IR 05000315/2023004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000315/2023004 and 05000316/2023004
ML24030A965
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 01/31/2024
From: Dariusz Szwarc
NRC/RGN-III/DORS/ERPB
To: Lies Q
Indiana Michigan Power Co
References
IR 2023004
Download: ML24030A965 (1)


Text

SUBJECT:

DONALD C. COOK NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000315/2023004 AND 05000316/2023004

Dear Q. Shane Lies:

On December 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Donald C. Cook Nuclear Plant. On January 10, 2024, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Dariusz Szwarc, Acting Chief Engineering and Reactor Projects Branch Division of Operating Reactor Safety Docket Nos. 05000315 and 05000316 License Nos. DPR-58 and DPR-74

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000315 and 05000316

License Numbers:

DPR-58 and DPR-74

Report Numbers:

05000315/2023004 and 05000316/2023004

Enterprise Identifier:

I-2023-004-0048

Licensee:

Indiana Michigan Power Company

Facility:

Donald C. Cook Nuclear Plant

Location:

Bridgman, MI

Inspection Dates:

October 01, 2023 to December 31, 2023

Inspectors:

J. Cassidy, Senior Health Physicist

T. Hooker, Health Physicist

J. Mancuso, Resident Inspector

J. Park, Reactor Inspector

J. Winslow, Reactor Systems Engineer

P. Zurawski, Senior Resident Inspector

Approved By:

Dariusz Szwarc, Acting Chief

Engineering and Reactor Projects Branch

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Donald C. Cook Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 and Unit 2 began the inspection period at rated thermal power and remained at or near rated thermal power with the following exceptions: Unit 1 was shut down for refueling outage from October 11, 2023, to November 18, 2023, and reduced power to approximately 22 percent on December 10, 2023, for repair of a main steam leak. Unit 1 was returned to 100 percent power on December 12, 2023. Unit 2 reduced power to approximately 75 percent on December 8, 2023, for main turbine valve testing and returned to100 percent power on December 9,

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 Outage U1C32 High Risk: Low Reactor Coolant System (RCS) Inventory/High RCS Heat Load on October 17, 2023
(2) Unit 1 Dual Essential Service Water (ESW) Pump Outage with Unit 2 ESW/Component Cooling Water Pumps, 4kV Rooms, Emergency Diesel Generators (EDGs) and SDGs guarded on October 23, 2023
(3) Unit 1 & 2 Spent Fuel Pool Heat Exchangers/Cooling on October 30, 2023

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 1 N-Train Battery system on October 3, 2023.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1 Outage U1C32 Key Safety Function Fire Preservation Actions During the weeks of October 9 and October 16, 2023:
  • Fire Zone 42D, E.P.S. Battery Room, Unit 1 Elevation 609'-6"
  • Fire Zone 44N, Auxiliary Building North, Both Units Elevation 609'-0"
  • Fire Zone 44S, Auxiliary Building South, Both Units Elevation 609'-0"
  • Fire Zone 53, Unit 1 Control Room
(2) Fire Zones 8, 9, 10, 11, 23, 24, 25, & 26: U-1 Quadrants 3N, M, S, 4 RCT and U-2 Quadrants 3N, M, S, & 4 Cable Tunnel - Elev. 596'-3.5"
(3) Fire Zone 55: Switch Gear Room Cable Vault, Unit 1 Elevation 625' 10" on November 27, 2023

===71111.08P - Inservice Inspection Activities (PWR) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from October 16, 2023, to October 31, 2023.

PWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding Activities (IP Section 03.01)===

The inspectors verified that the following nondestructive examination and welding activities were performed appropriately:

(1) Ultrasonic Examination
  • Feedwater System Pipe Welds, 1-FW-12-02S and -03S, Cat. R-A, Item R1.20
  • Pressurizer Support Weld, 1-PZR-26, Cat. B-K, Item B10.10 Visual Examination
  • Repair/Replacement of Weld No. 1 and 2, Replacement of Check Valve 1-SI-158-L2 on Safety Injection (SI) to Loop #2 Hot Leg under WO 55512999-02 PWR Inservice Inspection Activities Sample - Boric Acid Corrosion Control Inspection Activities (IP Section 03.03) (1 Sample)

The inspectors verified the licensee is managing the boric acid corrosion control program through a review of the following evaluations:

(1) Boric Acid Evaluations
  • Action Request (AR) 2022-4046-1, Boric Acid on Bottom of U1 Lower Vessel, June 7, 2022
  • AR 2022-2646-1, 12 RCP Shaft Seal is Overflowing Down the Side of the Pump, April 26, 2022
  • AR 2023-3461-1, Unit 1 North SI Pump Mechanical Seal Boric Acid Leak, May 30, 2023 Corrective Actions
  • AR 2022-2701, Boric Acid Deposit on U1 SWI Piping Suspect Through Wall, April 5, 2022
  • AR 2022-2941, RCP #12 Shaft Seal Lower Housing Cap Screws are Corroded, April 13, 2022

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from February 14, 2023, to March 20, 2023.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during Unit 1 U1C32 Shutdown on October 13, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 1 and 2 Ice Condenser a(1) Plan on November 6, 2023
(2) Unit 1 Non-Essential Service Water System on December 11, 2023

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 1 refueling outage U1C32 risk management on October 23, 2023
(2) U1 AB EDG auto voltage regulator did not respond as expected on October 25, 2023
(3) Unit 1 unisolable steam leak with downpower and weld repair on December 11, 2023
(4) Maintenance Risk Cycle 128, Week 12, with Unit 1 risk significant component cooling water work and condenser waterbox isolations the week of December 18, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 1 and Unit 2 Open Operational Decision Making Issues on October 5, 2023
(2) AR 2023-7398; Unit 1 Motor Driven Aux Feed Pump did not Restart During LOP/LOCA Test on October 23, 2023
(3) AR 2023-8319; Char Testing Identified Sort on Outer Shield to Ground (Source Range Instrumentation) on November 8, 2023
(4) AR 2023-9006; High Reactor Coolant Activity/Potential Failed Fuel on November 28, 2023
(5) AR 2023-9354; Cracks on Walls of Battery 1-BATT-AB Cells 55 and 113 on December 13, 2023

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1)10CFR 50.59 Technical Specification change 2019-0189-03 for dose equivalent I-131 specific activity due to leaking fuel assembly on December 10, 2023

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Refueling Outage U1C32 activities from October 14 through November 15, 2023.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (8 Samples)

(1) Unit 1 East Residual Heat Removal (RHR) Heat Exchanger Outlet Control Valve 2-IRV-310 on October 5, 2023
(2) Unit 1 AB EDG following work during Refueling Outage U1C32 on October 26, 2023
(3) Unit 1 Containment Chiller A on October 10, 2023
(4) Ice Condenser Testing during Refueling Outage U1C32 on November 9, 2023
(5) Unit 1 Motor Driven Auxiliary Feedwater Pump following failure on November 18, 2023
(6) Unit 1 East Component Cooling Water Loop Surveillance Test on December 4, 2023
(7) Unit 1 West Component Cooling Water MOV Diagnostic Testing on December 19, 2023
(8) Unit 1 East Centrifugal Charging Pump Operability Test on December 26, 2023

Surveillance Testing (IP Section 03.01) (3 Samples)

(1)12-IHP-4030-046-001; Unit 1 and 2 Personnel Airlock Leak Rate Surveillance on November 8, 2023 (2)12-IHP-4030-0082-005; AB, CD, and N-Train Battery Monthly Surveillance and Maintenance on November 28, 2023 (3)2-OHP-4030-232-027AB; AB Diesel Generator Operability Test (Train B) on December 20, 2023

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Unit 1 Trevi-Testing on October 12, 2023

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1)1-OHP-4030-108-053A & 053B; Emergency Core Cooling System Vale Operability Test - Train A & B on October 30, 2023

Ice Condenser Testing (IP Section 03.01) (1 Sample)

(1) Unit 1 Ice Condenser Ice Basket Weighing, October 12 through November 15, 2023

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
  • RMA-2080-EPA-008: Screening # 22-33, June 22, 2022
  • RMA-2080-EPA-008: Screening # 22-47, November 17, 2022
  • RMA-2080-EPA-008: Screening # 23-17, May 11, 2023 This evaluation does not constitute NRC approval.

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels, the concentrations and quantities of radioactive materials, and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Licensee surveys and decontamination of equipment and supplies leaving the radiologically controlled area (RCA)
(2) Workers exiting Unit 1 upper containment during a refueling outage

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated the licensees control of radiological hazards for the following radiological work:

(1) Unit 1 containment spray valve internals inspection
(2) Unit 1 quick release valve testing
(3) High radiation area and contamination briefing for Unit 1 quick release valve internals replacement High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following high radiation areas (HRAs) and very high radiation areas (VHRAs):

(1) Unit 1 reactor pit hatch
(2) Unit 1 lower containment reactor coolant drain tank gate
(3) Unit 1 upper containment reactor coolant drain tank hatch Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (October 1, 2022 through September 30, 2023)
(2) Unit 2 (October 1, 2022 through September 30, 2023)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 1 (October 1, 2022 through September 30, 2023)
(2) Unit 2 (October 1, 2022 through September 30, 2023)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1 (October 1, 2022 through September 30, 2023)
(2) Unit 2 (October 1, 2022 through September 30, 2023)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) October 1, 2022 through September 30, 2023 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) October 1, 2022 through September 30, 2023

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) AR 2023-7857; Mistras Part 21 Notification Regarding Falsification of Calibration Certificate for Acoustic Emission Test Equipment Used for Reactor Head and Internals Lift Rigs

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in minimum staffing that might be indicative of a more significant safety issue.

INSPECTION RESULTS

Observation: Updated Information Related to Acoustic Emission (AE) Test Instrument Issue for Reactor Head and Internals Lifting Rigs was Not Reviewed 71152A As a result of an issue identified during the June 2021, Nuclear Procurement Issues Corporation (NUPIC) audit of the licensees vendor, Mistras Services, regarding falsification of calibration for an acoustic emission (AE) data acquisition system instrument, the licensee documented the condition under Action Requests (AR) 2021-5416 and 2021-7084. Under these ARs, the licensee evaluated the AE tests performed during the reactor head and internals lift activities in March 2019, for Unit 1, and October 2019, for Unit 2. It concluded there was no adverse licensee impact on the use of the AE test instrument, and that the calibration of the AE test instrument used at the licensee facility was valid.

However, during an inquiry into the licensee actions following the vendor issuance of a Title 10 Code of Federal Regulations (CFR) Part 21 Interim Report, dated October 20, 2023, noting a deviation in the calibration certificates for the AE instruments used at the licensee facility, the inspectors identified that the vendor previously sent the licensee a letter dated April 4, 2023. This letter notified the licensee that the AE tests performed in March and October 2019, for Units 1 and 2, respectively, both used the instruments that did not have a then-current valid certificate of calibration. This was updated information that was not reviewed against the result of the licensee corrective action review for ARs 2021-5416 and 2021-7084. The importance of reviewing the updated information is to ensure whether theres any significant effect to the results of a prior corrective action review that had been performed. The promptness of such review ensures potential issues are fully identified and appropriate corrective actions assigned as necessary in a timely manner. It becomes especially important for major activities such as the reactor head and internals lifting devices during refuel outages.

As a result, the licensee initiated AR 2023-7857 on October 24, 2023. Immediate corrective actions included a detailed evaluation of instrumentation used during the 2019, Unit 1 AE test, prior to the scheduled reactor head and internals lifts during the 2023, Unit 1 refuel outage. The licensee also completed similar evaluation for the Unit 2 AE test. These reviews concluded that the 2019 AE tests were acceptable as-is. Inspectors did not identify any safety concern or performance deficiency.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 10, 2024, the inspectors presented the integrated inspection results to Q. Lies, Senior VP and Chief Nuclear Officer, and other members of the licensee staff.
  • On October 27, 2023, the inspectors presented the radiation protection inspection results to K. Ferneau, Site Vice President, and other members of the licensee staff.
  • On October 31, 2023, the inspectors presented the Inservice inspection results to M. Scarpello, Regulatory Affairs Director, and other members of the licensee staff.
  • On November 30, 2023, the inspectors presented the Emergency Action Level and Emergency Plan change review inspection results to M. Scarpello, Regulatory Affairs Director, and other members of the licensee staff.

THIRD PARTY REVIEWS Inspectors reviewed the World Association of Nuclear Operators (WANO) September 2023 Peer Review Report. The inspectors evaluated this report to ensure that NRC perspectives of licensee performance were consistent with any issues identified during the assessment. The inspectors also reviewed this report to determine whether INPO identified any significant safety issues that required further NRC follow-up.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 2015-14835

2-QC-3 Area (SFP) Requires Painting

11/15/2015

AR 2021-9726

No Vibration Pads on N SFP Pump/Motor

11/30/2021

AR 2022-8028

SFP Temp Alarm Coming in 6 degrees early

10/09/2022

Corrective Action

Documents

AR 2022-8635

Incorrect Date Entered on Procedure Attachment

10/24/2022

1-OHP-4021-032-

008AB

Operating DG1AB Subsystems

036

1-OHP-4021-032-

008CD

Operating DG1CD Subsystems

043

1-OHP-4021-082-

015

Operation of the N Train Battery System

21

2-OHP-4021-

018-002

Placing in Service and Operating the Spent Fuel Pit Cooling

and Cleanup System

2-OHP-4021-

019-001

Operation of the Essential Service Water System

076

2-OHP-4021-

2-008CD

Operating DG2CD Subsystems

037

2-OHP-4021-032-

008AB

Operating DG2AB Subsystems

040

71111.04

Procedures

PMP-4100-SDR-

001

Plant Shutdown Safety and Risk Management

055

Fire Pre-Plans -

Volume 1

Fire Zone 8: Unit 1 Quadrant 4 RCT elev. 596' -3.5"

Fire Pre-Plans -

Volume 1

Fire Zone 9: Unit 1 Quadrant 3N RCT elev. 596' -3.5"

Fire Pre-Plans -

Volume 1

Fire Zone 10: Unit 1 Quadrant 3M RCT elev. 596' -3.5"

Fire Pre-Plans -

Volume 1

Fire Zone 23: Quadrant 3N Cable Tunnel Unit 2

elev. 596' -3.5"

Fire Pre-Plans -

Volume 1

Fire Zone 24: Quadrant 3M Cable Tunnel Unit 2

elev. 596' -3.5"

71111.05

Fire Plans

Fire Pre-Plans -

Volume 1

Fire Zone 25: Quadrant 3S Cable Tunnel Unit 2

elev. 596' -3.5"

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Fire Pre-Plans -

Volume 1

Fire Zone 26: Quadrant 4 Cable Tunnel Unit 2

elev. 596' -3.5"

Fire Pre-Plans -

Volume 1

Fire Zone 11: Unit 1 Quadrant 3S RCT elev. 596' -3.5"

Fire Pre-Plans -

Volume 1

Fire Zone 44N: Auxiliary Building North Both Units,

elev. 609'-0"

Fire Pre-Plans -

Volume 1

Fire Zone 44S: Auxiliary Building South Both Units,

elev. 609'-0"

Fire Pre-Plans -

Volume 1

Fire Zone 53: Unit 1 Control Room, elev. 633'-0"

Fire-Pre-Plans -

Volume 1

Fire Zone 55: Switchgear Room Cable Vault Unit 1 - 625'-10"

2-FP-4030-066-

205

Fire Detection Instrumentation Channel Operational Test

(U-1 Zones 6, 8, 9, 12, 13[4kV], 14[RCT], 15[4kV], 17, 19,

21, 23 and 24)

2-FPP-4030-

066-204

Fire Detection Instrumentation Channel Operational Test

(U-2 Zones 1, 3, 4, 5, 7, 8, 10, 17, 18, 19, 21, 23, 25, 27, and

28)

Procedures

2-FPP-4030-

066-205

Fire Detection Instrumentation Channel Operational Test

(U-1 Zones 6, 8, 9, 12, 13[kV], 14[RCT], 15[4kV], 17, 19, 21,

23, and 24)

Work Orders

55548577-01

U1 Switchgear Cable Vault CO2 Fire Suppression Test

07/29/2021

22-2543

Variable Spring Support Setting Out of Tolerance

04/01/2022

22-2701

Boric Acid Deposit on U1 SWI Piping Suspect Through Wall

04/05/2022

22-2941

RCP #12 Shaft Seal Lower Housing Cap Screws are

Corroded

04/13/2022

22-6922

VT-2 Task Not Performed for Completed Work During

U1C31

08/30/2022

22-7339

Missed Construction Code Exam on E RHR Min-Flow Line

U1C31

09/20/2022

22-8007

Potential Trend of Missing Components from ISI Program

10/08/2022

Corrective Action

Documents

23-5741

Exam Item No. and Associated Welds Missing from ISI

Program

08/10/2023

71111.08P

Corrective Action

23-7287

Issues with Records for WO 55512999-02

10/13/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Resulting from

Inspection

AR 2022-2646-1

RCP Shaft Seal is Overflowing Down the Side of the

Pump

04/26/2022

AR 2022-4046-1

Boric Acid on Bottom of U1 Lower Vessel

06/07/2022

Engineering

Evaluations

AR 2023-3461-1

Unit 1 North SI Pump Mechanical Seal Boric Acid Leak

05/30/2023

U1-MT-23-001

Surface Exam (MT) of Pressurizer Support Weld 1-PZR-26

10/28/2023

U1-UT-23-001

Volumetric Exam of RH Pipe Weld 1-RH-28-12S

10/31/2023

U1-UT-23-002

Volumetric Exam of RH Pipe Weld 1-RH-28-13S

10/31/2023

U1-UT-23-016

Volumetric Exam of FW Pipe Weld 1-FW-12-02S

10/31/2023

U1-UT-23-017

Volumetric Exam of FW Pipe Welds 1-FW-12-03S

10/31/2023

U1-VT-23-017

Visual Examination of BMI Penetration Welds

10/25/2023

NDE Reports

U1-VT-23-018

Visual Examination of BMI Penetration Nozzle DM Welds

10/25/2023

2-QHP-5050-

NDE-002

Magnetic Particle Examination

2-QHP-5050-

NDE-027

Visual Examination for Boric Acid and Condition of

Component Surface

PMP-5030-001-

001

Boric Acid Corrosion Control

WDI-STD-1185

Generic Ultrasonic Examination Procedure for Ferritic Welds

in Accordance with PDI-UT-1

Procedures

WDI-STD-1186

Generic Ultrasonic Examination Procedure for Austenitic

Welds in Accordance with PDI-UT-2

Work Orders

55512999-02

1-SI-158-L2 Replace Valve

05/25/2022

71111.11A

Miscellaneous

Requalification

Program Annual

Testing Summary

Results

Licensed Operator Annual Examination Performance

Records for 2023

10/30/2023

AR 2023-1949

1-PP-85 Outboard Bearing is Hot

03/08/2023

AR 2023-1997

1-PP-*N Outboard Bearing is Hot to the Touch

03/09/2023

AR 2023-8958

U1 S NESW Pump Trip/Motor Fire

11/26/2023

AR 2023-9030

1-PP-8s Motor Grounding Bolt Broke Off

11/28/2023

71111.12

Corrective Action

Documents

GT 2022-9972

Complete a Risk Assessment for Ice Basket Restoration

2/08/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Maintenance Rule Scoping Document - Ice Condenser

Engineering

Evaluations

Ice Condenser - Unit 1 (a)(1) Action Plan Revision

10/03/2023

Procedures

2-EHP-4030-

010-262

Ice Condenser Surveillance and Operability Evaluation

Corrective Action

Documents

AR 2023-7908

U1 AB EDG Auto Voltage Regulator Did Not Respond as

Expected

10/25/2023

Unit 1 Online Risk, Cycle 128 Week 12

0, 1, 2

Miscellaneous

Unit 1 Online Risk, Cycle 128 Week 12

0, 1, 2

2-IHP-6030-032-

001

Emergency Diesel Generator Automatic Voltage Regulator

Timing and Adjustment

009

2-IHP-6030-032-

004

Emergency Diesel Generator Woodward 2301A Analog

Governor Tuning and Adjustment

017

71111.13

Procedures

PMP-4100-SDR-

2

Outage Risk Assessment Management

2

AR 2010-3656-21

Revise 12-IHP-5021-EMP-033

08/09/2010

AR 2010-3732

1-AB Diesel Fuel Oil Pump Cable Failures

AR 2018-7809

Error in AEP-15-46

08/06/2018

AR 2022-1764

RCP #2 Seal is Sticking Open

2/28/2023

AR 2022-7453

Unit 1 Generator Hydrogen Consumption Elevated

09/22/2022

AR 2022-9452

U2 Steam Seal Degraded

11/17/2022

AR 2022-9698

Unit 1 RCS In-Leakage Trend

11/29/2022

AR 2023-5879

Elevated Noise at 12AB Loop Feed Enclosure

08/16/2023

AR 2023-7398

West Motor Driven Aux Feed Pump Did Not Restart

10/15/2023

AR 2023-8319

Char Testing Identified Short on Outer Shield to Ground

(Source Range Instrumentation)

11/04/2023

AR 2023-9006

Elevated Radionuclide Activity Detected in Unit 1

11/28/2023

AR 2023-9354

Cracks on Walls of Battery 1-BATT-AB Cells 55 and 113

2/13/2023

Corrective Action

Documents

AR 2023-9475

Gas Void Near 1-RH-125W

2/21/2023

Miscellaneous

PMP-7030-OPR-

001 Data Sheet

  1. 3

Adverse Condition Monitoring Plan; AR 2023-9354, Cracks

on Walls of Battery 1-BATT-AB Cells 55 and 113

2/13/2023

71111.15

Operability

Evaluations

1-2022-001

Operational Decision Making Issue (ODMI); Unit 1 Main

Generator Hydrogen Usage

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1-2022-003

Operational Decision Making Issue (ODMI); 1-SV-45A

Pressurizer OME-4 Safety Valve A Leaking to the

Pressurizer Relief Tank

1-2022-003

1-SV-45A OME-4 Pressurizer OME-4 Safety Valve A is

Leaking to the Pressurizer Relief Tank

1-2022-003

1-SV-45A OME-4 Pressurizer OME-4 Safety Valve A is

Leaking to the Pressurizer Relief Tank

1-2022-003

1-SV-45A OME-4 Pressurizer OME-4 Safety Valve A is

Leaking to the Pressurizer Relief Tank

1-2023-001

RCP #2 Seal is Sticking Open

1-2023-001

RCP #2 Seal is Sticking Open

2-2022-004

Unit 2 Steam Seal System is Degraded

22-7453-2

Operational Decision Making Issue (ODMI); Unit 1 Main

Generator Hydrogen Usage

10/27/2022

AR 2023-9006

Implement 12-EHP-PER-100, Fuel Performance Monitoring

and Failed Fuel Action Plan

11/27/2023

AR 2023-9354

Cracks on Walls of Battery 1-BATT-AB Cells 55 and 113

PMP-4010-ACM-

001; Data Sheet 1

Adverse Condition Monitoring Plan; Indications of Partial

Discharge on 12AB Loop Feed Enclosure

1-EHP-4030-108-

001B

Train B Monitoring and Trending of Gas Accumulation in

ECCS

004

2-IHP-5021-

EMP-033

Cable Removal and Installation

2-IHP-5021-

EMP-033

Cable Removal and Installation

2-OHP-4022-

2-019

High Reactor Coolant Activity or Failed Fuel

Procedures

2-OHP-4022-

2-019

High Reactor Coolant Activity or Failed Fuel

005

Work Orders

5555715322

TPG, DIS, U1, Install Cable 35994-1, 35995-1, 36005-1,

36006-1

01/18/2022

71111.18

Miscellaneous

DIT-B-03776-01

Supporting Radiological Analysis Information for

Compensatory Measures on Dose Equivalent I-131 for

Postulated Natural Circulation with an Idle Faulted Steam

2/10/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Generator

PWROG-19030-P

Asymmetric Natural Circulation Cooldown - Revised

Strategies

WCAP-16632-P

Inactive Loop Flow Stagnation During Natural Circulation

Cooldown, PA-ASC-0145

AR 2023-7312

1-RH-144; East RHR Upper Compartment Spray Ring

Header Draw Valve

10/14/2023

AR 2023-7321

1-NLP-151-IE; Instrument Equalization Valve

10/14/2023

AR 2023-7323

1-QDA-21; RCP 2 Thermal Barrier DP Alarm Switch

10/14/2023

AR 2023-7330

1-RC-142; RC Loop 1 XTMA 1-NPS-122 Pressure Indicator,

1-NPI-110, and Hot Leg Sample 1-NSX-101 Drain Valve

10/14/2023

AR 2023-7343

1-NFP-222-V2; RC Loop 2 Channel 3 Differential Flow

Instrument, 1-NFP-222 Low Side Root Valve 10/14/2023

AR 2023-7348

1-SI-167-2; Accumulator 2 Outlet and SI Pumps to RC Loop

Cold Leg Test Line Drain Valve

10/14/2023

AR 2023-7353

1-SI-156E; RHR East HX and North SI Pump RC Loop 1

Loop Hot Leg Drain Valve

10/14/2023

AR 2023-7392

1-RC-140; RX Vessel Level Indicators Hi-Pressure Root

Valve

10/15/2023

AR 2023-7421

RHR 1-ICM-129 Between Seat Equalization Line Connection

Valve

10/16/2023

AR 2023-7434

1-QRV-114; Excess Letdown to Excess Letdown

HX 1-HE-13 Train A Shutoff Valve

10/16/2023

Corrective Action

Documents

AR 2023-7447

1-OME-3-2/3; No. 2 Steam Generator (Manway Cover)

10/16/2023

DIT-10037-00

Unit 1 Cycle 31 End-of-Cycle (EOC) Time-to-Boil Information

08/29/2023

DIT-10038-00

Unit 1 Cycle 32 Beginning-of-Cycle (BOC) Time-to-Boil

Information

08/29/2023

Miscellaneous

PMP-4015-RMP-

001: Data Sheet 1

Reactivity Management Guidance Form: Unit 1 Cycle 31

TREVI Testing Downpower and Shutdown

10/05/2023

Operability

Evaluations

1-OHP-4030-103-

2E

East Centrifugal Charging Pump Operability Test

24

71111.20

Procedures

PMP-4100-SDR-

2

Outage Risk Assessment and Management

71111.24

Corrective Action

AR 2023-9010

Cell 88 Fill Cap Found Off 1-BATT-CD

11/28/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Resulting from

Inspection

Engineering

Evaluations

Projected Net Weights Report (4/15/2028) U1C35

10/24/2023

1-OHP-4030-108-

053A

E.C.C.S. Valve Operability Test

031

1-OHP-4030-108-

053B

E.C.C.S. Valve Operability Test

033

1-OHP-4030-116-

20E

East Component Cooling Water Loop Surveillance Test,

2-EHP-4030-

010-262

Ice Condenser Surveillance and Operability Evaluation

28

2-IHP-4030-046-

001

Unit 1 and 2 Personnel Airlock Leak Rate Surveillance

2

2-IHP-4030-082-

005

AB, CD, and N-Train Battery Monthly Surveillance and

Maintenance

2-IHP-5030-

EMP-001

Limitorque Valve Operator Preventive Maintenance

048

2-IHP-5030-

EMP-014

MOV Diagnostic Testing

2-MHP-4030-

010-007

Ice Condenser BSKET Surveillance

2-OHP-4030-208-

053A

East Residual Heat Removal Heat Exchanger HE-17E Outlet

Flow Control Valve 2-IRV-310 Stroke Test - RHR Shutdown

Procedures

2-OHP-4030-232-

27AB

DG2AB Slow Speed Start

C10008429-001

1-SV-1A-2, Assist with Setpoint Test

10/12/2023

C10008431001

1-SV-1A-3, Perform Setpoint Test/Adjust (RIP)

10/12/2023

C10008437001

1-SV-1B-2, Perform Setpoint Test/Adjustment (RIP)

10/12/2023

C10008522-001

1-SV-2A-3, Perform Setpoint Test/Adjust (RIP)

10/12/2023

C10008769-001

1-SV-2B-3, Perform Setpoint Test/Adjustment (RIP)

10/12/2023

C10008775-001

1-SV-3-3, Perform Setpoint Test/Adjustment (RIP)

10/12/2023

Work Orders

C10009919-001

1-SV-2B-2, Perform Setpoint Test/Adjustment (RIP)

10/12/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

(Trevitest)

C1002647001

Unit 1 Lower Ice Perform Door Surveillance 1-DR-CNT642-1

and Install Blast Shield

RMA-2080-EPA-008 Screening Form # 22-33

06/22/2022

RMA-2080-EPA-008 Screening Form # 23-17

05/11/2023

CFR 50.54 (Q) Reviewer Qualification Records

(Spreadsheet)

07/05/2023

Miscellaneous

RMA-2080-EPA-008 Screening Form # 22-47

11/17/2022

CEP

Donald C. Cook Emergency Plan

CEP

Donald C. Cook Emergency Plan

PMP-2080-EPP-

101

Emergency Classification

PMP-2080-EPP-

101

Emergency Classification

71114.04

Procedures

PMP-2080-EPP-

101

Emergency Classification

PMP-6010-ALA-

001

This ALARA Plan is to Provide Assistance to Personnel

Assigned to Perform Preventative and Corrective

Maintenance Activities for Primary and Secondary Valves in

the Containment & Auxiliary Buildings During U1C32.

ALARA Plans

RWP 231151

Remove Lower Motor Oil Spill Pans, Instrumentation,

Inspect/Replace Seal Package: Support Work on the RCP

22-9808

Individual Observed Exiting RCA after Turning in DLR.

2/01/2022

Corrective Action

Documents

23-5650

Unlocked Gate

09/27/2023

Corrective Action

Documents

Resulting from

Inspection

23-7980

Whole Body Counter was Using the Previous Calibration

Data

10/26/2023

Historical Alpha Data Characterization.xlsx

10/15/2023

Miscellaneous

Lapel air sampler

data

Lapel Air Sampler Usage by Employees During the

Refueling Outage

10/25/2023

2-THP-6010-

RPP-418

Radiological Posting

71124.01

Procedures

2-THP-6010-

Monitor Alarm Response and Personnel Decontamination

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

RPP-703

PMP-6010-RPP-

003

High, Locked High, and Very High Radiation Area Access

CNP-2310-00060

Flux Map Investigational Survey

10/19/2023

Radiation

Surveys

CNP-2310-00386

1-CTS-131W Valve Breach

10/24/2023

231128

U1C32 - Valve Activities in the Auxiliary Building,

Containment, and Plant Radiologically Controlled Areas

(RCA)

Radiation Work

Permits (RWPs)

231151

Remove Lower Motor Oil Spill Pans, Instrumentation,

Inspect/Replace Seal Package: Support Work on the RCP

Self-Assessments GT 2022-8073-2

Quick Hit Self-Assessment - 71124.01 Radiological Hazard

Assessment and Exposure Controls

Work Orders

5555685602

1-CTS-131W, Inspect Valve Internals for IST Inspection

10/24/2023

MSPI Derivation Report - MSPI Emergency AC Power

System (October 2022 - September 2023) - Unit 1

MSPI Derivation Report - MSPI Emergency AC Power

System (October 2022 - September 2023) - Unit 2

Operations Narrative Logs

Reactor Coolant System Leakage Performance Indicator

Data (October 2022 - September 2023) - Unit 1

Reactor Coolant System Leakage Performance Indicator

Data (October 2022 - September 2023) - Unit 2

Data Sheet 10

Reactor Coolant System Specific Activity

Various

Data Sheet 15

Occupational Exposure Control Effectiveness

Various

Miscellaneous

Data Sheet 16

RETS/ODCM Radiological Effluent Occurrences

Various

71151

Procedures

PMP-5078-STD-

2

Surveillance Test Interval Control

21-5416

Mistras Services on Hold

06/16/2021

Corrective Action

Documents

21-7084

Conditions Imposed on Mistras Services

08/17/2021

Corrective Action

Documents

Resulting from

Inspection

23-7857

Mistras Vendor

10/24/2023

71152A

Engineering

AR 2023-7857

Falsification Inspection Records for 1-OME-25 Reactor

10/31/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Evaluations

Vessel OME-1 Head Lifting Rig and 1-OME-26 Reactor

Vessel OME-1 Internals Lifting Rig

C1006949

Contract Release C1006949 to Contract 1588238

04/18/2023

Miscellaneous

Letter from

MISTRAS to DC

Cook

Acoustic Emission Equipment Nonconformance Update

04/04/2023

Work Orders

55520965-01

1-OME-25, MISTRAS, Perform Acoustic Test of Head Lift

Rig

03/10/2019