IR 05000315/2024011

From kanterella
Jump to navigation Jump to search
NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation
ML24207A211
Person / Time
Site: Cook  
Issue date: 08/30/2024
From: Paul Zurawski
NRC/RGN-III/DORS/OB
To: Lies Q
Indiana Michigan Power Co
References
EA-24-047 IR 2024011
Download: ML24207A211 (1)


Text

August 30, 2024

SUBJECT:

DONALD C. COOK NUCLEAR PLANT - NRC INSPECTION REPORT 05000315/2024011 AND 05000316/2024011 AND NOTICE OF VIOLATION

Dear Q. Shane Lies:

On July 18, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Donald C. Cook Nuclear Plant and discussed the results of this inspection with Kelly Ferneau, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

Based on the results of this inspection, the NRC has determined that two violations of NRC requirements occurred. Specifically, seven operators resumed licensed activities without performing the required plant tour as required by Title 10 of the Code of Federal Regulations (10 CFR) 55.53(f), which resulted in the licensees failure to maintain the minimum licensed operator staffing requirements as required by 10 CFR 50.54 (m)(2)(i). These two violations are being characterized as a Severity Level IV problem.

These violations are normally categorized in accordance with the NRC Enforcement Policy at Severity Level III (see section 6.4.c of the NRC Enforcement Policy). However, the staff determined that the significance of this violation was Severity Level IV because the operators 1) stood a minimal number of watches, 2) did not cause consequential errors while standing watch, and 3) complied with all other requirements (e.g., full participation in the bi-annual requalification program and stood all required proficiency watches).

The Severity Level IV problem was evaluated in accordance with the NRC Enforcement Policy.

The current Enforcement Policy is included on the NRCs website at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html. The problem, which includes two violations, is cited in the enclosed Notice of Violation (NOV) and the circumstances are described in detail in the subject inspection report. The NOV met the criteria for treatment as a non-cited violation; however, because the violation is associated with multiple licensed operators and could have resulted in moderate safety consequences, the NRC determined the issuance of a NOV with a required response was appropriate for this case. You are required to respond to this letter and should follow the instructions specified in the enclosed Notice when preparing your response. Specifically, the response needs to include results of any causal analysis and actions taken to prevent recurrence. The NRCs review of your response will also determine whether further enforcement action is necessary to ensure your compliance with regulatory requirements.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Donald C. Cook Nuclear Plant.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure(s), and your response, will be made available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy or proprietary information so that it can be made available to the Public without redaction.

Sincerely, Paul J. Zurawski, Chief Operations Branch Division of Operating Reactor Safety Docket Nos. 05000315 and 05000316 License Nos. DPR-58 and DPR-74

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000315 and 05000316

License Numbers:

DPR-58 and DPR-74

Report Numbers:

05000315/2024011 and 05000316/2024011

Enterprise Identifier:

I-2024-011-0036

Licensee:

Indiana Michigan Power Company

Facility:

Donald C. Cook Nuclear Plant

Location:

Bridgman, MI

Inspection Dates:

February 26, 2024 to July 18, 2024

Inspectors:

B. Bergeon, Senior Operations Engineer

T. Henning, Senior Operations Engineer

Approved By:

Paul J. Zurawski, Chief

Operations Branch

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an NRC inspection at Donald C. Cook Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to certify operators re-activation in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 55.53(f) results in failures to meet minimum staffing requirements in accordance with 10 CFR 50.54(m)(2)(i).

Cornerstone Severity Cross-Cutting Aspect Report Section Not Applicable Severity Level IV Problem NOV 05000315,05000316/2024011-01 Open EA-24-047 Not Applicable 71111.11B An NRC identified Severity Level IV problem that includes a violation of 10 CFR 55.53(f) for the licensees failure to appropriately certify that seven operators completed the requirements to return their license to an active status prior to resuming functions authorized by the license; and, a violation of 10 CFR 50.54(m)(2)(i) when the licensee failed to meet minimum licensed operator staffing requirements.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from February 14, 2024 to March 14, 2024 and the biennial written examinations completed on March 14, 2024.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on February 29, 2024.

Annual Requalification Operating Tests The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.

Administration of an Annual Requalification Operating Test The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR

INSPECTION RESULTS

Failure to certify operators re-activation in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 55.53(f) results in failure to meet minimum staffing requirements in accordance with 10 CFR 50.54(m)(2)(i).

Cornerstone Severity Cross-Cutting Aspect Report Section Not Applicable Severity Level IV Problem NOV 05000315,05000316/2024011-01 Open EA-24-047 Not Applicable 71111.11B An NRC identified Severity Level IV problem that includes a violation of 10 CFR 55.53(f) for the licensees failure to appropriately certify that seven operators completed the requirements to return their license to an active status prior to resuming functions authorized by the license; and, a violation of 10 CFR 50.54(m)(2)(i) when the licensee failed to meet minimum licensed operator staffing requirements.

Description:

On February 26, 2024, the NRC identified that the licensee failed to certify that seven (7)operators (four

(4) SROs and three
(3) ROs) completed the requirements to return their license to an active status prior to resuming functions authorized by the license. The licensee incorrectly revised operations procedure OHI-2070, OPERATIONS TRAINING AND QUALIFICATION, Revision 72, April 15, 2021, for licensed operator reactivation, which allowed the licensee to N/A steps of the procedure. Specifically, the licensee marked N/A on step F in attachment 5 of the procedure. This allowed operators to forgo completing a plant tour and reviewing shift relief turnover procedures prior to the re-activation of their licenses as required by 10 CFR 55.53(f). As a result, the licensee did not maintain minimum staffing requirements which was a violation of 10 CFR 50.54(m)(2)(i) and Technical Specification (TS) 5.2.2.b.

Corrective Actions: Immediate corrective actions included the facility licensee placing the seven inactive operators (four

(4) senior operators and three
(3) licensed operators) on Administrative HOLD on February 27, 2024, when the issue was identified. The individuals have completed remedial training and were verified to meet all requirements of license reactivation prior to resuming watch standing activities on March 1, 2024. The facility licensee also entered the procedure issue into the corrective action program for revision. The facility licensee is conducting further investigation to identify the cause of the procedure revision that led to the non-compliances. AR 2024-1656 was generated to address this issue.

Corrective Action References: AR 2024-1656

Performance Assessment:

None

Enforcement:

The ROPs significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance. Therefore, it is necessary to address this violation which impedes the NRCs ability to regulate using traditional enforcement to adequately deter non-compliance.

Severity: A Severity Level IV problem was identified based on the facility licensee allowing seven operators to resume licensed activities without performing the required plant tour as required by 10 CFR 55.53(f). Subsequently, the facility licensee operated units 1 and 2 in MODE 1 across eleven

(11) shifts with a Main Control Room Staffing less than the requirements stated in 10 CFR 50.54(m)(2)(i) and TS 5.2.2.b.

These violations are normally categorized in accordance with the NRC Enforcement Policy at Severity Level III (see section 6.4.c of the NRC Enforcement Policy). However, the staff determined that the significance of these violations was Severity Level IV because the operators 1) stood a minimal number of watches, 2) did not cause consequential errors while standing watch, and 3) complied with all other requirements (e.g., full participation in the bi-annual requalification program and stood all required proficiency watches).

Violation: A 10 CFR Section 55.53

(e) requires, in part, if a licensee has not been actively performing the functions of an operator or senior operator, the licensee may not resume activities authorized by a license issued under this part except as permitted by paragraph
(f) of this section. To maintain active status, the licensee shall actively perform the functions of an operator or senior operator on a minimum of seven 8-hour or five 12-hour shifts per calendar quarter.

10 CFR Section 55.53(f), states, in part, if paragraph

(e) of this section is not met, before resumption of functions authorized by a license issued under this part, an authorized representative of the facility licensee shall certify the following:
(1) that the qualifications and status of the licensee are current and valid; and
(2) that the licensee has completed a minimum of 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> of shift functions under the direction of an operator or senior operator as appropriate and in the position to which the individual will be assigned. The 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> must have included a complete tour of the plant and all shift turnover procedures.

TS Section 5.4.1.a. requires, in part, that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978.

NRC Regulatory Guide 1.33, Revision 2, Appendix A, Section 1 addresses Administrative Procedures, Subsection b. addresses Authorities and Responsibilities for Safe Operation and Shutdown, Subsection g. addresses Shift and Relief Turnover, and Subsection k.

addresses Maintenance of Minimum Shift Complement and Call-In of Personnel.

The licensee established Procedure OHI-2070, Operations Training and Qualification, Rev. 72, April 15, 2021, to address the Operations Department training and qualifications policies and expectations.

Contrary to the above, from October 12, 2021 to February 26, 2024, the licensee failed to ensure that seven inactive licensed operators performed a complete tour of the plant and all shift turnover procedures prior to the resumption of functions authorized by their individual licenses issued under 10 CFR Part 55.

Additionally, from April 15, 2021, to February 26, 2024, the licensee failed to maintain an adequate written procedure covering Authorities and Responsibilities for Safe Operation and Shutdown, Shift and Relief Turnover, and Maintenance of Minimum Shift Complement and Call-in of Personnel. Specifically, the site failed to maintain procedure OHI-2070, Operations Training and Qualification, Rev. 72, April 15, 2021, such that it allowed the licensee to mark N/A on step F in attachment 5 of the procedure. Marking this step N/A allowed operators to forgo completing a plant tour and reviewing shift relief turnover procedures prior to the re-activation of their licenses as required by 10 CFR 55.53(f).

Violation: B 10 CFR 50.54(m)(2)(i) requires each licensee shall meet the minimum licensed operator staffing requirements in the following table. The table states the following, Minimum Requirements Per Shift for On-Site staffing of Nuclear Power Units by Operators and Senior Operators Licensed Under 10 CFR Part 55, with two nuclear power units operating, two units/two control rooms, the minimum number of senior operators is three.

TS 5.2.2.b states, in part, "shift crew composition may be less than the minimum requirement of 10 CFR 50.54(m)(2)(i) and Specifications 5.2.2.a and 5.2.2.f for a period of time not to exceed 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> in order to accommodate unexpected absence of on-duty shift crew members provided immediate action is taken to restore the shift crew composition to within the minimum requirements."

Contrary to the above, on 11 occasions between October 14, 2023 to November 14, 2023, the licensee failed to maintain the minimum licensed operator staffing requirements as required by 10 CFR 50.54(m)(2)(i).

Additionally on 11 occasions between October 14, 2023 to November, 14, 2023, the licensee failed to maintain the minimum licensed operator staffing requirements for greater than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, and failed to ensure immediate action was taken to restore shift crew composition to meet the minimum shift staffing requirements as required by TS 5.2.2.b. Specifically, the license failed to ensure the minimum number of senior operators were on shift on the following dates:

Day shifts of 10/14/23, 10/15/23, 10/19/23, 10/24/23, 10/25/23, 10/30/23, 11/4/23, 11/5/23, 11/8/23, 11/13/23, and 11/14/23.

These two violations are being characterized as a Severity Level IV problem.

Enforcement Action: These violations are being cited because the violations are associated with multiple licensed operators and could have resulted in in moderate safety consequences.

The NRC determined the issuance of a Notice of Violation with a required response was appropriate for this case (see Enclosure 2).

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On February 26, 2024, the inspectors conducted an Entrance Meeting with Q. Shane Lies - Chief Nuclear Officer and other members of the licensee staff.
  • On July 18, 2024, the inspectors presented the Exit Meeting inspection results to Kelly Ferneau - Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 2022-4393

Steam Generator 1 & 4 fed During Testing

05/17/2022

AR 2022-8729

U2 RHR Hx - CCW Side Fill and Vent

10/26/2022

AR 2022-9291

U2 Rx Trip

11/10/2022

AR 2023-6037

Bleed Steam Isolation on Clearance Hang

08/23/2023

Corrective Action

Documents

AR 2024-1656

Revision to OHI-2070 for Reactivation of Licenses

2/27/2024

DR 2023053

Turbine Control Valves Fail to Close during ATWS

10/11/2023

DR 2024002

WMFP Control Valve Position Outside Tolerances

01/14/2024

DR 2024005

Pressurizer Liquid and Surge Line Temperature Response to

Control Valve Testing

01/15/2024

EC 53364

Unit 2 RMS Replacement EC-53364

2/21/2022

EC 55284

Fire Protection Panel and Detector Replacement

2/17/2022

EC 57106

Unit 1 Plant Air Compressor Control Panel Replacement

11/13/2022

EC 57671

CVCS Change Calibrated Span of 12-QLA-610/620/630

06/27/2023

GT 2022-0369

TR RHR Loops vs. Trains (From AR 2022-8729)

01/13/2023

GT 2022-5819

TR (LOR) for Use of OV&V (From AR 2022-4393)

07/15/2022

GT 2022-5821

TR (LOR) Condensate / FW Long Path Recirc (From

AR 2022-4393)

07/15/2022

GT 2022-9419

TR MFP Control (From AR 2022-9291)

11/16/2022

GT 2022-9420

TR on Assigning Actions to Trip (From AR 2022-9291)

11/16/2022

GT 2022-9438

TR MFP Speed Control (From AR 2022-9291)

11/16/2022

GT 2023-0201

TR for JITT (Placing MFPs on Service) (From AR 2022-

291)

01/09/2023

GT 2023-4849

TR Operational Risk for Degraded Conditions

06/29/2023

GT 2023-6097

TR on Heater Level Switch Operations

08/25/2023

Job Performance

Measure (JPM)

RO-O-A095-U12

Job Performance

Measure (JPM)

RO-O-AEO-A006

Job Performance

Measure (JPM)

RO-O-E280-U12

71111.11B

Miscellaneous

Job Performance

RO-O-N073D

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Measure (JPM)

Job Performance

Measure (JPM)

SR-O-N0015

Job Performance

Measure (JPM)

RO-O-AEO-E221

Job Performance

Measure (JPM)

RO-O-AEO-E287

Job Performance

Measure (JPM)

RO-O-E026-U12

Job Performance

Measure (JPM)

RO-O-E107A-U12

LRTP (2022-

23)

LOR Long Range Training Plan for 2022 and 2023

OHI-2070

Reactivation (Operator #1)

OHI-2070

Reactivation (Operator #2)

OHI-2070

Reactivation (Operator #3)

OHI-2070

Reactivation (Operator #4)

OHI-2070

Reactivation (Operator #5)

OHI-2070

Reactivation (Operator #6)

OHI-2070

Reactivation (Operator #7)

OHI-2070

Reactivation (Operator #8)

OHI-2070

Reactivation #2 (Operator #4)

RO-I-5400

(Condensate

System)

Lesson Plan

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

RO-I-5500 (Feed

Water System)

Lesson Plan

RO-S-AOP-D4-

U2 (ILT AOP

Scenario)

Simulator Exercise Guide

RQ-C-4765 (LOR

Operations

Review)

Lesson Plan

RQ-C-4815 (LOR

Operations

Review)

Lesson Plan

RQ-S-4707-U2-

T1 (LOR Period

4707 Training

Scenario #1)

Simulator Exercise Guide

RQ-S-4707-U2-

T2 (LOR Period

4707 Training

Scenario #2)

Simulator Exercise Guide

RQ-S-4708-U2-

T1 (LOR Period

4708 Training

Scenario #1)

Simulator Exercise Guide

RQ-S-4802-U2-

T1 (LOR Period

4802 Training

Scenario #1)

Simulator Exercise Guide

Simulator

Evaluation Guide

(SEG)

RQ-E-ANN-26

Simulator

Evaluation Guide

(SEG)

RQ-E-ANN-61

Simulator

RQ-E-ANN-33

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Evaluation Guide

(SEG)

Simulator

Evaluation Guide

(SEG)

RQ-E-ANN-73

TRP-2070-SIM-

001 Data Sheet 1

Unit 1 Simulator Fidelity Assessment List

2/27/2024

TRP-2070-SIM-

001 Data Sheet 1

Unit 2 Simulator Fidelity Assessment List

2/27/2024

Written Exam

24 LORT NRC Crew E RO

2/19/2024

Written Exam

23 LORT NRC Crew E SRO

2/19/2024

OHI-2070

Operations Training & Qualification

OHI-2070

Operations Training & Qualification

OHI-2070

Operations Training & Qualification

OHI-2070

Operations Training & Qualification

OHI-2070

Operations Training & Qualification

OHI-2070

Operations Training & Qualification

OHI-2070

Operations Training & Qualification

OHI-2071

Reporting, Reassignment, Termination, and Conditions

Potentially Affecting Performance of Licensed Duties

OHI-2073

Operations Individual & Team Performance Improvement

OHI-4000

Conduct of Operations: Standards

151

TDG-SIM-004

Reactor Core Testing Guideline - DR 1000877, Unit 1 Cycle

Core Reload

2/07/2024

TPD-600-LOR

LOR Training Program Description

TRP-2070-LIC-

001

NRC License & Medical Requirements

TRP-2070-SIM-

003

23055, Simulator Performance Testing, U1C32 Refueling

Outage Trip

2/19/2024

TRP-2070-SIM-

003

23 ILT Power Escalation RO-C-NOP7 U1

05/22/2023

TRP-2070-SIM-

003

23 ILT Power Reduction, RO-C-NOP1 U1

05/22/2023

Procedures

TRP-2070-SIM-

23 ILT Reactor Startup, RO-C-NOP6 U1

05/23/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

003

TRP-2070-SIM-

003

23 Requal Training NRC Exam RQ-E-ANN11

01/25/2023

TRP-2070-SIM-

003

U1C31 Steady State Testing

07/07/2021

TRP-2070-SIM-

003

U1C32 Transient 3, Simultaneous Closure of all MSIVs

2/22/2023

TRP-2070-SIM-

003

U1C32 Transient 7, Maximum Rate Power Change 100%-

75%-100%

2/22/2023

TRP-2070-SIM-

003

U1C32 Transient 5, Trip of #13 RCP

2/22/2023

TRP-2070-SIM-

003

U1C32 Transient 8, Maximum Size RCS Break w/Loss of

Off-Site Power

2/22/2023

TRP-2070-SIM-

003

U1C32 Transient 10, Stuck Open PORV w/Hi Head Injection

Inhibited

2/12/2024

TRP-2070-SIM-

003

DR 1000281, Unit 2 Cycle 27 Core Reload

2/08/2023

TRP-2070-SIM-

003

24003, Main Turbine CV Testing Event 12/09/2023

2/22/2023

TRP-2070-SIM-

003

22053, U2C27 Refueling Reactor Trip

10/05/2022

TRP-2070-SIM-

003

22 Requal Training NRC Exam RQ-E-ANN13

11/30/2022

TRP-2070-SIM-

003

23 ILT Power Escalation, RO-C-NOP7 U2

05/17/2023

TRP-2070-SIM-

003

23 ILT Power Reduction, RO-C-NOP1 U2

05/17/2023

TRP-2070-SIM-

003

23 ILT Reactor Startup, RO-C-NOP6 U2

05/18/2023

TRP-2070-SIM-

003

U2C27 Simulator Steady State Test

2/01/2023

TRP-2070-SIM-

003

U2C27 Transient 2, Simultaneous Trip of Both Main Feed

Pumps

2/01/2023

TRP-2070-SIM-

U2C27 Transient 5, Trip of #23 RCP

2/01/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

003

TRP-2070-SIM-

003

U2C27 Transient 8, Maximum Size RCS Break w/Loss of

Off-Site Power

2/01/2023

TRP-2070-SIM-

003

U2C27 Transient 10, Stuck Open PORV w/Hi Head Injection

Inhibited

2/01/2023

TRP-2070-SIM-

003

Simulator Performance Testing

TRP-2070-TAP-

200

SAT Design

TRP-2070-TAP-

300

SAT Development

TRP-2070-TAP-

300-LOR

LOR Annual Operating Test & Biennial Written Exam

Development

TRP-2070-TAP-

300-OPS

Operations Training Examination & Simulator Exercise

Guide Development

TRP-2070-TAP-

400-LOR

LORT Annual Operating Test & Biennial Written Exam

Implementation

TRP-2070-TAP-

400-SEC

Operations Training Exam Security

Self-Assessments 2023-8762

24 Pre-NRC 71111.11 Inspection Quick-Hit

Self-Assessment

2/15/2023

NOTICE OF VIOLATION

Indiana Michigan Power Company

Docket Nos.: 05000315 and

05000316

D.C. Cook

License Nos.: DPR-58 and DPR-74

EA-24-047

Consistent with the NRC Enforcement Policy and Title 10 of the Code of Federal Regulations

(10 CFR) Part 2.201, the following two violations documented in inspection report 2024011 are

being cited as a Severity Level IV problem:

Violation: A

CFR Section 55.53 (e) requires, in part, if a licensee has not been actively

performing the functions of an operator or senior operator, the licensee may not resume

activities authorized by a license issued under this part except as permitted by

paragraph (f) of this section. To maintain active status, the licensee shall actively

perform the functions of an operator or senior operator on a minimum of seven 8-hour or

five 12-hour shifts per calendar quarter.

CFR Section 55.53(f), states, in part, if paragraph (e) of this section is not met,

before resumption of functions authorized by a license issued under this part, an

authorized representative of the facility licensee shall certify the following: (1) that the

qualifications and status of the licensee are current and valid; and (2) that the licensee

has completed a minimum of 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> of shift functions under the direction of an

operator or senior operator as appropriate and in the position to which the individual will

be assigned. The 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> must have included a complete tour of the plant and all shift

turnover procedures.

Technical Specification (TS) Section 5.4.1.a. requires, in part, that written procedures

shall be established, implemented, and maintained covering the applicable procedures

recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978.

NRC Regulatory Guide 1.33, Revision 2, Appendix A, Section 1 addresses

Administrative Procedures, Subsection b. addresses Authorities and Responsibilities

for Safe Operation and Shutdown, Subsection g. addresses Shift and Relief Turnover,

and Subsection k. addresses Maintenance of Minimum Shift Complement and Call-In of

Personnel.

The licensee established Procedure OHI-2070, Operations Training and Qualification,

Rev. 72, April 15, 2021, to address the Operations Department training and

qualifications policies and expectations.

Contrary to the above, from October 12, 2021 to February 26, 2024, the licensee failed

to ensure that seven inactive licensed operators performed a complete tour of the plant

and all shift turnover procedures prior to the resumption of functions authorized by their

individual licenses issued under 10 CFR Part 55.

Additionally, from April 15, 2021 to February 26, 2024, the licensee failed to maintain an

adequate written procedure covering Authorities and Responsibilities for Safe Operation

and Shutdown, Shift and Relief Turnover and Maintenance of Minimum Shift

Complement and Call-in of Personnel. Specifically, the site failed to maintain procedure

OHI-2070, Operations Training and Qualification, Rev. 72, April 15, 2021, such that it

allowed the licensee to mark N/A on step F in attachment 5 of the procedure. Marking

this step N/A allowed operators to forgo completing a plant tour and reviewing shift

relief turnover procedures prior to the re-activation of their licenses as required by

CFR 55.53(f).

Violation: B

CFR 50.54(m)(2)(i) requires each licensee shall meet the minimum licensed operator

staffing requirements in the following table. According to the table, Minimum

Requirements Per Shift for On-Site staffing of Nuclear Power Units by Operators and

Senior Operators Licensed Under 10 CFR Part 55, with two nuclear power units

operating, two units/two control rooms, the minimum number of senior operators is three.

TS 5.2.2.b states, in part, "shift crew composition may be less than the minimum

requirement of 10 CFR 50.54(m)(2)(i) and Specifications 5.2.2.a and 5.2.2.f for a period

of time not to exceed 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> in order to accommodate unexpected absence of on-duty

shift crew members provided immediate action is taken to restore the shift crew

composition to within the minimum requirements."

Contrary to the above, on 11 occasions between October 14, 2023 to November 14,

23, the licensee failed to maintain the minimum licensed operator staffing

requirements as required by 10 CFR 50.54(m)(2)(i).

Additionally on 11 occasions between October 14, 2023 to November 14, 2023, the

licensee failed to maintain the minimum licensed operator staffing requirements for

greater than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, and failed to ensure immediate action was taken to restore shift

crew composition to meet the minimum shift staffing requirements as required by

TS 5.2.2.b. Specifically, the license failed to ensure the minimum number of senior

operators were on shift on the following dates: Day shifts of 10/14/23, 10/15/23,

10/19/23, 10/24/23, 10/25/23, 10/30/23, 11/4/23, 11/5/23, 11/8/23, 11/13/23, and

11/14/23.

These violations are being characterized as a Severity Level IV problem.

Consistent with 10 CFR 19.11, you are required to post this Notice of Violation within two

working days of receipt.

Replying to Notice of Violation

You are required to submit a written explanation or statement under 10 CFR 2.201 to the U.S.

Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001

with a copy to the Regional Administrator, Region 3, and a copy to the NRC Resident Inspector

at

D.C. Cook, within 30 days of the date of the issuance of this Notice of Violation. Please mark

your reply "Reply to a Notice of Violation; EA-24-047" and include the following for each

violation:

(1) The reason for the violation, or, if contested, the basis for disputing the violation or

severity level

(2) The corrective steps that have been taken and the results achieved

(3) The corrective steps that will be taken

(4) The date when full compliance will be achieved

Your written explanation or statement may reference or include previous docketed

correspondence. If an adequate reply is not received within 30 days, an order or a Demand for

Information may be issued as to why the license should not be modified, suspended, or

revoked, or why other appropriate action should not be taken. Where good cause is shown,

consideration will be given to extending the required 30-day response time.

If you contest this enforcement action, please provide an additional copy of your response, with

your basis for denial, to the Director, Office of Enforcement, U.S. Nuclear Regulatory

Commission, Washington, DC 20555-0001.

Because your response will be made available electronically for public inspection in the NRC

Public Document Room or from the NRCs document system (ADAMS), accessible from the

NRC website at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not

include any personal privacy, proprietary, or safeguards information so that it can be made

available to the public without redaction. If personal privacy or proprietary information is

necessary to provide an acceptable response, then please provide a bracketed copy of your

response that identifies the information that should be protected and a redacted copy of your

response that deletes such information. If you request withholding of such material, you must

specifically identify the portions of your response that you seek to have withheld and provide in

detail the bases for your claim of withholding (e.g., explain why the disclosure of information will

create an unwarranted invasion of personal privacy or provide the information required by

CFR 2.390(b) to support a request for withholding confidential commercial or financial

information). If safeguards information is necessary to provide an acceptable response, please

provide the level of protection described in 10 CFR 73.21.

Dated this 30th day of August 2024.