—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection
ML24141A216
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 05/20/2024
From: Michael Ziolkowski
NRC/RGN-III/DRSS
To: Lies Q
Indiana Michigan Power Co
References
Download: ML24141A216 (1)


Text

Q. Shane Lies Senior VP and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106

SUBJECT:

DONALD C. COOK NUCLEAR POWER PLANT UNITS 1 AND 2INFORMATION REQUEST TO SUPPORT THE NRC ANNUAL BASELINE EMERGENCY ACTION LEVEL AND EMERGENCY PLAN CHANGES INSPECTION

Dear Q. Shane Lies:

This letter is to request information to support the Emergency Action Level and Emergency Plan change inspection that will be conducted during the third and fourth quarters of 2024. This inspection will be performed as an in-office review and in accordance with the U.S. Nuclear Regulatory Commission (NRC) baseline inspection procedure Inspection Procedure 71114.04.

The list of requested documents needed from your staff for this inspection is enclosed. We are requesting that these documents are for the time period specified in the list, as applicable.

The point of contact for this request is Jure Kutlesa, Region III Senior Emergency Preparedness Inspector, and can be reached at 630-829-9860. We will keep in close communications with the Emergency Preparedness staff at your site regarding this request and the inspection when performed.

This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.

May 20, 2024

Q. Lies 2

This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Michael E. Ziolkowski, Chief Security, Emergency Preparedness, and Incident Response Branch Division of Radiological Safety and Security Docket Nos. 50-315; 50-316 License Nos. DPR-58, DPR-74,

Enclosure:

Emergency Action Level and Emergency Plan Changes Inspection Document Request cc: Distribution via LISTSERV Signed by Ziolkowski, Michael on 05/20/24

ML24141A216

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available OFFICE RIII/DRSS RIII/DRSS NAME JKutlesa:dc MZiolkowski DATE 05/20/2024 05/20/2024

Enclosure EAL AND EMERGENCY PLAN CHANGES INSPECTION DOCUMENT REQUEST Please have the documents uploaded to a share file or web-based platform for our inspectors to access no later than July 15, 2024. Contact Jure Kutlesa with any questions about the electronic submittal.

Documents:

1.

Current revision of the Emergency Plan 2.

Current Emergency Action Level (EAL) scheme 3.

Most recent Safety Evaluation Report for the Emergency Plan and EALs 4.

On Shift Staffing Analysis baseline 5.

Most recent Evacuation Time Estimate 6.

Governing site document for Title 10 of the Code of Federal Regulations (CFR), Part 50.54(q) evaluation process 7.

Title 10 CFR 50.54(q) Evaluator Training Program and Qualification Records 8.

Title 10 CFR 50.54(q) Screenings and Evaluations for Emergency Plan and EAL changes that were completed between July 1, 2023, and June 30, 2024 9.

For each change of the Emergency Plan and EALs, submit the previous revision, proposed revision, and the associated 50.54(q) screening and evaluation (if performed) 10.

Corrective Action Program entries related to 50.54(q) screenings, 50.54(q) evaluations, EAL changes and Emergency Plan changes dated between July 1, 2023, and June 30, 2024