|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217M1851999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates JPN-99-035, Forwards Comments on Version 2 of Reactor Vessel Integrity Database for Plant.Table Listing Recommended Changes to Info in Rvid,Encl as Attachment 11999-10-15015 October 1999 Forwards Comments on Version 2 of Reactor Vessel Integrity Database for Plant.Table Listing Recommended Changes to Info in Rvid,Encl as Attachment 1 JPN-99-034, Forwards Proposed risk-informed ISI Program,Provided from NRC Review & Approval as Alternative to Current ASME Section XI Insp Requirements for Class 1 & 2 Piping1999-10-13013 October 1999 Forwards Proposed risk-informed ISI Program,Provided from NRC Review & Approval as Alternative to Current ASME Section XI Insp Requirements for Class 1 & 2 Piping JPN-99-033, Provides Response to Questions Contained in 990712,facsimile from NRC Re Ja FitzPatrick USI A-46 Program.Questions Were Also Discussed Between Members of Util & NRC Staff During Telcon1999-10-0808 October 1999 Provides Response to Questions Contained in 990712,facsimile from NRC Re Ja FitzPatrick USI A-46 Program.Questions Were Also Discussed Between Members of Util & NRC Staff During Telcon JPN-99-030, Forwards Application for Amend to License DPR-59,proposing Change to TS 3.5.B.3 & Associated Bases to Extend LCO Allowable Out of Service Time for RHRSW Sys from 7 Days to 11 Days1999-09-29029 September 1999 Forwards Application for Amend to License DPR-59,proposing Change to TS 3.5.B.3 & Associated Bases to Extend LCO Allowable Out of Service Time for RHRSW Sys from 7 Days to 11 Days JPN-99-032, Forwards Info Re Potential Environ Effects of Alternatives to Proposed Expansion of FitzPatrick Spent Fuel Pool,In Response to NRC Project Manager Request1999-09-29029 September 1999 Forwards Info Re Potential Environ Effects of Alternatives to Proposed Expansion of FitzPatrick Spent Fuel Pool,In Response to NRC Project Manager Request ML20212F8341999-09-22022 September 1999 Forwards Insp Rept 50-333/99-07 on 990718-0828.No Violations Noted JAFP-99-0262, Forwards Voluntary Response to Administrative Ltr 99-03, Re Preparation & Scheduling of Operator Licensing Exams. Completed NRC Form 536,containing Info Re Proposed Exam Preparation Schedule & Initial Operator License Exams,Encl1999-09-16016 September 1999 Forwards Voluntary Response to Administrative Ltr 99-03, Re Preparation & Scheduling of Operator Licensing Exams. Completed NRC Form 536,containing Info Re Proposed Exam Preparation Schedule & Initial Operator License Exams,Encl ML20212A8341999-09-0909 September 1999 Requests That Licensees Affected by Kaowool Fire Barriers Take Issue on Voluntary Initiative & Propose Approach for Resolving Subj Issues.Staff Plans to Meet with Licensees to Discuss Listed Topics ML20212A6951999-09-0909 September 1999 Requests That Licensees Affected by Kaowool Fire Barriers Take Issue on Voluntary Initiative & Propose Approach for Resolving Subj Issues.Staff Plans to Meet with Licensees to Discuss Listed Topics 05000333/LER-1998-015, Forwards LER 98-015-02 Re Logic Sys Functional Test Inadequacies,Per 10CFR50.73(A)(2)(i)(B).Rept Revised to Reflect Scheduled Completion Date for Corrective Action 3 of Jan 15, 2000 & Updates Status of Other C/As as Complete1999-09-0808 September 1999 Forwards LER 98-015-02 Re Logic Sys Functional Test Inadequacies,Per 10CFR50.73(A)(2)(i)(B).Rept Revised to Reflect Scheduled Completion Date for Corrective Action 3 of Jan 15, 2000 & Updates Status of Other C/As as Complete ML20211N4301999-09-0808 September 1999 Discusses Proposed Meeting to Discuss Kaowool Fire Barriers. Staff Requesting That Affected Licensees Take Issue on Voluntary Initative & Propose Approach for Resolving Issues JAFP-99-0258, Forwards Operator License Restriction Change for Tj Pelton, License SOP-10090-3.License Is Requested to Be Reissued with Restriction for Corrective Lenses.Encl Withheld1999-09-0808 September 1999 Forwards Operator License Restriction Change for Tj Pelton, License SOP-10090-3.License Is Requested to Be Reissued with Restriction for Corrective Lenses.Encl Withheld JPN-99-028, Informs That Util Requires Extension from 990901 to 1015,to Complete Review of Rvid & Forward Comments to Nrc,Per GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity1999-08-30030 August 1999 Informs That Util Requires Extension from 990901 to 1015,to Complete Review of Rvid & Forward Comments to Nrc,Per GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity JAFP-99-0247, Forwards JAFNPP Effluent & Waste Disposal Semi-Annual Rept for 990101-0630, IAW Amend 93,App B,Section 7.3.C of Plant Ts.Format Used for Rept Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 41999-08-26026 August 1999 Forwards JAFNPP Effluent & Waste Disposal Semi-Annual Rept for 990101-0630, IAW Amend 93,App B,Section 7.3.C of Plant Ts.Format Used for Rept Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 4 JAFP-99-0245, Informs That Two Licensed Operators Have Returned to Site Upon Release for Normal Duties by Physician.R Korthas, License OP-11159,meets ANSI Std 3.4-1983 & R Sarkissian License SOP-10007-3,was Terminated in Mar 19991999-08-19019 August 1999 Informs That Two Licensed Operators Have Returned to Site Upon Release for Normal Duties by Physician.R Korthas, License OP-11159,meets ANSI Std 3.4-1983 & R Sarkissian License SOP-10007-3,was Terminated in Mar 1999 ML20210U2621999-08-12012 August 1999 Forwards Insp Rept 50-333/99-06 on 990601-0717.No Violations Noted JPN-99-025, Forwards Relief Request 17 Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) for Reactor Pressure Vessel Circumferential Shell Weld Exams1999-08-0505 August 1999 Forwards Relief Request 17 Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) for Reactor Pressure Vessel Circumferential Shell Weld Exams JPN-99-026, Forwards Relief Requests 18 & 19 to Jaf ISI Program Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) & Relief from ASME Section XI Code Re Insp of RPV Vertical Shell & Shell to Flange Welds1999-08-0505 August 1999 Forwards Relief Requests 18 & 19 to Jaf ISI Program Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) & Relief from ASME Section XI Code Re Insp of RPV Vertical Shell & Shell to Flange Welds ML20216D9421999-07-28028 July 1999 Forwards Safety Evaluation Granting Requests for Relief from Requirements of ASME Code,Section XI for Second 10-year ISI Interval for James a FitzPatrick NPP JAFP-99-0229, Forwards Three Sets of Corrected Summaries of Changes for Inclusion Into Security Plan for Ja FitzPatrick Nuclear Power Plant,Rev 19 & Security Contingency Plan,Rev 5.Encls Withheld Per 10CFR73.21 & 10CFR2.790)d)(1)1999-07-22022 July 1999 Forwards Three Sets of Corrected Summaries of Changes for Inclusion Into Security Plan for Ja FitzPatrick Nuclear Power Plant,Rev 19 & Security Contingency Plan,Rev 5.Encls Withheld Per 10CFR73.21 & 10CFR2.790)d)(1) JAFP-99-0228, Forwards Rept Re Changes & Errors in ECCS Evaluation Models, Per 10CFR50.46(a)(3)(ii) for Period from 980701-990630.No Commitments Contained in Submittal1999-07-21021 July 1999 Forwards Rept Re Changes & Errors in ECCS Evaluation Models, Per 10CFR50.46(a)(3)(ii) for Period from 980701-990630.No Commitments Contained in Submittal ML20210A7001999-07-16016 July 1999 Forwards Request for Addl Info to Supplement Response Provided for GL 97-05, Steam Generator Tube Insp Techniques JAFP-99-0208, Provides Clarification of Info Re Proposed Its, & 0601.Table Reconciling Differences,Encl1999-07-14014 July 1999 Provides Clarification of Info Re Proposed Its, & 0601.Table Reconciling Differences,Encl ML20209D5511999-07-0606 July 1999 Informs That as Result of NRC Review of Licensee Response to GL 92-01,rev 1,suppl 1,staff Revised Info in Reactor Vessel Integrity Database & Releasing Database as Rvid Version 2 ML20210C9031999-06-30030 June 1999 Summarizes Impact of Changes & Errors in Methodology Used by GE to Demonstrate Compliance with ECCS Requirements of 10CFR50.46.Summary of Changes & Errors Provided in Attached Table JPN-99-021, Forwards Application for Amend to License DPR-59,changing to Pressure Temp Limits.Pressure Temp Curves & Associated LCO & Bases Changes Included in Proposed Amend1999-06-22022 June 1999 Forwards Application for Amend to License DPR-59,changing to Pressure Temp Limits.Pressure Temp Curves & Associated LCO & Bases Changes Included in Proposed Amend JPN-99-020, Submits Response to RAI Re ISI Program Relief Requests for Second 10-yr Interval Closeout & Summary Rept,Per 990426 Telcon with Nrc.Info Provided to Clarify or Withdraw Individual Relief Requests Contained in Summary Rept1999-06-21021 June 1999 Submits Response to RAI Re ISI Program Relief Requests for Second 10-yr Interval Closeout & Summary Rept,Per 990426 Telcon with Nrc.Info Provided to Clarify or Withdraw Individual Relief Requests Contained in Summary Rept ML20196G2981999-06-18018 June 1999 Forwards Insp Rept 50-333/99-04 on 990412 to 0529.Violations Being Treated as non-cited Violations ML20212J0541999-06-17017 June 1999 Responds to Requesting That NRC Staff ...Allow BWR Plants Identified to Defer Weld Overlay Exams Until March 2001 or Until Completion of NRC Staff Review & Approval of Proposed Generic Rept,Whichever Comes First JPN-99-019, Withdraws Recent Exemption Request Re 10CFR50,App R, Use of Core Spray to Achieve Safe Shutdown. Exemption Dealt with Use of Core Spray for Reactor Coolant Makeup to Achieve Safe Shutdown in One Fire Area at Plant1999-06-15015 June 1999 Withdraws Recent Exemption Request Re 10CFR50,App R, Use of Core Spray to Achieve Safe Shutdown. Exemption Dealt with Use of Core Spray for Reactor Coolant Makeup to Achieve Safe Shutdown in One Fire Area at Plant ML20196L1451999-06-0707 June 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Ss Bajwa Will Be Section Chief for Ja Fitzpatrick & Indian Point NPPs JPN-99-018, Forwards Revised Application,Previously Submitted,For Amend to Plant TS for Converting CTS to ITS Consistent with Improved Std TS (NUREG-1433,Rev 1)1999-06-0101 June 1999 Forwards Revised Application,Previously Submitted,For Amend to Plant TS for Converting CTS to ITS Consistent with Improved Std TS (NUREG-1433,Rev 1) ML20207D9191999-05-27027 May 1999 Informs That on 990521 NRC Staff Held Planning Meeting to Identify Insp Activities at Facility Over Next Six Months JAFP-99-0171, Forwards Revised Ja FitzPatrick Nuclear Power Plant 1999 FSAR Update. Update Also Includes Changes to Chapter 17, QA Program Which Described in Attachment 1.No Commitments Contained in Ltr1999-05-20020 May 1999 Forwards Revised Ja FitzPatrick Nuclear Power Plant 1999 FSAR Update. Update Also Includes Changes to Chapter 17, QA Program Which Described in Attachment 1.No Commitments Contained in Ltr JPN-99-016, Forwards Application for Amend to License DPR-59,requesting 14 Day AOT for EDG Sys.Commitment Made by Util,Encl1999-05-19019 May 1999 Forwards Application for Amend to License DPR-59,requesting 14 Day AOT for EDG Sys.Commitment Made by Util,Encl ML20207A6751999-05-17017 May 1999 Forwards RAI Re 960626 Submittal & Suppl Related to IPEEEs for Plant.Licensee Committed to Revise Plant Fire IPEEE to Reflect Issues Associated with EPRI Fire PRA Implementation Guide within 120 Days of Issues Resolution JAFP-99-0168, Forwards Eight Operator License Renewal Applications for Listed Individuals.Without Encls1999-05-13013 May 1999 Forwards Eight Operator License Renewal Applications for Listed Individuals.Without Encls ML20206N0721999-05-11011 May 1999 Forwards Insp Rept 50-333/99-03 on 990301-0411.Four Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy JAFP-99-0160, Forwards 1998 Annual Radiological Environ Operating Rept for Ja FitzPatrick Nuclear Power Plant. Distribution for Rept Is IAW Reg Guide 10.1,Rev 41999-04-30030 April 1999 Forwards 1998 Annual Radiological Environ Operating Rept for Ja FitzPatrick Nuclear Power Plant. Distribution for Rept Is IAW Reg Guide 10.1,Rev 4 ML20206C8551999-04-27027 April 1999 Informs That Util 990406 Submittal, Licensing Rept for Reracking of Ja FitzPatrick Spent Fuel Pool,Rev 7, Will Be Marked as Proprietary & Will Be Withheld from Public Disclosure Pursuant to 10CFR2.790(b)(5) & Section 103(b) ML20205T1141999-04-22022 April 1999 Provides Comments from Technical Review of Draft Info Notice Re Unanticipated Reactor Water Draindown at Quad Cities Nuclear Power Station,Unit 2,ANO,Unit 2 & JAFNPP JPN-99-012, Informs That Authority Identified Typographical Error on Page 3 of Attachment 3 of 990331 Response to NRC RAI Re App R.Corrected Response to NRC Question 3 Is Attached1999-04-16016 April 1999 Informs That Authority Identified Typographical Error on Page 3 of Attachment 3 of 990331 Response to NRC RAI Re App R.Corrected Response to NRC Question 3 Is Attached ML20205P4641999-04-15015 April 1999 Forwards for Review & Comment Draft Info Notice That Describes Unanticipated Reactor Water Draindown at Quad Cities Nuclear Power Station Unit 2,Arkansas Nuclear One Unit 2 & Ja Fitzpatrick NPP ML20205P1991999-04-0909 April 1999 Discusses 990224 PPR & Forwards Plant Issues Matrix & Insp Plan.Advises of Planned Insp Effort Resulting from Plant PPR Review JAFP-99-0129, Submits Comments on Technical Review of Draft Info Notice Describing Unanticipated Reactor Water Draindown at Quad Cities Unit 2,ANO & FitzPatrick1999-04-0909 April 1999 Submits Comments on Technical Review of Draft Info Notice Describing Unanticipated Reactor Water Draindown at Quad Cities Unit 2,ANO & FitzPatrick JAFP-99-0127, Forwards Affidavit Signed by Holtec Which Describes Proprietary Nature of Licensing Rept & Addresses Considerations Listed in 10CFR2.790.Attachment 4 in Util Re Design Features Should Be Withheld1999-04-0808 April 1999 Forwards Affidavit Signed by Holtec Which Describes Proprietary Nature of Licensing Rept & Addresses Considerations Listed in 10CFR2.790.Attachment 4 in Util Re Design Features Should Be Withheld JAFP-99-0124, Forwards Rev 19 to JAFNPP Security Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Safeguards Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1)1999-04-0707 April 1999 Forwards Rev 19 to JAFNPP Security Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Safeguards Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1) ML20205M8941999-04-0707 April 1999 Forwards Rev 21 to App C of JAFNPP Emergency Plan & Rev 1 to EAP-32, Recovery Support Group Manager JAFP-99-0125, Forwards Rev 5 to JAFNPP Security Contingency Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1)1999-04-0707 April 1999 Forwards Rev 5 to JAFNPP Security Contingency Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1) 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARJPN-99-035, Forwards Comments on Version 2 of Reactor Vessel Integrity Database for Plant.Table Listing Recommended Changes to Info in Rvid,Encl as Attachment 11999-10-15015 October 1999 Forwards Comments on Version 2 of Reactor Vessel Integrity Database for Plant.Table Listing Recommended Changes to Info in Rvid,Encl as Attachment 1 JPN-99-034, Forwards Proposed risk-informed ISI Program,Provided from NRC Review & Approval as Alternative to Current ASME Section XI Insp Requirements for Class 1 & 2 Piping1999-10-13013 October 1999 Forwards Proposed risk-informed ISI Program,Provided from NRC Review & Approval as Alternative to Current ASME Section XI Insp Requirements for Class 1 & 2 Piping JPN-99-033, Provides Response to Questions Contained in 990712,facsimile from NRC Re Ja FitzPatrick USI A-46 Program.Questions Were Also Discussed Between Members of Util & NRC Staff During Telcon1999-10-0808 October 1999 Provides Response to Questions Contained in 990712,facsimile from NRC Re Ja FitzPatrick USI A-46 Program.Questions Were Also Discussed Between Members of Util & NRC Staff During Telcon JPN-99-030, Forwards Application for Amend to License DPR-59,proposing Change to TS 3.5.B.3 & Associated Bases to Extend LCO Allowable Out of Service Time for RHRSW Sys from 7 Days to 11 Days1999-09-29029 September 1999 Forwards Application for Amend to License DPR-59,proposing Change to TS 3.5.B.3 & Associated Bases to Extend LCO Allowable Out of Service Time for RHRSW Sys from 7 Days to 11 Days JPN-99-032, Forwards Info Re Potential Environ Effects of Alternatives to Proposed Expansion of FitzPatrick Spent Fuel Pool,In Response to NRC Project Manager Request1999-09-29029 September 1999 Forwards Info Re Potential Environ Effects of Alternatives to Proposed Expansion of FitzPatrick Spent Fuel Pool,In Response to NRC Project Manager Request JAFP-99-0262, Forwards Voluntary Response to Administrative Ltr 99-03, Re Preparation & Scheduling of Operator Licensing Exams. Completed NRC Form 536,containing Info Re Proposed Exam Preparation Schedule & Initial Operator License Exams,Encl1999-09-16016 September 1999 Forwards Voluntary Response to Administrative Ltr 99-03, Re Preparation & Scheduling of Operator Licensing Exams. Completed NRC Form 536,containing Info Re Proposed Exam Preparation Schedule & Initial Operator License Exams,Encl JAFP-99-0258, Forwards Operator License Restriction Change for Tj Pelton, License SOP-10090-3.License Is Requested to Be Reissued with Restriction for Corrective Lenses.Encl Withheld1999-09-0808 September 1999 Forwards Operator License Restriction Change for Tj Pelton, License SOP-10090-3.License Is Requested to Be Reissued with Restriction for Corrective Lenses.Encl Withheld 05000333/LER-1998-015, Forwards LER 98-015-02 Re Logic Sys Functional Test Inadequacies,Per 10CFR50.73(A)(2)(i)(B).Rept Revised to Reflect Scheduled Completion Date for Corrective Action 3 of Jan 15, 2000 & Updates Status of Other C/As as Complete1999-09-0808 September 1999 Forwards LER 98-015-02 Re Logic Sys Functional Test Inadequacies,Per 10CFR50.73(A)(2)(i)(B).Rept Revised to Reflect Scheduled Completion Date for Corrective Action 3 of Jan 15, 2000 & Updates Status of Other C/As as Complete JPN-99-028, Informs That Util Requires Extension from 990901 to 1015,to Complete Review of Rvid & Forward Comments to Nrc,Per GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity1999-08-30030 August 1999 Informs That Util Requires Extension from 990901 to 1015,to Complete Review of Rvid & Forward Comments to Nrc,Per GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity JAFP-99-0247, Forwards JAFNPP Effluent & Waste Disposal Semi-Annual Rept for 990101-0630, IAW Amend 93,App B,Section 7.3.C of Plant Ts.Format Used for Rept Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 41999-08-26026 August 1999 Forwards JAFNPP Effluent & Waste Disposal Semi-Annual Rept for 990101-0630, IAW Amend 93,App B,Section 7.3.C of Plant Ts.Format Used for Rept Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 4 JAFP-99-0245, Informs That Two Licensed Operators Have Returned to Site Upon Release for Normal Duties by Physician.R Korthas, License OP-11159,meets ANSI Std 3.4-1983 & R Sarkissian License SOP-10007-3,was Terminated in Mar 19991999-08-19019 August 1999 Informs That Two Licensed Operators Have Returned to Site Upon Release for Normal Duties by Physician.R Korthas, License OP-11159,meets ANSI Std 3.4-1983 & R Sarkissian License SOP-10007-3,was Terminated in Mar 1999 JPN-99-025, Forwards Relief Request 17 Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) for Reactor Pressure Vessel Circumferential Shell Weld Exams1999-08-0505 August 1999 Forwards Relief Request 17 Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) for Reactor Pressure Vessel Circumferential Shell Weld Exams JPN-99-026, Forwards Relief Requests 18 & 19 to Jaf ISI Program Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) & Relief from ASME Section XI Code Re Insp of RPV Vertical Shell & Shell to Flange Welds1999-08-0505 August 1999 Forwards Relief Requests 18 & 19 to Jaf ISI Program Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) & Relief from ASME Section XI Code Re Insp of RPV Vertical Shell & Shell to Flange Welds JAFP-99-0229, Forwards Three Sets of Corrected Summaries of Changes for Inclusion Into Security Plan for Ja FitzPatrick Nuclear Power Plant,Rev 19 & Security Contingency Plan,Rev 5.Encls Withheld Per 10CFR73.21 & 10CFR2.790)d)(1)1999-07-22022 July 1999 Forwards Three Sets of Corrected Summaries of Changes for Inclusion Into Security Plan for Ja FitzPatrick Nuclear Power Plant,Rev 19 & Security Contingency Plan,Rev 5.Encls Withheld Per 10CFR73.21 & 10CFR2.790)d)(1) JAFP-99-0228, Forwards Rept Re Changes & Errors in ECCS Evaluation Models, Per 10CFR50.46(a)(3)(ii) for Period from 980701-990630.No Commitments Contained in Submittal1999-07-21021 July 1999 Forwards Rept Re Changes & Errors in ECCS Evaluation Models, Per 10CFR50.46(a)(3)(ii) for Period from 980701-990630.No Commitments Contained in Submittal JAFP-99-0208, Provides Clarification of Info Re Proposed Its, & 0601.Table Reconciling Differences,Encl1999-07-14014 July 1999 Provides Clarification of Info Re Proposed Its, & 0601.Table Reconciling Differences,Encl ML20210C9031999-06-30030 June 1999 Summarizes Impact of Changes & Errors in Methodology Used by GE to Demonstrate Compliance with ECCS Requirements of 10CFR50.46.Summary of Changes & Errors Provided in Attached Table JPN-99-021, Forwards Application for Amend to License DPR-59,changing to Pressure Temp Limits.Pressure Temp Curves & Associated LCO & Bases Changes Included in Proposed Amend1999-06-22022 June 1999 Forwards Application for Amend to License DPR-59,changing to Pressure Temp Limits.Pressure Temp Curves & Associated LCO & Bases Changes Included in Proposed Amend JPN-99-020, Submits Response to RAI Re ISI Program Relief Requests for Second 10-yr Interval Closeout & Summary Rept,Per 990426 Telcon with Nrc.Info Provided to Clarify or Withdraw Individual Relief Requests Contained in Summary Rept1999-06-21021 June 1999 Submits Response to RAI Re ISI Program Relief Requests for Second 10-yr Interval Closeout & Summary Rept,Per 990426 Telcon with Nrc.Info Provided to Clarify or Withdraw Individual Relief Requests Contained in Summary Rept JPN-99-019, Withdraws Recent Exemption Request Re 10CFR50,App R, Use of Core Spray to Achieve Safe Shutdown. Exemption Dealt with Use of Core Spray for Reactor Coolant Makeup to Achieve Safe Shutdown in One Fire Area at Plant1999-06-15015 June 1999 Withdraws Recent Exemption Request Re 10CFR50,App R, Use of Core Spray to Achieve Safe Shutdown. Exemption Dealt with Use of Core Spray for Reactor Coolant Makeup to Achieve Safe Shutdown in One Fire Area at Plant JPN-99-018, Forwards Revised Application,Previously Submitted,For Amend to Plant TS for Converting CTS to ITS Consistent with Improved Std TS (NUREG-1433,Rev 1)1999-06-0101 June 1999 Forwards Revised Application,Previously Submitted,For Amend to Plant TS for Converting CTS to ITS Consistent with Improved Std TS (NUREG-1433,Rev 1) JAFP-99-0171, Forwards Revised Ja FitzPatrick Nuclear Power Plant 1999 FSAR Update. Update Also Includes Changes to Chapter 17, QA Program Which Described in Attachment 1.No Commitments Contained in Ltr1999-05-20020 May 1999 Forwards Revised Ja FitzPatrick Nuclear Power Plant 1999 FSAR Update. Update Also Includes Changes to Chapter 17, QA Program Which Described in Attachment 1.No Commitments Contained in Ltr JPN-99-016, Forwards Application for Amend to License DPR-59,requesting 14 Day AOT for EDG Sys.Commitment Made by Util,Encl1999-05-19019 May 1999 Forwards Application for Amend to License DPR-59,requesting 14 Day AOT for EDG Sys.Commitment Made by Util,Encl JAFP-99-0168, Forwards Eight Operator License Renewal Applications for Listed Individuals.Without Encls1999-05-13013 May 1999 Forwards Eight Operator License Renewal Applications for Listed Individuals.Without Encls JAFP-99-0160, Forwards 1998 Annual Radiological Environ Operating Rept for Ja FitzPatrick Nuclear Power Plant. Distribution for Rept Is IAW Reg Guide 10.1,Rev 41999-04-30030 April 1999 Forwards 1998 Annual Radiological Environ Operating Rept for Ja FitzPatrick Nuclear Power Plant. Distribution for Rept Is IAW Reg Guide 10.1,Rev 4 ML20205T1141999-04-22022 April 1999 Provides Comments from Technical Review of Draft Info Notice Re Unanticipated Reactor Water Draindown at Quad Cities Nuclear Power Station,Unit 2,ANO,Unit 2 & JAFNPP JPN-99-012, Informs That Authority Identified Typographical Error on Page 3 of Attachment 3 of 990331 Response to NRC RAI Re App R.Corrected Response to NRC Question 3 Is Attached1999-04-16016 April 1999 Informs That Authority Identified Typographical Error on Page 3 of Attachment 3 of 990331 Response to NRC RAI Re App R.Corrected Response to NRC Question 3 Is Attached JAFP-99-0129, Submits Comments on Technical Review of Draft Info Notice Describing Unanticipated Reactor Water Draindown at Quad Cities Unit 2,ANO & FitzPatrick1999-04-0909 April 1999 Submits Comments on Technical Review of Draft Info Notice Describing Unanticipated Reactor Water Draindown at Quad Cities Unit 2,ANO & FitzPatrick JAFP-99-0127, Forwards Affidavit Signed by Holtec Which Describes Proprietary Nature of Licensing Rept & Addresses Considerations Listed in 10CFR2.790.Attachment 4 in Util Re Design Features Should Be Withheld1999-04-0808 April 1999 Forwards Affidavit Signed by Holtec Which Describes Proprietary Nature of Licensing Rept & Addresses Considerations Listed in 10CFR2.790.Attachment 4 in Util Re Design Features Should Be Withheld JAFP-99-0124, Forwards Rev 19 to JAFNPP Security Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Safeguards Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1)1999-04-0707 April 1999 Forwards Rev 19 to JAFNPP Security Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Safeguards Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1) JAFP-99-0125, Forwards Rev 5 to JAFNPP Security Contingency Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1)1999-04-0707 April 1999 Forwards Rev 5 to JAFNPP Security Contingency Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1) ML20205M8941999-04-0707 April 1999 Forwards Rev 21 to App C of JAFNPP Emergency Plan & Rev 1 to EAP-32, Recovery Support Group Manager JPN-99-011, Forwards Application for Amend to License DPR-59,removing Position Title of General Manager from Sections & Will Delegate Responsibilities to Another Staff Member,In Writing1999-04-0505 April 1999 Forwards Application for Amend to License DPR-59,removing Position Title of General Manager from Sections & Will Delegate Responsibilities to Another Staff Member,In Writing ML20205G4111999-03-31031 March 1999 Forwards Rev 7 to JAFNPP EP App J & Rev 6,pages 7 & 8 to EAP-5.3 05000333/LER-1999-001, Forwards LER 99-001-01 Re Incorrect EDG line-up During Fire Placing Plant in Outside Design Basis.Suppl Contains Results of Completed Root Cause Evaluations & Subsequent Corrective Actions Taken.Rept Contains No Commitments1999-03-31031 March 1999 Forwards LER 99-001-01 Re Incorrect EDG line-up During Fire Placing Plant in Outside Design Basis.Suppl Contains Results of Completed Root Cause Evaluations & Subsequent Corrective Actions Taken.Rept Contains No Commitments JPN-99-008, Forwards Application for Amend to License DPR-59,converting CTS to Be Consistent with Improved Std TS in NUREG-1433, Rev 1.Synopsis of LAR for Conversion to Its,Pending Lars, List of Subsections,Scope of Changes & Commitments,Encl1999-03-31031 March 1999 Forwards Application for Amend to License DPR-59,converting CTS to Be Consistent with Improved Std TS in NUREG-1433, Rev 1.Synopsis of LAR for Conversion to Its,Pending Lars, List of Subsections,Scope of Changes & Commitments,Encl JPN-99-010, Transmits Revised Exemption Request from Some of Requirements of 10CFR50,App R.Exemption Would Permit Use of CS for Rc Makeup to Achieve Safe Shutdown in Fire Area XI at JAFNPP1999-03-31031 March 1999 Transmits Revised Exemption Request from Some of Requirements of 10CFR50,App R.Exemption Would Permit Use of CS for Rc Makeup to Achieve Safe Shutdown in Fire Area XI at JAFNPP JAFP-99-0114, Requests That License OP-11037,for Bs Brooks,Be re-issued Without Restriction for Corrective Lenses.Nrc Form 369,encl. Without Encl1999-03-29029 March 1999 Requests That License OP-11037,for Bs Brooks,Be re-issued Without Restriction for Corrective Lenses.Nrc Form 369,encl. Without Encl JAFP-99-0112, Informs of Util Determination That Listed Individuals No Longer Need to Maintain Operating License for Ja FitzPatrick Nuclear Plant.Termination of Listed Licenses,Requested1999-03-29029 March 1999 Informs of Util Determination That Listed Individuals No Longer Need to Maintain Operating License for Ja FitzPatrick Nuclear Plant.Termination of Listed Licenses,Requested JAFP-99-0097, Forwards JAFNPP Referenced Simulation Facility Four Year Performance Testing Rept, Containing Description of Performance Testing Completed During Past Four Years & Description of Testing Scheduled During Next Four Years1999-03-17017 March 1999 Forwards JAFNPP Referenced Simulation Facility Four Year Performance Testing Rept, Containing Description of Performance Testing Completed During Past Four Years & Description of Testing Scheduled During Next Four Years ML20204B6241999-03-17017 March 1999 Forwards Plant Referenced Simulation Facility Four Year Performance Testing Rept, Per 10CFR55.45(b)ii 05000333/LER-1999-003, Forwards LER 99-003-00,per 10CFR50.73(a)(2)(i)(B).One New Commitment Is Contained in Rept1999-03-16016 March 1999 Forwards LER 99-003-00,per 10CFR50.73(a)(2)(i)(B).One New Commitment Is Contained in Rept ML20204C7371999-03-15015 March 1999 Forwards Revised EP Coversheets for Sections to Vol 1 & Rev 26,Vol 3 to EPIP SAP-10, Meteorological Monitoring Sys Surveillance JAFP-99-0085, Submits in-vessel Visual Insp Summary Rept for RFO 13 for Ja FitzPatrick Nuclear Power Plant.All Relevant Indications Recorded During Insp Were Satisfactorily Dispositioned IAW Util Internal C/A Tracking Sys & Were Found Acceptable1999-03-0808 March 1999 Submits in-vessel Visual Insp Summary Rept for RFO 13 for Ja FitzPatrick Nuclear Power Plant.All Relevant Indications Recorded During Insp Were Satisfactorily Dispositioned IAW Util Internal C/A Tracking Sys & Were Found Acceptable ML20207J3201999-03-0505 March 1999 Forwards Form NRC-369,requesting That Restriction for Corrective Lenses Be Placed on Current License SOP-10089-3, for Ks Allen.Encl Withheld Per 10CFR2.790(a)(6).Without Encl JAFP-99-0073, Submits Annual Rept on SRV Challenges & Failures,Per Plant TS 6.9.A.2.b.No Challenges to SRVs from Automatic Control Circuits or from RCS Pressure Transients,Occurred.Ltr Contains No New Commitments1999-02-26026 February 1999 Submits Annual Rept on SRV Challenges & Failures,Per Plant TS 6.9.A.2.b.No Challenges to SRVs from Automatic Control Circuits or from RCS Pressure Transients,Occurred.Ltr Contains No New Commitments JAFP-99-0071, Forwards Semi-Annual Radioactive Effluent Release Rept for Period of 980701-1231. Format Used for Effluent Data Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 41999-02-25025 February 1999 Forwards Semi-Annual Radioactive Effluent Release Rept for Period of 980701-1231. Format Used for Effluent Data Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 4 JAFP-99-0068, Forwards Form NRC-5 Equivalent Records of All Individuals Monitored at JAFNPP from 980101-1231 on Electronic Media, Per 10CFR20.2206(b) & App a of NRC Reg Guide 8.7, Instruction for Recording & Reporting..1999-02-22022 February 1999 Forwards Form NRC-5 Equivalent Records of All Individuals Monitored at JAFNPP from 980101-1231 on Electronic Media, Per 10CFR20.2206(b) & App a of NRC Reg Guide 8.7, Instruction for Recording & Reporting.. JAFP-99-0019, Informs of Licensee Intent to Upgrade ERDS at Ja FitzPatrick in Preparation for Year 2000 (Y2K) Readiness,Per GL 98-01. Encl Contains Brief Summary of Proposed Changes to ERDS1999-01-25025 January 1999 Informs of Licensee Intent to Upgrade ERDS at Ja FitzPatrick in Preparation for Year 2000 (Y2K) Readiness,Per GL 98-01. Encl Contains Brief Summary of Proposed Changes to ERDS JAFP-99-0012, Documents Util Position Re Methodology for LPRM Calibr During Reactor Operation Using Traversing In-core Probe Sys1999-01-18018 January 1999 Documents Util Position Re Methodology for LPRM Calibr During Reactor Operation Using Traversing In-core Probe Sys 1999-09-08
[Table view] Category:UTILITY TO NRC
MONTHYEARJPN-90-063, Responds to NRC Re Deviations Noted in Insp Rept 50-333/90-19.Interim Corrective Action:Temporary Procedure Change Implemented to Administratively Prohibit Concurrent Closure of Upstream Feeder Breakers Until Issue Resolved1990-09-18018 September 1990 Responds to NRC Re Deviations Noted in Insp Rept 50-333/90-19.Interim Corrective Action:Temporary Procedure Change Implemented to Administratively Prohibit Concurrent Closure of Upstream Feeder Breakers Until Issue Resolved JPN-90-061, Forwards Analyses Re Installation of Hardened Wetwell Vent, Including Benefits of Elevated Vs Ground Level Gas Release. Analyses Provide Further Evidence That Addition of Elevated Release to Existing Hardened Vent Not Cost Beneficial1990-09-0707 September 1990 Forwards Analyses Re Installation of Hardened Wetwell Vent, Including Benefits of Elevated Vs Ground Level Gas Release. Analyses Provide Further Evidence That Addition of Elevated Release to Existing Hardened Vent Not Cost Beneficial JPN-90-060, Forwards Info to Satisfy 900716 Commitment Re Switchgear Deficiency,Per SSFI Insp Rept 50-333/89-80.Waiver Requested Re Design Requirements for Three Phase Bolted Fault Criteria for Switchgear Configuration for Diesel Generator Testing1990-09-0404 September 1990 Forwards Info to Satisfy 900716 Commitment Re Switchgear Deficiency,Per SSFI Insp Rept 50-333/89-80.Waiver Requested Re Design Requirements for Three Phase Bolted Fault Criteria for Switchgear Configuration for Diesel Generator Testing JPN-90-057, Forwards GE Supplemental Rept of Ultrasonic Indications in Top Head Weld VC-TH-1-2 at Ja Fitzpatrick Power Station1990-08-14014 August 1990 Forwards GE Supplemental Rept of Ultrasonic Indications in Top Head Weld VC-TH-1-2 at Ja Fitzpatrick Power Station JAFP-90-0581, Forwards Proposed Rev 6 to IAP-2, Classification of Emergency Conditions, Per Insp Rept 50-333/90-15,Unresolved Item 89-11-03.Rev Incorporates Changes Assuring That Applicable Initiating Conditions,Per NUREG-0654,addressed1990-07-30030 July 1990 Forwards Proposed Rev 6 to IAP-2, Classification of Emergency Conditions, Per Insp Rept 50-333/90-15,Unresolved Item 89-11-03.Rev Incorporates Changes Assuring That Applicable Initiating Conditions,Per NUREG-0654,addressed JPN-90-055, Forwards Comments on Installation of Hardened Wetwell Vent at Plant,Per 891027 Response to Generic Ltr 89-16.Concludes That Hardened Vent Not Cost Beneficial & Consideration of Mods Be Deferred Until Individual Plant Evaluation Complete1990-07-25025 July 1990 Forwards Comments on Installation of Hardened Wetwell Vent at Plant,Per 891027 Response to Generic Ltr 89-16.Concludes That Hardened Vent Not Cost Beneficial & Consideration of Mods Be Deferred Until Individual Plant Evaluation Complete 05000333/LER-1990-012, Advises That Suppl Rept to LER 90-012 Re Svc Water Check Valves Will Be Submitted by 9008201990-07-18018 July 1990 Advises That Suppl Rept to LER 90-012 Re Svc Water Check Valves Will Be Submitted by 900820 05000333/LER-1989-012, Advises That Suppl to LER 89-012-00 Re Postulated Fault 4 Kv Bus Fault Will Be Submitted by 9009041990-07-16016 July 1990 Advises That Suppl to LER 89-012-00 Re Postulated Fault 4 Kv Bus Fault Will Be Submitted by 900904 ML20044A9311990-07-0606 July 1990 Responds to NRC 900611 Ltr Re Violations Noted in Insp Rept 50-333/90-17.Corrective Action:Suspended Surveillances Reinstated on 900507 ML20043J0101990-06-21021 June 1990 Forwards Application for Amend to License DPR-59,making Temporary Change Re LPCI Pump Flow Permanent,Per 900228 Ltr. Change Reduced Surveillance Test Flow Acceptance Value for RHR Pump JAFP-90-0468, Informs That Licensed Operator Requalification Training Program at Plant Completed Transition to Program Based on Sys Approach to Training as Ref to in 10CFR55.4 & 591990-06-14014 June 1990 Informs That Licensed Operator Requalification Training Program at Plant Completed Transition to Program Based on Sys Approach to Training as Ref to in 10CFR55.4 & 59 ML20043G2491990-06-12012 June 1990 Forwards Application for Amend to License DPR-59,revising Tech Specs to Reflect Containment Isolation Valves in RHR & Core Spray keep-full Sys ML20043F5931990-06-11011 June 1990 Forwards GE Nonproprietary Rept, GE11 Lead Test Assembly Fo Ja Fitzpatrick Nuclear Power Plant Reload 9 Cycle 10 & Proprietary Rept GE11 Lead Test Assembly Fuel Bundle.... Proprietary Rept Withheld (Ref 10CFR2.790) ML20043G6131990-06-11011 June 1990 Responds to Notice of Violation & Proposed Imposition of Civil Penalties in Amount of $75,000 Re Radiation Exposure. Corrective Actions:Worker Decontaminated & Examined by Physician.Civil Penalty Fee Transferred Electronically ML20043H0851990-06-11011 June 1990 Forwards Reload 9/Cycle 10 Core Operating Limits Rept. ML20043G7561990-06-11011 June 1990 Forwards Application for Amend to License DPR-59 Re Performance Discharge Testing of 125-volt Dc Batteries & LPCI Motor Operated Valve Independent Power Supplies ML20043H0451990-06-0808 June 1990 Responds to NRC 900509 Ltr Re Violations Noted in Insp Rept 50-333/90-02.Corrective Actions:Refuel Floor Work Stopped, Chief Radiation Protection Technician Disciplined & Importance of Following Procedural Guidelines Reinforced ML20043E8911990-06-0707 June 1990 Forwards IGSCC Insp 1990 Refueling Outage Summary Rept Addendum ML20043C3381990-05-31031 May 1990 Forwards Application for Amend to License DPR-59,revising Tech Spec 5.5.B to Increase Number of Spent Fuel Assemblies That Can Be Stored in Spent Fuel Pool ML20043C5091990-05-30030 May 1990 Forwards Application for Amend to License DPR-59,updating Tech Spec Tables 3.2-8 & 4.2-8 to Reflect Installation of post-accident Monitoring Instrumentation,Per Reg Guide 1.97 & Deleting Tables 3.2-6,4.2-6 & 4.7-1 ML20043C7411990-05-25025 May 1990 Forwards Structural Evaluation of Indications in Reactor Top Head at Ja Fitzpatrick Power Station, Based on Evaluation Analyses for Flaw Indications Identified During Routine Inservice Insps ML20043A7681990-05-16016 May 1990 Responds to NRC Bulletin 90-002, Loss of Thermal Margin Caused by Channel Box Bow. Channel Boxes Not Reused After First Lifetime.Methodology Developed by Ge,Vendor for Plant, Used to Account for Channel Bow ML20043B1021990-05-14014 May 1990 Responds to NRC 900412 Ltr Re Violations Noted in Insp Rept 50-333/90-01.Corrective Actions:Disciplinary Actions Taken & Job Performance Counseling Provided Re Responsibilites for Control Room Operations & Command in Control Room ML20043A7471990-05-14014 May 1990 Responds to NRC 900413 Ltr Re Violations Noted in Insp Rept 50-333/90-13.Util Requests That Notice of Violation Be Withdrawn & Reclassified as Deviation & That Submittal of Inaccurate Info Be Considered Isolated Case ML20042G8271990-05-0909 May 1990 Responds to NRC 900410 Ltr Re Violations Noted in Insp Rept 50-333/90-11.Corrective Actions:Mod Error Corrected,New Transmitters Installed & Mod Procedures to Be Revised to Assign Responsibility for Calibr Points Value Calculation ML20042F3891990-04-30030 April 1990 Responds to Generic Ltr 89-19, Request for Action Re Resolution of USI A-47, 'Safety Implication of Control Sys in LWR Nuclear Power Plants.' ML20042E6251990-04-20020 April 1990 Forwards Application for Amend to License DPR-59,changing Tech Specs to Remove cycle-specific Parameter Limits & Ref Core Operating Limits Rept Which Contains Limits,Per Generic Ltr 88-16 ML20012F0361990-04-0505 April 1990 Forwards Temporary Addendum Rept for Rev 1 to Security Plan. Rept Withheld (Ref 10CFR73.21 & 2.790(d)(1)) ML20012F2161990-04-0202 April 1990 Forwards Application for Amend to License DPR-59,revising Sections 3.5.F & 4.5.F of Tech Specs, Min ECCS Availability. ML20012C9821990-03-13013 March 1990 Forwards Application for Amend to License DPR-59,changing Tech Spec Section 4.9.F, LPCI Motor-Operated Valve Independent Power Supplies, on Page 222a.Changes Purely Editorial in Nature & Revises Surveillance Requirement ML20012C0441990-03-0909 March 1990 Forwards Application for Amend to License DPR-59,clarifying Spec 3.9.B.3 Re Diesel Generator Operability to Eliminate Erroneous Ref to Both Diesel Generator Sys ML20012A1021990-03-0101 March 1990 Forwards Inservice Insp Hydrostatic Test Program for Class 2 & 3 Sys Conducted During First 10-Yr Insp Interval. Relief Requested for Second 10-yr Insp Interval for Hydrostatic Relief Requests Contained in Encl ML20012A0201990-02-28028 February 1990 Forwards Response to NRC SALP Initial Rept 50-333/88-99 for May 1988 - Sept 1989.Emergency Operating Procedures Being Upgraded to Rev 4 of Emergency Procedures Guidelines & Will Be in Place Upon Startup from Spring Refueling Outage ML20012A9301990-02-28028 February 1990 Forwards New York Power Authority Ja Fitzpatrick Nuclear Power Plant Effluent & Waste Disposal Semiannual Rept Jul-Dec 1989 & Rev 7 to Odcm. JPN-90-016, Requests That 900209 Application for Amend to License DPR-59 Be Processed on Emergency Basis & Approved by 900225 to Avoid Premature Plant Shutdown1990-02-21021 February 1990 Requests That 900209 Application for Amend to License DPR-59 Be Processed on Emergency Basis & Approved by 900225 to Avoid Premature Plant Shutdown ML20006E3921990-02-13013 February 1990 Forwards Response to Generic Ltr 89-13, Svc Water Sys Problems Affecting Safety-Related Equipment. Testing of Circulating Water/Svc Water Sys for Mussels Will Begin Spring 1990 ML20006E2681990-02-0909 February 1990 Forwards Application for Amend to License DPR-59,revising Tech Specs Re RHR Pump Operability ML20006E3321990-02-0808 February 1990 Notifies Second 10-yr Inservice Insp Interval Scheduled to End in Jul 1995 & Valve Insp During 1990,91 & 93 Refueling Outages ML20006C8271990-01-29029 January 1990 Responds to NRC 891229 Ltr Re Violations Noted in Insp Rept 50-333/89-21.Corrective Action:Background Instrumentation Results Will Be Reviewed on Periodic Basis ML20006C3811990-01-29029 January 1990 Forwards Preoutage IGSCC Insp Plan for Upcoming 1990 Refueling Outage.Util Will Not Routinely Submit Preoutage Plans in Future Per Generic Ltr 88-01 & NUREG-0313 ML20006A7771990-01-19019 January 1990 Responds to NRC Bulletin 89-002, Stress Corrosion Cracking of High Hardness Type 410 Stainless Steel Internal Preloaded Bolting in Anchor Darling Model S350W Swing-Check Valves or Valves of Similar Design. No Insp of Valves Performed ML19354E0341990-01-16016 January 1990 Forwards Application for Amend to License DPR-59,revising Tech Spec 4.11.B.2, Crescent Area Ventilation to Require Calibr of Existing Temp Indicator Controllers or New Temp Control Switches ML19354E0321990-01-16016 January 1990 Forwards Application for Amend to License DPR-59,revising Tech Spec Section 4.7.A.2 & Associated Bases Re Primary Containment Leak Rate Testing Requirements ML19354E0421990-01-16016 January 1990 Forwards Application for Amend to License DPR-59,revising Tech Specs Re Augmented Inservice Insp of Main Steam & Feedwater Piping Welds.Spec 4.6.F.2, Structural Integrity & Associated Bases on Pages 144 & 153 Deleted ML19354D8861990-01-12012 January 1990 Forwards Application for Amend to License DPR-59,modifing Tech Spec Table 3.7.1, Process Pipeline Primary Containment & Table 4.7.2, Exception to Type C Tests to Replace Traversing in-core Probe Sys ML19354D8701990-01-12012 January 1990 Forwards Application for Amend to License DPR-59,revising Note 16 to Table 3.1-1 & Note 9 to Table 3.2-1 to Increase Main Steam Line High Radiation Monitor Trip Level Setpoint During Operating Cycle 10 ML19354E0531990-01-12012 January 1990 Forwards Application for Amend to License DPR-59,revising Tech Spec 3.6.A, Pressurization & Thermal Limits, to Comply W/Generic Ltr 88-11 & Reg Guide 1.99,Rev 2 ML20005G7191990-01-12012 January 1990 Forwards Application for Amend to License DPR-59,revising Tech Spec Table 3.2-2, Instrumentation That Initiates or Controls Core & Containment Cooling Sys to Change Second Level Undervoltage Trip Setpoint for 1990 Refueling Outage ML20006A4021990-01-12012 January 1990 Forwards Application for Amend to License DPR-59,removing cycle-specific Parameter Limits from Tech Specs & Relocating Limits to Core Operating Limits Rept,Per Generic Ltr 88-16 ML20005G2671990-01-0909 January 1990 Forwards Application for Amend to License DPR-59,changing Safety Limit Min Critical Power Ratio from Current Value of 1.04 to 1.07 to Support Cycle 10 Reload Fuel Design 1990-09-07
[Table view] |
Text
e POWER AUTHORITY OF THE STATE OF NEW YORK 10 COLUMBUS CIRCLE NEW YORK. N. Y.1o019 (2121 397.6200 TRUSTEES GEORGET SERRY
' '
JOHN S.DYSON oPERAT NG OFF CER JOHN W. BOSTON CEQRGE L. ING ALLS E curi vi
, g g g vtC E CMAIRMAN OF POWE1 OPERAff 0NS RICH ARD M. rLYNN JCSEPH R. Sc IEDER RO8ERTI. MILLONZI PRE DENT 4 CHIEF r R E o ERic x R. c'^"* "
October 22, 1979 L*cOS ,'",*'
c;^%,,,,,7 JPN-79-65 *,,,
" "
"s^r'n iRvcsrRasiOrwT O'
Director, Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attention: Mr. Darrell G. Eisenhut, Acting Director Division of Operating Reactors
Subject:
James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Response to NRC Requirements Based on Studies of TMI
Reference:
Letter Darrell G. Eisenhut (NRC) to all Operating Nuclear Power Plants, Dated September 13, 1979
Dear Sir:
Enclosed as Attachment 1 to this letter are the Authority's proposed implementation commitments and schedules in response to the requirements of the referenced letter.
The Authority recognizes the importance of efforts to apply knowledge gained from the Three Mile Island accident and proposes an expedited schedule, wherever possible meeting the implementation schedules of Attachment 6 to the referenced letter.
In certain cases, where substantial engineering effort is required, final installation schedules for equipment have not been proposed, but will be as soon as reliable estimates are available.
Very truly yours,
-
..
.(- ,. /
-
,(t._.$.
Paul J. Early Assistant Chief Engineer-Projects g 0
4'0 vt p.
1210 178 %.l N-dy ~ ',
.
-
300RORBE.
ATTACIIMENT I TII"9E MILE ISLAt1D LESSONS LEARt1ED COMMITME!1TS*
.
- When scheduled dates are neither specifically provided herein nor reserved for later identification, the dates identified by IIRC in the September 13, 1979 letter will be met.
.
. \2\D \l9 .
uy w-- 9 9
" '-
' -
F -g
- w W
.
.
ATTACHMENT I THREE MILE ISLAND LESSONS LEARNED C O M M I T M E N T_S_
y 2.1.1 - Emergency Power Supply for Power Operated Relief Valves and Pressurizer Level Indicator.
- As discussed in M2DO-24703, natural circulation in the BWR is strong and inherent in all off-normal modes of operation, independent of any powered system, as long as sufficient inventory is maintained. This is because even in normal operation the BWR is essentially an augmented natural cir-culation machine. Because the BWR operates with both liquid and steam in the reactor pressure vessel, saturation conditions are always maintained irrespective of system pressure. Thus, there is no need for emergency power to maintain natural circulation or to keep the system pressurized.
The power-operated relief valves in BWR's are already powered by emergency power. They have no blocking valves.
The reactor vessel level indication instrument channels for safety system activation and control are already powered b3 emergency power.
For the reasons stated above, the Authority believes no action is necessary in response to recommendation 2.1.1 for the FitzPatrick Plant.
2.1.2 - Relief and Safety Valves Tests The BWR design basis includes no transients or accidents in which two-phase flow or subcooled liquid flow at high pressure is calculated or expected. In determining the need for special testing of BWR safety and relief valves it is essential to consider the service duty to which the primary system re-lief and safety valves of the BWR are exposed, and the consequences of maloperation of these valves. Relief valves are routinely used to mitigate the effects of system transients. A stuck-open valve is not an event of great significance in a BWR: in 300 reactor years of experience, 50 cases have occurred; in 3 such cases, the safety relief valves passed two-phase flow. Tables 1 and 2 summarize the experience to date. This experience, as will be explained, clearly shows that there is no need for an extensive testing program for BWR safety and relief valves.
A) BWR Safety and Relief Valves .
Table 2.1-3 of NEDO-24708 shows the complement of safety and relief valves for all domestic operating BWRs. The FitzPatrick plant has eleven (11) safety / relief valves (S/RV) designed Their discharges to mitigate the effect of system transients.
are piped to the containment suppression pool.
.
)}\0 .
M4 @P W- $ g
'
'N -
.
-2 This heat sink pr vents significant containment heatop.
Compliance of a system transient by a stuck-open valve has essentially no effect on reactor vessel water level measurement or on forced or natural circulation capability.
The flow through the valve is saturated steam. If the valve cannot be closed by operator action the olant can be shut down
,
using normal operating procedures.
.
B) Two-Phase Flow
.
Expected operating conditions and transients do not include two-phase flow through S/RV's. However, in 3 incidents, circumstances combined to cause high pressure water to flow down the steam lines and a steam / water mixture to flow through the valves. A summary of these events is given in Table 2. In these events, Electromatic relief valves and direct acting safety valves were actuated, discharged a steam / water mixture and reclosed, indicating that the flow did not cause a stuck-open valve condition. However, following these events, high water level trips were added to the FiztPatrick plant. Since all the S/RVs are piped to the suppression pool, direct pressurization of the drywell is minimal.
C) Valve Qualification Three-stage Target Rock S/RVs were subjected to restricted flow steam tests to qualify the set-point and valve opening time delay. Soleneid valves (used during power actuation) are qualified by autoclave test for the LOCA environment.
Satisfactory. valve operation is indicated by field service.
D) Field Experience Since 1971 there have been 50 events in BWR plant operation wherein S/RV's have stuck open (Table 1) . In each of these cases the reactor was depressurized, the stuck valve was repaired or replaced, and the plant was placed back into service.
Although a stuck-open S/RV is ordinarily of no safety concern, programs are underway to reduce the frequency of such events.
. From Table 1 it is seen that the total number of S/RV blowdowns has steadily decreased since the mid-70's. The improvement in the number of S/RV blowdowns as a factor of number of S/RV's in service has been even more dramatic. From Table 2 it is seen that experience with 2-stage Target Rock relief valves has been good. At the FitzPatrick plant 9 out of the 11 S/RVs have been modified to the 2-stage type and the remaining 2 will be modified during the 1980 refueling outage. .
E) Summary (1) BWR S/RV's are routinely tested for the only expected mode of operation (saturated steam), both by in-place functional tests and by frequent usage in mitigating plant transients; 1210 181 .
. . _ . . . . . ... _ _ _ . .__ _ _____
(2) There is no design-basis transient or accident which requires S/RV's to pass two-phase or liquid flow at high pressure-(3) Inadvertent passage of two-phase flow is not likely vbere high pressure feedwater and injection
~ system are tripped by high vessel water level.
(4) In the three events wherein BWR S/RV's did pass
,
two-phase flow, the valves reclosed.
(5) The consequences of a stuck-open valve are minimal and reactor shutdown is uncomplicated, as proven by numerous filed occurrences. The procedures for responding to a stuck-open relief valve includes the opening of additional relief valves. This is no concern for core uncovery, and the valve need not pass two-phase flow. Improvement from 3-stage to 2-stage topworks on S/RVs will reduce the frequency of such 3 vents.
2.1.3.a -
Direct Indication of Valve _ Position The Authority's program to implement the captioned NRC position calls for engineering review to be completed by December 1, 1979 and final implementation during the Spring 1980 scheduled refueling outage, dependent upon equipment availability.
2.1.3.b - Instrumentation fer Detection of Inadequate Core Cooling Additional hardware to identify inadequate core cooling on BWRs is not determined to be necessary at this time.
Procedures will identify the diverse methods of determining inadequate core cooling, using existing instrumentation.
The results of analysis being performed, in response to 2.1.9 will be factored into procedures as required, after the analysis is complete.
Because the BWR operates with both liquid and steam An the reactor pressure vessel, saturation conditionsThus are there always maintained irrespective of system pressure.
is no need for a subcooling meter in the BWR.
2.1.4 -
Diverse Containment Isolation A review of the FitzPatrick Plant containment isolation systems by our Architect-Engineer to confirm that the
- existing design meets the captioned NRC position, is scheduled for completion by January 1, 1980.
. 1210 182: .
. -
.
_4 2.1.5.a - Dedicated H, Control Penetrations A review of the Fit: Patrick Plant purge system by our Architect-Engineer to confirm that the existing design meets the captioned NRC position, is scheduled for
"
completion by January 1, 1980.
,
2.1.5.b - Not applicable to the FitzPatrick plant.
2.1.5.c -
Recombiner Procedures It is the position of the Authority that no action is required for this item at this time as the Nuclear Regulatory Commission has so indicated in the September 13, 1979 letter.
2.1.6.a - System Integrity for High Radioactivity The Authority plans to implement measures for leak reduction for systems that could carry radioactive fluid outside of the containment. The Authority will also institute a program to include periodic leak checks on these systems, modifications identified as a result of the leak rede.ction program will be examined and a schedule for implementation will be proposed.
2.1.6.b - Plant Shielding Review The Authority's program to implement the captioned NRC position calls for engineering review to be completed by April 1, 1980. More guidance may be sought regarding development of shielding source terms and allowable com-part. ment radiation levels. Any plant modifications1980, and a indicated by the review will be examined by May 1, schedule for implementation proposed at that time.
2.1.7.a - Auto Initiation of Auxiliary Feed This NRC position does not apply to the Fit: Patrick Plant design.
2.1.7.b - Auxiliary Feed Flow Indication This NRC position does not apply to the Fit: Patrick Plant design.
2.1.8.a - Post Accident Sampling The Authority's program to implement the captioned NRC ,
position calls for engineering review to be completed by April 1, 1980. Any plant modifications indicated will be examined at that time, and a schedule for implementation proposed. Procedures will be developed for post accident samplino after engineerinJ review and implementation of necessary modifications.
12i0 183 2.1.8.b - High Rance Radiation Monitors.
-
Interim procedures will be developed to estimate noble
. - - - -- - .- - - _ __ _ _ _ _ _ ,
.
2-gas and radiciodine concentration,should the existing instrumentation go off scale. Based on availability and current state-of-the-art, high range radiation monitors will be procured and installed in the contain-ment. Additional procedures will be developed based on the new hardware changes.
2.1.8.c - Improved Inplant Iodine Instrumentation
.
No additional hardware is necessary for improved inplant iodine instrumentation, as the existing plant equipment is more than adequate. The Authority will review the existing plant procedures and modify them as necessary to meet the NUREG position.
2.1.9 - Transient and Accident Analysis This item is already covered in the responses being provided to the Commission through the Bulletin and Orders Task Force. Specific requirements are being developed in a continuing series of meetings between the BWR Utility Owners Group and the NRC Bulletin and Task Force. The implementation of special procedures and retraining will be done on a schedule consistent with those established with die Bulletin and Orders Task Force.
Addition Addendum Items to NU"EG L573 Instrumentation to Monitor Contairment Conditions During Course of Accident (Containment Pressure, Water Level, and Hydrogen Monitor)
The Authority's program calls for engineering review of the captioned NRC position to be completed by March 1, 1980.
Any plant modifications deemed necessary wil.1 be evaluated at that time, and a schedule for implementation proposed.
- RCS Venting BWRs like the FitzPatrick Plant are provided with a number of power operated safety grade relief valves which can be used to vent the reactor pressure vessel in addition to the air operated vent valves on the reactor vessel head.
The piping arrangement is such that accumulation of gases above this point in the vessel will not affect natural circulation cooling of the reactor core.
The power operated relief valves satisfy the intent of the NRC position. Information regarding the design, quali-
- fication, power source, etc., of .hese val'res has been provided in the Fit: Patrick Final Safety Analysis Report.
1210 184
.
.
_y_
The Authority's position is that the requirement of single f ai. lure criteria for prevention of inadvertent actuation of these valves is not applicable to BWR's. These valves serve an important function in mitigating the effects of transients and also provides ASME code overpressure protection. Therefore, the addition of a second " block" valve to the vent lines could result in a less safe design and in some cases a
-
" violation of the ASME code requirements. Also, inadvertent opening of relief valve in a BWR is a design basis event and
- is a controllable transient (this is discussed in our position of NUREG-0578, Item 2.1.2).
In addition to the power-operated relief valves, FitzPatrick Plant includes various other means of high-point venting.
Among these are:
- 1) Normally closed reactor vessel head vent valves, operable from the cor trol room which discharge to the drywell equipment drain sump;
- 2) Normally open reactor head vent line, which disenarge to a main steam line;
- 3) Main steam-driven Reactor Core Isolation Cooling (RCIC)
System turbines, operable from the control room, which exhaust to the suppression pool;
'
- 4) Main steam-driven High Pressure Coolant Injection (HPCI) system turbines, operable from the control room, which exhaust to the suppression pool:
Although the power-operated relief valves fully satisfy the intent of the requirement, these other means also provide protection against the accumulation of noncondensibles in the reactor pressure vessel.
Because the relief valves, HPCI, and RCIC will vent the reactor contintously, and because containment hydrogen calculations in normal safety analysis calculations assume continuous venting, no special analyses are required to demonstrate "that the direct venting of noncondensible gases with perhaps high hydrogen concentrations does not result in violation of com-bustible gas concentration limits in containment".
In view of what has been stated above the Authority believes that adequate reactor coolant system venting is provided by the existing plant design.
2.2.1.a - Shift Supervisor Responsibilities
.
The Authority plans to review and update if necessary the administrative and management procedures to emphasize the duties, responsibilities and authority of the Shift Supervisor as delineated in NUREG 0578.
2.2.1.b -
Shift Technical Advisor 1210 185 The Authority plans to hire qualified technical personnel
- .
- **+'**6 "T N W*- M M M _ M M*
'
_,.
to work on each shif t as Surveillance Test Engineer to meet the requirement concerning operating experience assessment.
The Shift Supervisor will be trained and qualified as necessary to satisfy the accident assessment function. However, as it is impossible to hire and /or train these people by January 1, 1980, the Authority plans to utilize plant engineers to be on call at a short time notice- to be available
"
at the plant during emergency. The Authority plans to meet the requirement of this NUREG position by January 1, 1931.
Iloweve r , it is anticipated that fully training the Shitt Supervisors will require continuous action until January 1, 1982.
2.2.1.c -
Shif: c.nC..211ef
"
Tarnover Procedures The Authority plans to review and revise plant procedures as necessary to assure that adequate coverage exists during shift and relief turnover.
2.2.2.a -
Control Rcom Access The Authority plans to review plant procedures and revise them as necessary to assure that access to the control room is limited to those persons necessary for the safe command and control of operations.
2.2.2.b - Oncite Technical Support Center A Onsite Technical Support Center exists for the Fit: Patrick plant in the onsite emergency center. The permanent location for the Technical Support Center with the filtered ventilation system and necessary communication links anc monitoring capability for the critical reactor parameters will be established within the restraint of construction and instrumentation availability.
2.2.2.c - Onsite Operation Support Center The Authority plans to utilize the visitor's 9:11ery and corridor to the control room as an operation suptort center.
Item Covered by Enclosures 7 and 8 to the September 13, 1979 NRC letter Near Term Emergency Preoaredness Improved Implementation
- 1) Upgrade Emergency Plan The Authority has initiated action to upgrade the emergency plan to meet the requirements of RG. 1.101, Revision 1.
- 2) Short Term Actions Recommended by Lessons Learned Task Force .
Items covered under this heading, namely 2.1. 8. a . b, and c are already addressed and as such no action plan is indicated under this heading.
- 3) Emergency Operation Center for Federal, State and Local Officials _
for federal, state The temporary emergency operating center The and local officials exists for the Fit: Patrick Plant. .
- . . .- -
1210 186 . - ,
. . - - _ - _
_g_
Authority plans to review and take necessary steps to meet the long term requirement.
- 4) Improved Off Site Monitoring Capability
"
It is the Authority's position that the Fit: Patrick Plant is already in compliance as large numbers of TLD's have been
. distributed throughout the surrounding area of the plant site to monitor off site radiation exposure to the public.
- 5) Adequacy of State / Local Plans The Authority has reviewed the adequacy of the state plan and has suggested action in upgrading the local plans. New York State has an NRC approved emergency plan for dealing with radiological emergencies in nuclear power plants.
- 6) Conduct of Test Exercises It is the position of the Authority that the plant continue the present emergency plan testing as specified in the technical specifications and any augumentation that will be necessary will be implemented within the 5 year time schedule.
.
1210 187
.
O # OMMM E % MW 9 ' J
e
'
.
TABLE 1 S/RV BLOWDOWilS IN BWR OPERATION 2 STAGE CROSBY-0KANO-DIKKERS ,hgg3 3-STAGE TARGET ROCK TARGE1 Rock TOTAL TOTAL DIVIDED
- OF S/RV S/RVs BY TOTAL
- OF # OF STUCK OPEN VALVES IN DLOW- IN VALVES IN TOTAL VALVES Ih TOTAL TOTAL FOLLOWING VALVES IN SERVICE SERVICE BLOWDOWNS DEMAND SERVICE BLOWDOWNS SERVICE BLOWDOWNS SERVICE DOWNS YEAR 2 4 0.5 2 2 14 1971 1 23 0.04 1 23 1972 1 1 56 0.02 1 56 1973 1 10 108 0.09 10 1 108 1974 7 127 0.06 7 0 127 1975 11 149 0.07 11 1 149 1976 9 157 0.05 9 4 157 1977 0 35 5 203 0.02 3 157 0 11 1978 5 36 0 52 4 220 0.02 4 1 132 0.
1979 to Sept.
NOTE:
The above table does not include Dresser Safety Valves (unpiped til:cnarge)
N See Table 2 for infonnation on this equipment.
- or "Electromatic" relief valves.
cp
-
CO
TABLE 2 BWR EVENTS IN WHICH 1UO-PHASE FLOW OR L10VIL PASSED THROUGH SAFETY /RELIET VALVES
~
. DRESDEN 2 - JUNE 5,1970 During the course of the initial test program on Dresden 2 with the unit operating at 75% power, a spurious signal in the reactor pressure control system occurred.
This spurious signal resulted in sumultaneous opening of the control and the turbine bypass valves with resultant turbine trip, reactor scram, and main steamline isolation.
In response to the initial and expected water level drop, the operator switched to manual control of the feedwater systen and began filling the reactor vessel at the maximum rate. Water level misinterpretation led to reactor water over-flowing into the main steam lines. A pressure surge resulted in the main steam lines when relief valves were cycled. This momentarily opened one of the safety valves, resulting in a discharge directly to the containment (unpiped discharge).
The fluid impinged upon the lifting levers of two other safety valves causing these safety valves to cock slightly open. The water-steam mixture from the two safety valves pressurized the primary containment. As a result, the containment was pressurized to an estimated 20 psig and an estimated temperature of approxi-mately 300 F. Damage within the drywell was generally limited to over-heating of most of the flu'x monitoring instrumentation cables and water impingement on insu-lation. At no time during the event was there difficulty maintaining adequate water supply to the reactor core, and there was no question of adequate core cooling.
DRESDEN 2 - DECEMBER 8,1971 Unit 3 was operating about 98% power on December 8,1971, when the plant was shut down due to a reactor low water level scram. The scram resul ted from a .
condensate / condensate booster pump trip and the subsequent trip of two reactor feed pumps on low suction pressure. Following the scram, the standby feed pump Due to a pressure started. The vessel was overfilled and the steam lines flooded.
surge in the main steam lines, a safety valve lifted causing discharge directly to the containment (unpiped discharge) . Pressurization of the containment
.
1210 189
TABLE 2 (cont'd)
,~ continued as high as 20 psig. Inspections showed that the high humidity and temperature in the drywell following the release to the containment danaged
- LORM cables, which required replacement. Other results of the discharge from the safety valve included damage to an electronatic relief valve con-troller, damage to insulation near the safety valve, r ; red paint on the drywell walls, and a damaged ventilation duct. There was never any concern for maintaining adegaate water supply to the reactor core, and there was no question of adequate core cooling.
KRB (GERMANY) - JANUARY 13, 1977 The unit was operating at 100% power when a bus on two of its 200 KV lines opened. The plant was scramed and isolated. l'.anual fee &ater control was initiated which resulted in flooding of the steam lines. Safety valves opened and discharged water, steam and two-phase media. The valves discharged directly to the containment (unpiped discharge). The safety valves opened and reclosed several times. Because of the unique piping arrangement (which is not present in any US-BWR), reaction forces of the discharging valves caused or contributed to a pipe rupture in two of the fourteen flanged nozzles by which the valves are connected to a U-shaped header. At no time during the event was there concern for maintaining adequate water supply to the reactor core, and there was no questic, of adequate core cooling.
.
1210 190
- .
-- .--
. - - . . .~ . - . . - . - _ _
_ _ _ _