05000316/LER-2024-004, AB Emergency Diesel Generator Inoperable for Longer than Allowed by Technical Specifications

From kanterella
Jump to navigation Jump to search
AB Emergency Diesel Generator Inoperable for Longer than Allowed by Technical Specifications
ML24316A006
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 11/11/2024
From: Dailey S
Indiana Michigan Power Co
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
AEP-NRC-2024-83 LER 2024-004-00
Download: ML24316A006 (1)


LER-2024-004, AB Emergency Diesel Generator Inoperable for Longer than Allowed by Technical Specifications
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications

10 CFR 50.73(a)(2)(v), Loss of Safety Function
3162024004R00 - NRC Website

text

INDIANA MICHIGAN POWER.

An AEP Company BOUNDLESS ENERGY-November 11, 2024 Docket No.: 50-316 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 Donald C. Cook Nuclear Plant Unit 2 LICENSEE EVENT REPORT 316/2024-004-00 Indiana Michigan Power Cook Nuclear Plant One Cook Place Bridgman, Ml 49106 indianamichiganpower.com AEP-NRC-2024-83 10 CFR 50.73 2AB Emergency Diesel Generator Inoperable for longer than allowed by Technical Specifications In accordance with 10 CFR 50. 73, Licensee Event Report (LER) System, Indiana Michigan Power Company, the licensee for Donald C. Cook Nuclear Plant Unit 2, is submitting as an enclosure to this letter the following report:

LER 316/2024-004-00: 2AB Emergency Diesel Generator Inoperable for longer than allowed by Technical Specifications There are no commitments contained in this submittal.

Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Director, at (269) 466-2649.

Sincerely,

~AIU Scott A. Dailey Site Vice President MPH/sjh Enclosure:

Licensee Event Report 316/2024-004-00: 2AB Emergency Diesel Generator Inoperable for longer than allowed by Technical Specifications

U.S. Nuclear Regulatory Commission Page 2 c:

EGLE - RMD/RPS J. B. Giessner -- NRC Region Ill NRC Resident Inspector N. Quilico -- MPSC R. M. Sistevaris -- AEP Ft. Wayne S. P. Wall, NRC Washington D.C.

A. J. Williamson -- AEP Ft. Wayne AEP-NRC-2024-83

Enclosure to AEP-NRC-2024-83 Licensee Event Report 316/2024-004-00: 2AB Emergency Diesel Generator Inoperable for longer than allowed by Technical Specifications

Abstract

On May 21, 2024, with Cook Nuclear Plant (CNP) Units 1 and 2 in Mode 1 at 100% power, the 2AB EOG failed to reach the required frequency during the slow speed start surveillance, per the required acceptance criteria range of 59.5 to 60.4 Hz. The failure to reach the required frequency was originally attributed to corroded connections on the Minimum Speed Threshold and Slow Start control relays.

On July 23, 2024, the 2AB EOG, once again, failed to reach the required frequency during a surveillance run. The cause of the failure was determined to be an intermittent failure of the Digital Reference Unit (DRU). Due to the similar symptoms between the two failures of the 2AB EOG, it was determined that the 2AB EOG failure on May 21, 2024, was also due to a failure of the DRU. Due to the discovery that both EOG failures were a result of a failure of the DRU, the 2AB EOG was determined to be inoperable from the time the original condition was discovered on 05/21/2024 at 2115, until the time it successfully passed a surveillance after the DRU was replaced on 7/24/2024 at 2300.

Therefore, the identified condition is reportable, for both units, in accordance with 10 CFR 50.73(a)(2)(i)(B) as a Condition prohibited by Technical Specifications. Furthermore, during this period of time, there were instances on Unit 2 where concurrent with the 2AB EOG, the 2CD EOG was inoperable, which results in being reportable per 10 CFR 50.73(a)(2)(v) as an Event or Condition which could have prevented the fulfillment of a Safety Function. An Apparent Cause Evaluation and Root Cause Evaluation of the DRU failure are currently in progress and a supplement to this Licensee Event Report, with additional information, will be submitted upon completion.

EVENT DESCRIPTION 050 052

2. DOCKET NUMBER
3. LER NUMBER I

00316 NUMBER NO.

I YEAR SEQUENTIAL REV

~-I 004 1-0 On May 21, 2024, with Cook Nuclear Plant (CNP) Units 1 and 2 in Mode 1 at 100% power, the 2AB Emergency Diesel Generator (EDG) [DG] failed to reach the required frequency during the slow speed start surveillance, per the required acceptance criteria range of 59.5 to 60.4 Hz. The failure to reach the required frequency was originally attributed to corroded connections on the Minimum Speed Threshold and Slow Start control relays.

On July 23, 2024, the 2AB EOG, once again, failed to reach the required frequency during a surveillance run. The cause of the failure was determined to be an intermittent failure of the Digital Reference Unit (DRU). Due to the similar symptoms between the two failures of the 2AB EDG, it was determined that the 2AB EDG failure on May 21, 2024, was also due to the failure of the DRU.

Unit 2 Limiting Condition of Operation (LCO) 3.8.1 requires two diesel generators (DGs) capable of supplying the onsite Class 1 E power distribution subsystem(s) to be OPERABLE in MODE 1. Additionally, Unit 1 LCO 3.8.1 requires the Unit 2 EDG(s) to be capable of supporting the associated equipment required to be OPERABLE by LCO 3.7.8, Essential Service Water (ESW) System [Bl]. If both Unit 1 ESW trains are cross-tied to Unit 2, then the two Unit 2 EDGs are required to be OPERABLE. The maximum COMPLETION TIME allowed to restore an inoperable EDG to OPERABLE status in MODE 1 is 14 days. With this COMPLETION TIME not met, then the affected Unit is required to be in MODE 3 in 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and MODE 5 in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

Due to the discovery that both EDG failures were a result of a failure of the DRU, the 2AB EDG was determined to be inoperable from the time the original condition was discovered on 05/21/2024 at 2115, until the time it successfully passed a surveillance after the DRU was replaced on 7/24/2024 at 2300. The period of time that the 2AB EDG was determined to be INOPERABLE exceeds the time allowed by LCO 3.8.1. Therefore, the identified condition is reportable in accordance with 10 CFR 50.73(a)(2)(i)(B) as a Condition prohibited by Technical Specifications, for Units 1 and 2.

Additionally, during this period of time, it was determined that the redundant EDG (2CD) was INOPERABLE for surveillance and maintenance activities during the following times:

05/22/2024 21 :08 - 05/22/2024 22:33 U2 CD INOPERABLE for U1 ESW surveillance 05/30/2024 07:05 - 05/30/2024 14:50 U2 CD INOPERABLE for maintenance 06/03/2024 20: 15 - 06/04/2024 01 :25 U2 CD INOPERABLE for surveillance activities 07/09/2024 19:34 - 07/10/2024 00:15 U2 CD INOPERABLE for surveillance activities 07/10/2024 20:52 - 07/10/2024 21 :46 U2 CD INOPERABLE for U2 ESW surveillance Additionally, LCO 3.8.1 contains a Prescribed Action to declare supported systems inoperable upon discovery of the inoperability of redundant required features concurrent with DG inoperability, with a Completion Time of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. During the time that the 2AB EDG was determined to be inoperable, there were instances where supported systems should have been declared inoperable. Therefore, during these instances, as well as the 5 instances that 2CD EDG was INOPERABLE for surveillance and maintenance activities, the identified condition is reportable per 10 CFR 50.73(a)(2)(v) as an Event or Condition which could have prevented the fulfillment of a Safety Function for Unit 2.

COMPONENT 2-DGAB-DRU - 2AB EDG DRU CAUSE OF THE EVENT

2. DOCKET NUMBER
3. LER NUMBER I

00316 NUMBER NO.

I YEAR SEQUENTIAL REV

~-I 004 1-0 An Apparant Cause Evaluation (ACE) is in progress at the time of the writing of this LER, to determine the cause and corrective actions associated with the 2AB EOG DRU failure. Additionally, a Root Cause Evaluation (RCE) is in progress to determine why the station failed to identify and correct the cause of the 2AB EOG Surveillance failure that occurred on May 21, 2024. A supplement to this LER will be submitted upon completion of these cause evaluations.

CORRECTIVE ACTIONS The corrective actions will be provided in a supplement to this LER upon completion of the ACE and RCE.

ASSESSMENT OF SAFETY CONSEQUENCES NUCLEAR SAFETY A probabilistic risk assessment (PRA) was performed to estimate the impact of the 2AB EOG inoperability on Core Damage Frequency (CDF) and Large Early Release Frequency (LERF). Further review of the condition was performed to identify appropriate PRA mapping for this assessment. This review concluded that for the frequencies observed during the failed surveillances, the 2AB EOG would have been able to meet its PRA success criteria. However, this review was unable to eliminate the potential for the failed DRU to result in an EOG failure during its mission time. To capture these insights, this assessment was performed by assuming a higher failure probability for the 2AB EOG.

The evaluation used the average test/maintenance internal events and fire PRAs to estimate an increase in CDF and LERF over an assumed 63-day exposure time. These results are within the bounds for "Very Low Safety Significance" as described within NRC Inspection Manual Chapter 0609.

INDUSTRIAL SAFETY There was no actual or potential industrial safety hazard resulting from the 2AB EOG lnoperability.

RADIOLOGICAL SAFETY There was no actual or potential radiological safety hazard resulting from the 2AB EOG lnoperability.

PREVIOUS SIMILAR EVENTS A review of Licensee Event Reports for the past five years found no similar events. Page 3

of 3