and temporary) such as storage tanks, plant water intake structures,

and fire and flood response equipment; and developed mitigating strategies to cope with the loss of that important function.

Use IP 71111.21, Component Design Basis Inspection, Appendix 3, Component Walkdown Considerations, as a

guideline to assess the thoroughness of the licensees walkdowns and inspections.

Describe the licensees actions to assess the potential impact of seismic

Licensee Action events on the availability of equipment used in fire and flooding mitigation

strategies.

a. Verify through walkdowns that Licensee actions included identifying equipment utilized/required to mitigate fire and

all required materials are flood events. Plant walkdowns were performed to assess functionality of important

adequate and properly equipment needed to mitigate a flood or fire following a design basis earthquake.

staged, tested, and Walk downs included external visual inspections of associated pumps, diesels,

maintained. motors, breakers, pipes, valves, tanks, intake structures, hoses, and fittings. The

material condition of surrounding equipment and structures, including the structure

that houses the credited equipment, were also inspected. Non-seismic equipment

and structures were visually inspected to determine if any surrounding SSCs could be

adversely impacted due to seismic interaction.

Describe inspector actions to verify equipment is available and useable.

Assess whether procedures were in place and could be used as intended.

The inspectors accompanied licensee personnel on selected walkdowns to verify the

licensees actions and assess their adequacy. Additionally, the inspectors

independently walked down fire piping, fire mitigating components, the B.5.b fire

truck, B.5.b related equipment, flooding barriers, and areas susceptible to flooding.

The walkdown included the residual heat removal and containment spray pump

rooms, emergency diesel generator rooms, fire water storage tank yard and the

screen house intake structure. The inspector's assessment was consistent with the

licensees conclusions that there were a few potential seismic vulnerabilities that

need to be evaluated, as described below.

11 Enclosure

Discuss general results including corrective actions by licensee.

Briefly summarize any new mitigating strategies identified by the licensee as a

result of their reviews.

The licensee identified four potential deficiencies as summarized below:

1) The licensee noted that the alarms in the condenser pits and the auxiliary

building sump that are credited to alert operators to take action to mitigate

internally flooding are both non safety-related and non-seismic. Therefore,

seismic response procedures will be enhanced to have Auxiliary Equipment

Operators check the turbine and auxiliary buildings for internal flooding as

soon as possible in order to assist control room operators in taking action to

mitigate/terminate the event.

2) The licensee identified that during an external flooding event due to a seiche,

the west wall of the turbine building is credited for preventing flooding on the

turbine building 591 foot elevation. However, documentation could not be

found to verify that the turbine building west wall that extends beyond the

screenhouse was Seismic Class I. Therefore, structural design engineering

will evaluate if the wall can be analyzed to be seismically qualified, or if it has

to be modified.

3) The license identified that although the plant is designed with diverse sources

of fire protection equipment and water sources to supply fire mitigation

equipment, this equipment and its associated water sources are not designed

and installed to Seismic Class I requirements. Therefore, the licensee will

evaluate the need to develop mitigating strategies to provide additional means

of mitigating a fire following a seismic event.

4) The licensee identified that the plant fire truck is currently housed in a

structure on site that is not designed to Seismic Class I requirements.

Therefore, the licensee will evaluate the need to relocate the fire truck to a

Seismic Class I structure or to a location that would not present a seismic

hazard to the equipment.

The inspectors verified that all of these issues were entered into the licensees

corrective action program.

The inspectors did not identify any issues of concern.

12 Enclosure

Meetings

.1 Exit Meeting

The inspectors presented the inspection results to Mr. J. Gebbie and other members of

licensee management on April 29, 2011. The inspectors asked the licensee whether

any materials examined during the inspection should be considered proprietary. No

proprietary information was identified.

13 Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

J. Gebbie, Site Vice President

Q. Lies, Plant Manager

D. Cobb, Maintenance Manager, WIN Team

G. Curten, Design Engineering, Mechanical

R. Pletz, Fire Protection and Safety Services Supervisor

M. Scarpello, Regulatory Affairs Manager

Nuclear Regulatory Commission

J. Cameron, Chief, Reactor Projects Branch 6/DRP/RIII

14 Enclosure

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply that the NRC inspectors reviewed the documents in their entirety but rather that

selected sections of portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

03.01 Assess the licensees capability to mitigate conditions that result from beyond design

basis events

Number Description or Title Date or

Revision

Fire Pre-Plans Fire Protection Response to a Large Fire or Revision 12

Explosion Event

Berrien County Emergency Management Memorandum of February 1,

Understanding 2010

Lake Township Fire and Rescue Memorandum of November 17,

Understanding 2010

Bridgman City Fire Department Memorandum of December 6,

Understanding 2010

Lakeland HealthCare Memorandum of Understanding November 5,

2010

Medic1 Ambulance Memorandum of Understanding December 21,

2010

Entergy, Palisades Nuclear Plant Reciprocal Laboratory Use October 14,

Agreement 2010

Mutual Assistance Agreement between Detroit Edison, November 5,

Entergy Nuclear Palisades, LLC, and Indiana Michigan Power 2010

Nuclear Power Plant Emergency Response Voluntary January 17.

Assistance Agreement 2007

Voluntary Assistance Agreement by and Among Electric January 17,

Utilities Involved in Transportation of Nuclear Materials 2007

Berrien County Sherriffs Department Memorandum of November 9,

Understanding 2010

Michigan State Police Memorandum of Understanding September 26,

2008

12-OHP-4022- Loss of Spent Fuel Pit Cooling Revision 13

018-001

12-OHP-4026- Extensive Damage Mitigation Initial Response November 18,

EDM-001 2008

12-OHP-4026- Extensive Damage Mitigation Enhanced Site Response November 18,

EDM-002 Strategies 2008

12-OHP-4026- Extensive Damage Mitigation Resource Management November 18,

EDM-003 Guidance 2008

12-OHP-5030- Appendix R Toolbox and Ladder Inventory Revision 3

APR-001

AR 2011-3416 Enhance 12-OHP-4022-018-001 Loss of Spent Fuel Pit

Cooling

AR 2011-4027 SAMG, EDM, B.5.b Training Not Given as Reqd by TPD-600-

EPT

15 Enclosure

AR 2011-4983 Appendix R Toolbox Electrical Tape Not Correct Type By

Procedure

Donald C. Fukushima Daiichi Nuclear Station Fuel Damage Caused by April 15, 2011

Cook Nuclear Earthquake and Tsunami Action Plan Response

Plant

Lesson Plan Abnormal/ Emergency Tasks August 12,

AE-C-00104 2008

Lesson Plan Auxiliary Equipment Operators Continuing Training Revision 0

AE-C-EDMG

Lesson Plan B.5.b EDMG3 February 28,

AE-J-3322 2009

Lesson Plan Validated SEC Threat/Extensive Damage Mitigation November 8,

RQ-C-3245 2007

Lesson Plan License Operator Requalification SAMG/SACRG Review Revision 0

RQ-C-3614

Lesson Plan Licensee Operator Requalification Dual Unit Training Scenario Revision 0

RQ-S-3601-D1

OP-12-5132- Flow Diagram CVCS-Boron Hold up Boric Acid Reserve Tank Revision 29

29 Units 1 & 2

SAMG SAG-1 Feeding Steam Generators April 8, 2009

SAMG SAG-2 Depressurize RCS April 8, 2009

SAMG SAG-4 Inject Into Containment April 8, 2009

SAMG-1 Severe Accident Management Guidance Manual April 10, 2007

WO 55367675- Appendix R Toolbox and Ladder Inventory January 29,

01 2001

03.02 Assess the licensees capability to mitigate station blackout (SBO) conditions

Number Description or Title Date or

Revision

12-OHP-4021- Supplemental Diesel Generator Operations Revision 6

033-001

12-OHP-4023- Restoration of 4KV Power from EP Revision 7

SUP-009

1-OHP-4021- Initiating or Restoring From ESW Cooling To Air Handling Revision 26

028-014, Units Following A Failure of Both Chiller Packages

Attachment 6

1-OHP-4022- Loss of Condensate to Auxiliary Feedwater Pumps Revision 9

055-003

1-OHP-4023- Loss of All AC Power Revision 25

ECA-0.0

1-OHP-4025- Restore Diesel Generators Revision 4

R-13

2-OHP-4022- Loss of Component Cooling Water Revision 19

016-004

2-OHP-4023- Loss of All AC Power Revision 24

ECA-0.0

2-OHP-4025- Steam Generator 2/3 Level Control Revision 4

LS-3

2-OHP-4025- Component Restoration Revision 6

R-12

16 Enclosure

2-OHP-4025- Restore Electrical System Revision 2

R-8

03.03 Assess the licensees capability to mitigate internal and external flooding events required

by station design

Number Description or Title Date or

Revision

12-OHP-4022- Seiche August 12,

001-009 2010

1-OHP-4024- Annunciator #124 Response: Containment March 9 2007

124

MD-12-CW- Flooding Due to Circulating Water Expansion Joint Failure April 6, 2006

005-N

MD-12-SCRN- Screen House Internal Flood Levels January 15,

001-N 2009

SD-061206- Flooding Evaluation Report for D.C. Cook Power Plant Revision 2

001

WO 55311728- 12-DR-129, Inspect for Functionality/ Corrosion / Degradation July 13, 2010

02

WO 55325852- Inspect and Lube Watertight Doors per ME.DOOR.001 August 26,

01, MTM 2009

03.04 Assess the thoroughness of the licensees walkdowns and inspections of important

equipment needed to mitigate fire and flood events to identify the potential that the

equipments function could be lost during seismic events

Number Description or Title Date or

Revision

DCC-PV-12- Flood Protection Features October 14,

MC17-N 2001

DCC-PV-12- Flood Protection November 23,

MC33-N 1994

DIT-B-02531- Seismic Class I Boundaries October 23,

00 2002

N920101 Fire Protection Storage Tanks at Cook Plant February 11,

1992

OP-125152-14 Flow Diagram Fire Protection-Water Yard Piping Unit 1 & 2 Revision 14

17 Enclosure

LIST OF ACRONYMS USED

AC Alternating Current

ADAMS Agencywide Documents Access and Management System

AR Action Request

CFR Code of Federal Regulations

EDMG Extensive Damage Mitigation Guidelines

IP Inspection Procedure

KV Kilovolt

NRC United States Nuclear Regulatory Commission

SAMG Severe Accident Management Guidelines

SBO Station Blackout

SSC Structures, Systems, and Components

TI Temporary Instruction

18 Enclosure

L. Weber -2-

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter

and its enclosure will be made available electronically for public inspection in the NRC

Public Document Room or from the Publicly Available Records (PARS) component of

NRCs document system (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Jamnes L. Cameron, Chief

Branch 6

Division of Reactor Projects

Docket Nos. 50-315; 50-316

License Nos. DPR-58; DPR-74

Enclosure: Inspection Report 05000315/2011011; 05000316/2011011

cc w/encl: Distribution via ListServ

DOCUMENT NAME: G:\DRPIII\1-Secy\1-Work In Progress\TI Reports\Cook 2011 001Rev.docx

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII RIII

NAME J. Rutkowski:dtp J. Cameron

DATE 05/10/11 05/11/11

OFFICIAL RECORD COPY

Letter to L. Weber from J. Cameron dated May 13, 2011.

SUBJECT: D. C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 - NRC TEMPORARY

INSTRUCTION 2515/183 INSPECTION REPORT 05000315/2011011;

05000316/2011011

DISTRIBUTION:

Daniel Merzke

RidsNrrDorlLpl3-1 Resource

RidsNrrPMDCCook Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Steven Orth

Jared Heck

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Patricia Buckley

Tammy Tomczak

ROPreports Resource