IR 05000315/2024003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000315/2024003 05000316/2024003 07200072/2024001 and Exercise of Enforcement Discretion
ML24298A098
Person / Time
Site: Cook  
Issue date: 10/31/2024
From: Matthew Learn
NRC/RGN-III/DORS/ERPB
To: Lies Q
Indiana Michigan Power Co
References
EA-24-078 IR 2024003, IR 2024001
Download: ML24298A098 (1)


Text

SUBJECT:

DONALD C. COOK NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000315/2024003; 05000316/2024003; 07200072/2024001 AND EXERCISE OF ENFORCEMENT DISCRETION

Dear Q. Shane Lies:

On September 30, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Donald C. Cook Nuclear Plant. On October 8, 2024, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding did not involve a violation of NRC requirements.

If you disagree with a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Donald C. Cook Nuclear Plant.

October 31, 2024 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Matthew C. Learn, Acting Branch Chief Engineering and Reactor Projects Branch Division of Operating Reactor Safety Docket Nos. 05000315; 05000316 and 07200072 License Nos. DPR58 and DPR74

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000315; 05000316 and 07200072

License Numbers:

DPR-58 and DPR-74

Report Numbers:

05000315/2024003; 05000316/2024003 and 07200072/2024001

Enterprise Identifiers: I2024-003-0057 and I2024-001-0130

Licensee:

Indiana Michigan Power Company

Facility:

Donald C. Cook Nuclear Plant

Location:

Bridgman, MI

Inspection Dates:

July 01, 2024 to September 30, 2024

Inspectors:

N. Audia, Reactor Inspector

J. Cassidy, Senior Health Physicist

A. Guieb, Project Engineer

T. Hooker, Health Physicist

E. Kokkinis, Project Engineer

J. Kutlesa, Senior Emergency Preparedness Inspector

J. Mancuso, Senior Resident Inspector

T. Okamoto, Project Engineer

D. Sargis, Health Physicist

Approved By:

Matthew C. Learn, Acting Branch Chief

Engineering and Reactor Projects Branch

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Donald C. Cook Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Implement Design Control Process Causes Main Turbine Trip Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green FIN 05000315,05000316/2024003-01 Open/Closed None (NPP)71153 A self-revealed finding of very low safety significance (Green) was identified with the licensee's failure to implement a modification to a turbine supervisory instrumentation (TSI)card. Specifically, the licensee failed to correctly implement a modification to the turbine protection system, leading to incorrect inputs included into the turbine trip circuit which led to a main turbine trip and subsequent reactor trip.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000316,05000315/20 23011-01 Safety-Related Motor Control Center Bus Bar Commercial Grade Dedication 71111.21N.03 Discussed EDG EA24-078 Failure to Comply with 10 CFR Part 37 71124.08 Closed LER 05000316/2024-001-00 LER 2024-001-00 for Donald C. Cook Nuclear Plant, Unit 2, Reactor Trip due to Main Turbine Trip from a High-High Thrust Bearing Position Trip 71153 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On September 27, 2024, Unit 1 reduced power to approximately 90 percent of rated thermal power for main turbine valve testing. The unit returned to full rated thermal power on September 28, 2024, and remained at or near full rated thermal power for the inspection period.

Unit 2 began the inspection period shutdown to address a reactor coolant system leak in excess of the 10 gallons per minute allowed by technical specifications. The unit started up on July 1, 2024, reached full rated thermal power on July 4, 2024, and remained at or near full rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)1E motor driven auxiliary feedwater pump (MDAFP) following a surveillance run on July 12, 2024 (2)2CD emergency diesel generator (EDG) during 2AB EDG work on July 25, 2024 (3)1CD EDG following planned surveillance on September 4, 2024 (4)1AB EDG following surveillance run on September 11, 2024

(5) Unit 2 turbine driven auxiliary feedwater pump (TDAFP) during 12AB loop feed enclosure maintenance window on September 19, 2024

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 emergency core cooling (SIS) on August 5, 2024.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 17A/D Unit 1: auxiliary feed pump rooms and corridor to auxiliary feed pump rooms, both units, elevation 591' on September 3, 2024
(2) Fire Zone 107/50: auxiliary feedwater battery room and HVAC on September 18, 2024
(3) Fire Zone 18: CD diesel generator room, Unit 2, elevation 587' - 0" on September 18, 2024

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill on August 15, 2024.

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in the Unit 1 safety injection pump room on September 16, 2024.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during a Unit 1 downpower for main turbine valve functional testing on September 13, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (2 Samples)

(1) The inspectors observed and evaluated RQ-E4903 As-found Simulator Training on August 6, 2024.
(2) The inspectors observed and evaluated an As-found Simulator Evaluation Scenario on August 27, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 1 main steam on July 15, 2024
(2) Unit 2 component cooling water (CCW) a(1) action plan on July 8, 2024
(3) EDG frequency issues on July 29, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)risk management during loop feed enclosure replacement on September 16, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples 1 Partial)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) AR 2024-5435; 1-DCR205 Failed Inservice Test (IST) Stroke Time on July 15, 2024
(2) AR 2024-5371; FLEX Blended RCS Pump Out of Service on July 16, 2024
(3) AR 2023-4337; Indications of Partial Discharge on 12AB Loop Feed Enclosure on July 17, 2024
(4) AR 2024-5322; 2-HV-AFP-T2AC is not working properly on July 17, 2024
(5) AR 2024-6357; Work Order Generation for 2-IMO52 Repack on August 20, 2024
(6) AR 2024-6986; Use of Local Tachometer for EDG Surveillance on September 18, 2024 (7)

(Partial)

AR 2024-6650; Ice Bed Temperature Following Glycol Restoration on September 19, 2024

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (3 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1)12 AB loop feed enclosure temp modifications on July 17, 2024

(2) Unit 1 TDAFP temporary modifications on July 17, 2024 (3)1-DCR205 temporary modifications on July 18, 2024

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (9 Samples)

(1)2-QRV251 following packing leak on July 11, 2024 (2)2W component cooling water PMT following planned work on July 18, 2024 (3)east diesel driven fire pump PMT following planned work window on July 30, 2024 (4)2N safety injection (SI) pump PMT following planned work on July 30, 2024 (5)supplemental diesel generator on August 14, 2024 (6)1-BATT-AB Cell 114 replacement on August 26, 2024

(7) CEQ fan tripping on September 18, 2024
(8) AB loop feed enclosure PMT on September 24, 2024 (9)2-WMO716, west containment spray heat exchanger essential service water inlet valve on September 27, 2024

Surveillance Testing (IP Section 03.01) (4 Samples)

(1)2W residual heat removal (RHR) operability test on August 19, 2024 (2)2AB EDG monthly surveillance run on August 20, 2024 (3)2W MDAFP surveillance run on September 12, 2024

(4) Unit 1 main turbine valve functional testing on September 13, 2024

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Unit 2 west charging pump operability test on July 29, 2024

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1) FLEX diesel testing on September 13, 2024

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the following maintenance and testing of the alert and notification system:

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the Emergency Preparedness Organization.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the Emergency Preparedness Program.

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) hostile action-based drill on September 24,

RADIATION SAFETY

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated environmental monitoring equipment and observed collection of environmental samples.

Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the implementation of the licensees radiological environmental monitoring program.

Groundwater Protection Initiative (GPI) Implementation (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees implementation of the GPI program to identify incomplete or discontinued program elements.

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage,

& Transportation

Radioactive Material Storage (IP Section 03.01)

The inspectors evaluated the licensees performance in controlling, labeling and securing the following radioactive materials:

(1) Dry Active Waste Building
(2) Radioactive Material Building

Radioactive Waste System Walkdown (IP Section 03.02) (1 Sample)

The inspectors walked down the following accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality:

(1) Cask Dewatering Area in 587' Drumming Room

Waste Characterization and Classification (IP Section 03.03) (3 Samples)

The inspectors evaluated the following characterization and classification of radioactive waste: (1)2022 Dry Active Waste (2)2023 Primary Filters (3)2022 Primary Resins

Shipping Records (IP Section 03.05) (3 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1) Shipment DCC24-048, Surveillance Coupon, UN2915 Type A package
(2) Shipment DCC24-030, Dry Active Waste, UN3321
(3) Shipment DCC23-015, Primary Resin, UN3321 LSA-II, RQ

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS07: High Pressure Injection Systems (IP Section 02.06)===

(1) Unit 1 (April 1, 2023, through March 31, 2024)
(2) Unit 2 (April 1, 2023, through March 31, 2024)

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 1 (July 1, 2023, through June 30, 2024)
(2) Unit 2 (July 1, 2023, through June 30, 2024)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (July 1, 2023, through June 30, 2024)
(2) Unit 2 (July 1, 2023, through June 30, 2024)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (April 1, 2023, through March 31, 2024)
(2) Unit 2 (April 1, 2023, through March 31, 2024)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 1 (September 1, 2023, through June 30, 2024)
(2) Unit 2 (September 1, 2023, through June 30, 2024)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) September 1, 2023, through June 30, 2024 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) September 1, 2023, through June 30, 2024

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) April 1, 2022, through June 30, 2024.

EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)

(1) April 1, 2022, through June 30, 2024.

EP03: Alert and Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)

(1) Sirens are not part of the sites primary ANS. ANS will be inspected via IP 71114.02.

===71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03) (2 Samples 1 Partial)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)turbine trip for steam leak on July 15, 2024 (2)indication of partial discharge on 12AB loop feed enclosure on August 1, 2024 (3)

(Partial) damage to the rod cluster control assembly in Unit 2 outage on August 12, 2024 71153 - Follow-up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)===

The inspectors evaluated the following licensees event reporting determinations to ensure it complied with reporting requirements.

(1) LER 2024-001-00 for Donald C. Cook Nuclear Plant, Unit 2, Reactor Trip due to Main Turbine Trip from a High-High Thrust Bearing Position Trip, 05000316/2024-001-00 (ADAMS Accession No. ML24141A120). The inspection conclusions associated with this LER are documented in this report under Inspection Results Section 71153. This LER is Closed.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

60855 - Operation of an ISFSI Operation of an ISFSI

(1) The inspectors evaluated the licensees independent spent fuel storage installation (ISFSI) cask loading activities from August 19 through August 23, 2024. Specifically, the inspectors observed the following activities during the loading of cask No. 65:
  • fuel loading
  • heavy load movement of loaded multi-purpose canister (MPC) out of the spent fuel pool
  • closure welding and non-destructive evaluations
  • stack-up and download of the MPC from the transfer cask into the storage cask
  • radiological field surveys The inspectors performed walkdowns of the ISFSI pad and haul path, which also included performing independent radiation surveys.

The inspectors evaluated the following:

  • spent fuel selected for loading into dry cask storage during this loading campaign
  • selected corrective action program documents
  • selected 72.48 screenings
  • changes to the sites 10 CFR 72.212 report since the previous inspection

INSPECTION RESULTS

URI (Discussed)

Safety-Related Motor Control Center Bus Bar Commercial Grade Dedication URI 05000316,05000315/2023011-01 71111.21N.03

Description:

The NRC continued to evaluate the unresolved item documented in inspection report 2023011-01 (ADAMS Accession Number ML23233A187) related to the commercial grade dedication activities for a motor control center bus bar. The inspectors requested additional information related to the issues of concern and plan to review it to determine whether any performance deficiencies or violations exist.

Enforcement Discretion Enforcement Action EA24-078: Failure to Comply with 10 CFR Part 37 71124.08

Description:

On November 15, 2016, the licensee was issued NRC Inspection Report Nos.

05000315/2016404 and 05000316/2016404, which documented a licensee-identified violation of 10 CFR Part 37, Physical Protection of Category 1 and Category 2, Quantities of Radioactive Material at Facilities with a 10 CFR Part 73, Physical Protection Program. The violation met the criteria for Enforcement Discretion as described in Enforcement Guidance Memorandum (EGM) 14-001, Interim Guidance for Dispositioning 10 CFR Part 37 Violations with Respect to Large Components or Robust Structures Containing Category 1 or Category 2 Quantities of Material at Power Reactor Facilities Licensed Under 10 CFR Parts 50 and 52.

Subsequently, the inspectors re-evaluated this activity and found that while a violation of regulatory requirements continues to exist, the conditions remain within the criteria for Enforcement Discretion established within Section 9.3 of the NRC Enforcement Policy.

Corrective Actions: As specified in NRC Enforcement Policy, the application of discretion is authorized until the underlying technical issue is dispositioned through rulemaking or other regulatory action. Additional corrective actions are not required.

Corrective Action References: Not Applicable

Enforcement:

Violation: On November 15, 2016, a violation of 10 CFR Part 37 was documented in Donald C. Cook Inspection Report Nos. 05000315/2016404 and 05000316/2016404. The inspectors determined that the previously identified violation remains.

Basis for Discretion: This violation met the criteria for Enforcement Discretion as described in Section 9.3 of the NRC Enforcement Policy Enforcement Discretion for Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material.

Failure to Implement Design Control Process Causes Main Turbine Trip Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green FIN 05000315,05000316/2024003-01 Open/Closed None (NPP)71153 A self-revealed finding of very low safety significance (Green) was identified with the licensees failure to implement a modification to a turbine supervisory instrumentation (TSI)card. Specifically, the licensee failed to correctly implement a modification to the turbine protection system, leading to incorrect inputs included into the turbine trip circuit which, led to a main turbine trip and subsequent reactor trip.

Description:

On March 22, 2024, the Unit 2 main turbine tripped due to a main turbine thrust bearing trip condition, which led to an automatic trip of the Unit 2 reactor. The thrust bearing trip signal is designed to trip the main turbine if a thrust bearing wear condition is sensed on the turbine and is fed by a 2-out-of-2 logic trip input from thrust bearing probes A and B. Directly prior to the trip, probe B had spiked above the high alarm setpoint while probe A remained normal.

The licensee investigated the alarm and determined the momentary indication was most likely an indication of probe failure or a bad driver and recommended bypassing the alarm.

Approximately a minute later, probe B spiked high again (with probe A still reading normal),this time above the trip setpoint, inputting one of two trip inputs required for the trip signal.

Despite only having one of the two designed inputs for a trip, the Unit 2 main turbine still tripped.

Licensee investigation revealed the cause to be during implementation of engineering change EC00000047291, which modified a TSI card. This card is connected to the thrust bearing probes, with additional probes used to monitor various other trip conditions. In 2007, the main turbine thrust bearing trip was incorrectly set to monitor all probes on the TSI card instead of only the thrust bearing probes, allowing a 2-out-of-all logic trip input for the trip signal. At the time of the trip, vibration probe 1X on the TSI card showed bad quality (interpreted by the logic as failed or above setpoint), which input one of two trip inputs required for the trip signal. When thrust bearing probe B exceeded the trip setpoint, the second required trip input was met, signaled a trip, and caused the main turbine to trip and subsequent reactor trip.

Corrective Actions: The licensee took immediate corrective actions to remove the incorrect inputs for the thrust bearing trip, replaced the TSI card associated with the main turbine thrust bearing probes, and replaced probe B. Planned corrective actions going forward will be replacement of the remaining probes.

Corrective Action References: AR 2024-2321 Unplanned reactor/turb trip due to thrust bearing high vibe AR 2024-2318 MT TSI TP2 High vibes

Performance Assessment:

Performance Deficiency: The inspectors determined that the licensees failure to implement a modification to a TSI card was contrary to EC0000047291 and was a performance deficiency.

Specifically, the licensee included additional probes into the thrust bearing trip function of the TSI card, which altered the trip logic.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the failure to use adequate design control resulted in an automatic reactor trip.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined that this finding is of very low safety significance (Green) because they answered No to Exhibit 1, Section B, Transient Initiators screening question.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Inspectors did not identify a violation of regulatory requirements associated with this finding.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 8, 2024, the inspectors presented the integrated inspection results to Q. S. Lies, Executive Vice President and Chief Nuclear Officer, and other members of the licensee staff.
  • On July 11, 2024, the inspectors presented the radiation protection inspection results to Q. S. Lies, Executive Vice President and Chief Nuclear Officer, and other members of the licensee staff.
  • On July 26, 2024, the inspectors presented the emergency preparedness inspection results to L. Ellis, Plant Manager, and other members of the licensee staff.
  • On August 23, 2024, the inspectors presented the ISFSI cask loading inspection results to M. Scarpello, Director of Regulatory Compliance and Licensing, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Calculations

SD220712-001

Evaluation of ISFSI Pad Settlement Survey

AR 2021-6205

Dry Cask Personnel Did Not Follow Written Instructions

07/15/2021

AR 2021-7151

Dry Cask - Welding Interpass Temperature Not Monitored

08/17/2021

AR 2022-4965

Possible Degradation of Sheave Bearing on 12-QM3E

06/06/2022

AR 2024-0560

Elevated ISFSI Cask Delta T

01/20/2024

AR 2024-2987

Deficiencies Found during Monthly Dry Cask Inspection

04/07/2024

Corrective Action

Documents

AR 2024-3469

2-QM80 Cable Deterioration Observed

04/19/2024

Corrective Action

Documents

Resulting from

Inspection

AR 2024-6459

WOs for East Aux Building Crane (12-QM3E) Need

Updating

08/22/2024

EC1000494

DC Cook Dry Cask Loading Campaign #5

Engineering

Evaluations

NFG-DCO23-01

Decay Heat Calculations to Support Dry Cask Storage

Campaign #5 (Summer 2024)

2.48 Tracking

No.: 2021-0188-

Incorporation of Holtec Engineering Change Order (ECO)

5014-132

10/18/2021

2.48 Tracking

No.: 2021-0203-

Addition of 69kV-12kV Transformer #10

01/18/2022

2.48 Tracking

No.: 2022-0037-

The 72.212 Evaluations Report and Regulatory Compliance

Report are Being Updated

03/28/2022

2.48 Tracking

No.: 2024-0004-

Update of the 10 CFR 72.212 Evaluations Report to Address

the NRC Approved Changes for the Renewed Certificate(s)

of Compliance and Associated HOLTEC FSAR(s)

01/23/2024

2.48 Tracking

No.: 2024-0043-

Transport Operations

04/21/2024

60855

Miscellaneous

2.48 Tracking

No.: 2024-0048-

MPC Preparation for Loading Transfer Operations

04/26/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2.48 Tracking

No.: 2024-0052-

MPC Loading Operations

05/22/2024

2.48 Tracking

No.: 2024-0062-

MPC Boron Sampling

05/30/2024

2.48 Tracking

No.: 7248-2022-

0116-00

DC Cook Dry Cask Loading Campaign #5

10/19/2022

NDE Reports

20422-967-04

GQP-9.2 Liquid Penetrant Examination Report

08/21/2024

EHP SP.045

Ultrasonic Testing of Unit 1 Fuel for Cycle 14 Reload

EHP SP.048

Unit 1 In-Mast Fuel Sipping

2-EHP-4051-

DCO-300

Fuel Selection and Sequence Development for Dry Cask

Storage

2-OHL-4030-

SOM-009

Unit 12 Tours - ISFSI

2-OHP-4051-

DCO-300

MPC Loading Operations

2-OHP-4051-

DCO-400

MPC Welding, Blowdown, Drying and Backfill

2-OHP-4051-

DCO-500

Transfer Operations

MHI-5025

Control and Inspection of Rigging and Lifting Equipment,

Data Sheet 20, Annual Rigging and Lifting Inspection

Record

PMP-2350-SES-

2

CFR 72.48 Reviews

Procedures

PMP-5020-MHP-

001

Lifting and Rigging Program

CNP-2405-00110

Semi-Annual ISFSI Pad Survey

05/29/2024

Radiation

Surveys

SW_VSDS-M-

210807-2

Neutron Dose Rate Survey for Comparison of Meters

08/07/2021

GT 2023-8773

NRC ISFSI Inspection

05/09/2024

Self-Assessments

NOS-21-03

Nuclear Oversight Audit: Spent Fuel Storage

10/11/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

55565828-48

Perform DCO-805 Special Lifting Device Inspections

05/01/2024

C10044660001

MTE (12-QM-3E) Perform Inspection/Maintenance

2/12/2023

C10044660003

MTM: 12-QM-3E Perform Inspections and Maintenance

2/14/2023

Work Orders

C10070699001

MTM: 12-QM-3E, Perform Monthly Mechanical Crane

Inspection

06/06/2024

OP-1-5151A-51

Flow Diagram Emergency Diesel Generator AB Unit No. 1

07/15/2021

OP-1-5151B-65

Flow Diagram Emergency Diesel Generator AB Unit #1

04/15/2024

OP-2-5135-40

Flow Diagram CCW Pumps and CCW Heat Exchangers

11/14/2022

OP-2-5142

Flow Diagram Emergency Core Cooling (SIS)

10/19/2022

Drawings

OP-2-5151D-71

Flow Diagram Emergency Diesel Generator CD Unit No. 2

07/13/2021

1-OHP-4021-032-

008AB

Operating DG1AB Subsystems - DB1AB Fuel Oil System

Valves

1-OHP-4021-032-

008CD

Operating DG1CD Subsystems

1-OHP-4030-156-

017E

East MDAFP Valve Lineup

1-OHP-4030-156-

017E

East MDAFP Valve Lineup

2-OHP-4021-008-

2

Placing Emergency Core Cooling System in Standby

Readiness

036

2-OHP-4021-032-

008CD

Operating DG2CD Subsystems

2-OHP-4030-208-

053V

E.C.C.S. Valve Position Verification

009

2-OHP-4030-216-

20E

Unit Two East CCW Loop Flow Path Verification

2-OHP-4030-216-

20W

Unit Two West CCW Loop Flow Path Verification

71111.04

Procedures

2-OHP-4030-256-

017T

Turbine Driven Auxiliary Feedwater System Test

Fire Plans

Fire Pre-Plans Volume 1

D.C. Cook Nuclear Plant Fire Safety Analysis (FSA)

Revision 5

08/11/2021

71111.05

Miscellaneous

24-009-A

Fire Drill

08/15/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PRA-FLOOD-004

Internal Flooding - Qualitative Screening Analysis

PRA-FLOOD-007

Floor Drains Capacity

PRA-FLOOD-008

Flood Sources and the Associated Flood Mechanisms

71111.06

Calculations

PRA-FLOOD-014

Internal Flood Detailed Analysis

71111.11Q

Procedures

RQ-E-4903-U2

Licensed Operator Requalification Training Scenario

08/06/2024

2019-9540

As-Found LLRT Failure of Both 2-CCW-244-25 and

2-CCW-243-25

10/07/2019

21-10369

CCW-05 Maintenance Rule (a)(1) Consideration

2/22/2021

21-3313

As-Found LLRT of 2-CCW-244-25 Was Unable to be

Pressurized

04/20/2021

21-8634

SML-78 Drop 75 (C-9 Status Light) Not Lit

10/19/2021

21-9413

MRule Reliability Criteria for Function MS-09 Exceeded

11/17/2021

22-3634

Open & Inspect CCW Contain Isolation Valves on Unit 2

04/26/2022

22-5260

Sparge/Flush the Component Cooling Water Hx in U2C28

06/20/2022

23-7589

1-CCW-243-25 LLRT Failed

10/18/2023

24-2445

2-CCW-244-72 Gross LLRT Failure

03/26/2024

24-2448

2-CCW-243-25 Gross LLRT Failure

03/26/2024

Corrective Action

Documents

24-2450

2-CCW-244-25 Gross LLRT Failure

03/26/2024

Cook Nuclear Plant Excellence Plan Indicator CNP.142

Number of (a)(1) Systems, Unit 1, Unit 2 and Common

07/2024

Maintenance Rule Scoping Document; Component Cooling

Water

71111.12

Miscellaneous

Maintenance Rule Scoping Document; Main Steam System

71111.13

Procedures

2-OHP-SP-475

Risk Management for LCO 3.8.1 Entry during AB Loop Feed

Modification

09/09/2024

23-4337

Indications of Partial Discharge on 12AB Loop Feed

06/08/2023

23-9079

1-IMO-255 10 dpm Packing Leak

11/30/2023

24-4592

2-HV-AFP-T1AC Will Not Run

05/26/2024

24-5371

FLEX Blended RCS Pump Out of Service

07/01/2024

24-5435

1-DCR-205 Failed IST Stroke Time

07/04/2024

24-6357

Work Order Generation for 2-IMO-52 Repack

08/19/2024

71111.15

Corrective Action

Documents

24-6650

Ice Bed Temperature Following Glycol Restoration

08/30/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 2024-5322

2-HV-AFP-T2AC is Not Working Properly

06/28/2024

AR 2024-6986

Use of Local Tachometer for EDG Surveillance

09/17/2024

Miscellaneous

OHI-4032

Leakage Monitoring Program Cumulative Leak Rate Data

Log

2/07/2023

1-OHP-4030-114-

011

RCDT and Containment Sumps Valve Test

EHI-5072

ECCS Recirculation Leakage Reduction Program

OHI-4032

Leakage Monitoring Program

21

PMP-4030-001-

001

Impact of Safety Related Ventilation on the Operability of

Technical Specification Equipment

Procedures

PMP-7030-OPR-

001

Operability Determination

22-5345

Evaluate TDAFP Room Cooler Performance

06/23/2022

22-5373

U1 TDAFP Room Cooler 1-HV-T1AC Not Working Correctly

06/24/2022

22-5375

U1 Unexpected CR Alarm for TDAFP Room Coolers

06/25/2022

22-6759

MRE Needed on U1 TDAFP Room Cooler Conditions

23-8396

Create WO to Replace 1-HV-AFP-T1AC

11/06/2023

Corrective Action

Documents

24-2805

2-DCR-205 Blown Diaphragm

04/02/2024

DWWO 2022-

8603

1-HV-AFP-T1AC Replace Cooler Unit

07/28/2022

71111.18

Miscellaneous

GT 2022-10244

Risk Tracking for 1/2-DCR-205-206 and 1-VCR-11/21

Diaphragms

2/20/2022

Corrective Action

Documents

24-6974

Light Not Lit on 2-HV-CEQ-1 Control Switch

09/17/2024

1-OHP-4030-114-

031

Breaker Alignment

09/23/2024

1-OHP-5030-050-

001

Main Turbine and Feed Pump Turbine Valve Functional

Checks

09/14/2024

2-MHP-5021-

033-001

Supplemental Diesel Generator Maintenance

005

2-OHP-4030-

033-01

Supplemental Diesel Generator Testing - SDG Quarterly

Surveillance

71111.24

Procedures

2-OHP-5030-

FSG-421

FLEX 500 kW DG Functional Test

09/11/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-OHP-5030-

FSG-422

FLEX 250/350 kW DG Functional Test

09/11/2024

2-OHP-5030-

FSG-423

FLEX 26 kW DG Functional Test

09/11/2024

2-OHP-4030-203-

2W

West Centrifugal Charging Pump Operability Test

2-OHP-4030-214-

031

Breaker Alignment

09/24/2024

2-OHP-4030-217-

050W

West Residual Heat Removal Train Operability

Test Modes 1-4

08/15/2024

2-OHP-4030-256-

017W

West Motor Driven Auxiliary Feedwater System Test

09/13/2024

2-OHP-4030-

STP-017W

West Motor Driven Auxiliary Feedwater System Test

OHI-4016

Conduct of Operations: Guidelines IST Valve Operability

After Maintenance

C10054830 001

MTM, 12-OME-250-SDG1, Annual Maintenance

(Vendor/MT)

08/06/2024

C10055989002

2-WMO-716 Full PM

07/22/2024

C10062773 001

MTM, 12-OME-250-SDG2, Annual Maintenance (Vendor)

08/06/2024

C10062959024

1-BATT-AB Replace Cell 114

08/21/2024

C10071943004

MTI, 2-QRV-251, Reinstall Instr, A/L Diagnostics

06/28/2024

C10076413-001

MTE: 2-HV-CEQ-1 (2-152-CEQ1) Replace Back Up Breaker

09/17/2024

Work Orders

C10076413-003

2-HV-CEQ-1: 2-IHP-4030-228-005B - Post Maintenance

Test

09/17/2024

AR 2022-6301

Loss of Federal IPAWS System

08/05/2022

Corrective Action

Documents

AR 2024-1557

Nationwide Cell Phone Outage

2/22/2024

Miscellaneous

FEMA Design

Report

Alert and Notification System Evaluation Report

01/01/2021

71114.02

Self-Assessments NOS-24-02

Nuclear Oversight Audit NOS-24-02, Emergency

Preparedness

04/11/2024

AR 2024-1487

Evidence of EP-I-ERO Training Not Documented

(NOS-24-02)

2/20/2024

71114.03

Corrective Action

Documents

AR 2024-2141

ARM-24-03-01, EP Training and Qualification

03/19/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

N/A

ERO Staff Training Records: 25 Records

Various

Procedures

CNP OSA Report

ERO On-Shift Staffing Analysis Report

2/09/2019

Calculations

KLD TR - 1409

Donald C. Cook Nuclear Plant 2024 Population Update

Analysis

06/12/2024

Corrective Action

Documents

AR 2022-9770

PARs Not in Accordance With Drill Manual

11/30/2022

71114.05

Procedures

N/A

DC Cook Emergency Plan

Rev. 49

Cook Work

Practices

Evaluation SRA

Work Practice Evaluation for GPI Implementation at Cook

Calculations

DC Cook SSC

Risk Evaluations

SRA

Systems, Structures, and Components Site Risk

Assessment

AR 2022-10270

REMP Air Station Loss of Power Documentation for the

Annual

2/21/2022

AR 2023-0575

2-THP-6010-RPP-601 and Tech Spec 5.5.1c.3 Compliance

Issue

01/19/2023

AR 2023-2224

REMP TLD at Location OFT11 Lost

03/16/2024

Corrective Action

Documents

AR 2024-3218

NBF REMP Air Sample Unavailable

04/10/2024

ENVI-8916-GPI-

001

Groundwater Protection Program

Land Use Census

22

Radiological Environmental Monitoring Program Land Use

Census Summary

09/30/2022

Miscellaneous

Land Use Census

23

Radiological Environmental Monitoring Program Land Use

Census Summary

09/30/2023

2-THP-6010-

RPP-630

Collection of REMP Surface Water Sample

2-THP-6010-

RPP-634

Collection of REMP Groundwater Samples

Procedures

PMP-6010-OSD-

001

Off-Site Dose Calculation Manual

GT 2021-10170-1

Self-Assessment Report for the Radiological Environmental

Monitoring Program (REMP)

21

71124.07

Self-Assessments

GT 2023-8764 - 1

Self-Assessment Report for the Radiological Environmental

23

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Monitoring Program (REMP)

Calculations

RPC/TB RP-16-

CPR Part 37 Category 1 and Category 2 Quantity

Determination

09/06/2016

AR 2024-1644

CFR 61 Scaling Factor Data - 2022, Data Entry Error

2/27/2024

Corrective Action

Documents

AR 2024-3186

Vehicle Inspection Check off Sheet Tire Inspections

06/30/2024

Corrective Action

Documents

Resulting from

Inspection

AR 2024-5469

Part 37 Annual Review

07/08/2024

CFR 61

Scaling Factor

Data - 2022

CFR 61 Scaling Factor Data - 2022

Not Provided

CFR 61

Scaling Factor

Data - 2023

CFR 61 Scaling Factor Data - 2023

Not Provided

2-THP-6010-

RPP-011 Data

Sheet 2

Radioactive Source Leak Test Record

05/20/2024

Lesson Plan GP-

I-AIND

10CFR37 Approved Individual

NEI 14-04

Cook Nuclear Plant Indiana and Michigan Power Part 37

Security Plan for the Protection of Category 1 and

Category 2 Quantities of Radioactive Material

Miscellaneous

SPP-2060-SFI-

217

Protection of Category 1 and Category 2 Quantities of

Radioactive Material

2-THP-6010-

RPP-011

Radioactive Source Control

2-THP-6010-

RPP-913

Scaling Factor Determination

2-THP-6010-

RPP-917

CFR Part 37 Material Accountability Program

71124.08

Procedures

PMP-6010-PCP-

900

Radioactive Waste Process Control Program

Procedures

PMP-6010-PCP-

901

Shipment of Radioactive Materials and Waste

GT 2023-0671

Perform the Annual Part 37 Security review for 2023

11/15/2023

Self-Assessments

GT 2023-8765-1

Radiation Protection Radwaste Program

06/06/2024

DCC23-015

Primary Resin

05/23/2023

DCC24-030

Dry Active Waste

04/10/2024

Shipping Records

DCC24-048

Surveillance Capsule S

06/11/2024

C10027792002

Received Leak Check Counting Data

11/22/2022

C10043544001

RP Perform Source Leak Checks

06/05/2023

71124.08

Work Orders

C10054043002

Received Leak Check Counting Data

11/20/2023

EPP-2080-ERO-

300

Emergency Preparedness Performance Indicators

Performance Indicator Verification

04/01/2022

through

06/30/2024

PMP-7110-PIP-

001

Reactor Oversight Program Performance Indicators and

Monthly Operating Report Data Sheets and MSPI Derivation

Sheets (High Pressure Injection Systems and Cooling Water

Systems; April 2023 through March 2024)

PMP-7110-PIP-

001

Reactor Oversight Program Performance Indicators and

Monthly Operating Report Data Sheets and MSPI Derivation

Sheets (Heat Removal System (AFW) and Residual Heat

Removal System; July 2023 through June 2024)

PMP-7110-PIP-

001 Data Sheet

Reactor Coolant System Specific Activity

Multiple

PMP-7110-PIP-

001 Data Sheet

Occupational Exposure Control Effectiveness

Multiple

71151

Miscellaneous

PMP-7110-PIP-

001 Data Sheet

RETS/ODCM Radiological Effluent Occurrences

Multiple