MONTHYEARML24183A2292024-07-0101 July 2024 Summary of Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 ML24103A1872024-04-16016 April 2024 Summary of Meeting with Indiana Michigan Power Co., Regarding Surveillance Capsule Program for DC Cook Nuclear Plant, Unit 2 ML24031A5872024-02-0202 February 2024 Summary of Meeting with Indiana Michigan Power Company Regarding Neutron Flux Instrumentation for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML23215A1662023-08-17017 August 2023 Summary of July 31, 2023, Meeting with Indiana Michigan Power Company Regarding Operating Power Sources for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML23199A2402023-07-19019 July 2023 Summary of the July 13, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 ML22355A6022023-01-0303 January 2023 Summary of December 14, 2022, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML22318A1992022-11-21021 November 2022 Summary of November 7, 2022, Meeting with Indiana Michigan Power Company Regarding Neutron Flux Instrumentation for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML22154A5342022-06-0909 June 2022 Summary of the June 1, 2022, Public Outreach to Discuss the NRC 2021 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant ML22011A2732022-01-13013 January 2022 Summary of Meeting with Indiana Michigan Power Company to Discuss Planned Final Response to Generic Letter 2004-02 for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21349B3092022-01-0303 January 2022 Summary of Meeting with Indiana Michigan Power Company to Discuss Potential Changes to the Quality Assurance Program for Donald C. Cook Nuclear Plant, Units 1 and 2 ML21202A1072021-07-23023 July 2021 Summary of July 20, 2021, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21196A5182021-07-15015 July 2021 July 8, 2021, Summary of Public Webinar to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of the Donald C. Cook Nuclear Plant ML21082A0052021-03-24024 March 2021 Summary of March 19, 2021, with Indiana Michigan Power Company Regarding Containment Water Level Channels for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20349A0152020-12-17017 December 2020 Summary of November 30, 2020, Teleconference with Indiana Michigan Power Company Regarding a Planned License Amendment Request to Extend the Containment Integrated Leak Rate Testing Interval for Donald C. Cook Nuclear Plant, Unit No. 2 ML20282A2712020-10-14014 October 2020 Summary of October 2, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML20248H4752020-09-10010 September 2020 Summary of August 6, 2020, Teleconference with Indian Michigan Power Company Related to Steam Generator Eddy Current Testing License Amendment Request ML20209A6032020-07-27027 July 2020 Summary of the July 21, 2020, Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of the Donald C. Cook Nuclear Plant, Units 1 and 2 ML20133K1282020-05-21021 May 2020 Summary of May 4, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20121A0692020-05-0404 May 2020 Summary of Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20041C9492020-02-13013 February 2020 Summary of February 6, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19350A0552019-12-30030 December 2019 Summary of 12/12/2019 Meeting with Indiana Michigan Power Company, License Amendment Request for D.C. Cook Nuclear Plant, Units 1 and 2 to Delete Surveillance Requirement Related to Diesel Generator Load Test Resistor Banks ML19212A5652019-07-30030 July 2019 Summary of Public Open House to Discuss NRC Activities and the 2018 End-Of-Cycle Performance Assessment of Donald C. Cook Nuclear Generating Plant, Units 1 and 2 ML19141A0622019-06-0606 June 2019 Summary of November 19, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19099A3262019-04-16016 April 2019 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19067A0482019-03-12012 March 2019 Summary of Public Teleconference with Indiana Michigan Power Co. (I&M) Review of LAR for Approval of Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping (EPID-2019-LLA-0054) ML18334A0402018-12-13013 December 2018 Summary of Meeting with Indian Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML18109A0692018-04-26026 April 2018 Summary of April 10, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML18052B0542018-02-26026 February 2018 Summary of February 15, 2018, Meeting with Indian Michigan Power Company Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 (EPID L-2018-LRM-0008 ML18018B1382018-01-22022 January 2018 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML17265A4922017-10-0404 October 2017 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 2 ML17235B1232017-08-23023 August 2017 Summary of the July 27, 2017, Open House to Discuss the 2016 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant ML17082A0762017-03-27027 March 2017 Summary of March 20, 2017, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML16308A1132016-11-16016 November 2016 Summary of October 27, 2016, Public Meeting with Indiana Michigan Power Company Regarding the Donald C. Cook Nuclear Plant, Units 1 and 2 ML16244A7062016-08-30030 August 2016 Summary of the August 22, 2016, Donald C. Cook Public Meeting ML16193A5912016-07-15015 July 2016 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML15271A0462015-10-0505 October 2015 Summary of Public Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML15237A3362015-09-0202 September 2015 Summary of August 24, 2015, Telephone Call to Provide Verbal Authorization of Relief Request ISIR-4-06, Alternate Repair of Socket Weld ML15107A0982015-04-24024 April 2015 April 14, 2015, Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML14311A3182014-11-14014 November 2014 Summary of Conference Call with Donald C. Cook Nuclear Plant, Unit 1 Regarding the Fall 2014 Steam Generator Inspections ML14231A0752014-08-27027 August 2014 Summary of the August 8, 2014, Pre-Application Meeting with American Electric Power Company to Discuss a Future License Amendment Request for Alternative Source Term and TSTF-490 ML14209A9422014-07-30030 July 2014 July 9, 2014, Summary of Category 1, Public Meeting with Indiana Michigan Power Company to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2.1 ML14199A0802014-07-18018 July 2014 Summary of July 8, 2014 Donald C. Cook Public Annual Assessment Meeting ML14023A3872014-01-30030 January 2014 Summary of Joint Steering Committee Meeting to Discuss Activities Related to Lessons-Learned from the Fukushima Dai-Ichi Nuclear Power Plant Event ML13210A2272013-08-0202 August 2013 6/26/13, Summary of Pre-Application Meeting to Discuss Pending License Amendment Request to Modify the CNP Unit 1 Normal Operating Pressure and Temperature ML13189A2322013-07-15015 July 2013 Summary of Conference Telephone Call Regarding the 2013 Steam Generator Tube Inspections ML13154A4062013-06-0303 June 2013 5/30/2013 - Summary of the D.C. Cook Public Meeting ML12159A4022012-06-0707 June 2012 May 31, 2012 Summary of Public Meeting to Discuss the 2011 Annual Assessment Results for D.C. Cook ML1133307782011-11-29029 November 2011 Record of Discussion by Phone on 10/5/11 Regarding Steam Generator Inspection ML11129A2422011-06-0808 June 2011 Summary of Meeting with Indiana Michigan Power Company to Discuss Issues Related to a Future Submittal Using NFPA 805 ML0931305572009-11-0909 November 2009 Summary of Public Meeting with Staff from the D.C. Cook Nuclear Power Plant Regarding the September 2008 Unit 1 Turbine Vibration Event 2024-07-01
[Table view] |
Text
~p,.R REG(/( .::,c," .,.0 'SI !§ ~) = UNITED STATES " . '* : NUCLEAR REGULATORY COMMISSION
- WASHINGTON, D.C. 20555-0001 +O *** ... April 26, 2018 LICENSEE
Indiana Michigan Power Company, LLC FACILITY:
Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2
SUBJECT:
SUMMARY
OF APRIL 10, 2018, MEETING WITH INDIANA MICHIGAN POWER COMPANY REGARDING DONALD C. COOK NUCLEAR PLANT, UNIT NOS. 1 AND2 On April 10, 2018, a Category I public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Indiana Michigan Power Company (l&M, the licensee) via teleconference.
This meeting was open to members of the public. No regulatory decisions were made at this meeting. The purpose of the meeting was to discuss the decommissioning trust funds for Donald C. Cook Nuclear Plant (CNP), Unit Nos. 1 and 2. The licensee submitted its Decommissioning Funding Status Report to the NRC via letter dated March 21, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17081A443).
The meeting notice and agenda, dated March 26, 2018, are available in ADAMS at Accession No. ML18085A008.
A list of attendees is included as Enclosure 1 to this memorandum.
The NRC staff began the teleconference by providing background information and discussing the reason for the meeting. The NRC staff stated that in l&M's 2017 submittal of the CNP Decommissioning Funding Status Reports, required by Title 10 of the Code of Federal Regulations ( 1 O CFR) Section 50. 75(f)( 1 ), l&M reported the amount of funds allocated for radiological decommissioning for items included in 10 CFR, Sections 50.75(b) and 50.75(c), to be $877,702,748, collectively, for both CNP Unit 1 and Unit 2. During the NRC staff review of this submittal, the staff observed that the amount of funds that had been reported by l&M in 2015 as allocated for radiological decommissioning was $1,027,257,392, collectively, for both CNP Unit 1 and Unit 2. The NRC staff calculated that the amount allocated for radiological decommissioning had decreased by $149,554,644, collectively, for both CNP Unit 1 and Unit 2, or $78,470,927 and $71,083,717 for CNP, Units 1 and 2, respectively, from 2015 to 2017. Thus, the public teleconference was requested in order for the NRC staff to obtain clarification from the licensee regarding the reason for the decrease in funds. The NRC staff asked the licensee whether there had been a withdrawal of funds from the decommissioning trust fund, and if not, to explain the decrease in funds allocated for radiological decommissioning.
In response to the staff's question, the licensee affirmed that there had been no withdrawals.
The licensee stated that the total value of the account had increased, in alignment with overall market conditions, but that the amount specifically allocated toward radiological decommissioning had decreased.
The licensee explained that the decrease was due to a 2017 site-specific cost study at CNP, which determined that additional funding would be required in the future for spent fuel management.
Therefore, the licensee had reallocated a percentage of the funds in the trust account, previously allocated for radiological decommissioning, to be used for future maintenance of CNP's independent spent fuel storage installation (ISFSI), pursuant to 10 CFR 50.54(bb).
The licensee stated that in crafting its biennial submittal to the NRC, it had followed the guidance provided in Regulatory Issue Summary (RIS) 2001-07, Revision 1, "10 CFR 50.75 Reporting and Recordkeeping for Decommissioning Planning," dated January 8, 2009 (ADAMS Accession No. ML083440158).
RIS 2001-07, Revision 1, discusses "the need to preserve the distinction between funds accumulated for radiological decommissioning which licensees are required to report, and funds accumulated for other purposes." The NRC staff stated that funds that have previously been reported as dedicated for radiological decommissioning cannot be repurposed.
Thus, the amount of funds reported biennially is generally expected to increase over time unless adversely affected by market conditions.
The NRC staff referenced 10 CFR 50. 75(h)(2), which states, "Disbursements or payments from the trust, escrow account, Government fund, or other account used to segregate and manage the funds, [ ... ]are restricted to decommissioning expenses." In response to this statement, the licensee declared that it had not made a disbursement from the account, only reallocated the funds in the account for future ISFSI (spent fuel management) expenses.
The NRC staff concluded the meeting by informing the licensee that if additional written explanation were required, the licensee would be informed by future correspondence. Members of the public were not in attendance.
Public Meeting Feedback forms were not received.
Please direct any inquiries to me at 301-415-3826, or Allison.Dietrich@nrc.gov.
Docket Nos. 50-315 and 50-316
Enclosure:
- 1. List of Attendees Cc: Listserv f/AI tit Allison W. Dietrich, Project Manager Plant Licensing Branch Ill Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LIST OF ATTENDEES APRIL 10, 2018, PUBLIC MEETING WITH l&M, LLC DONALD C. COOK NUCLEAR PLANT, UNIT NOS. 1 AND 2 DECOMMISSIONING FUNDING STATUS REPORT Name Organization Allison Dietrich NRC Richard Turtil NRC Anita Ghosh NRC Kosmas Lois NRC Jennivine Rankin NRC Anthony Bowers NRC Helen Levendosky*
l&M Ginger Hartman* l&M Bud Haemer* l&M Randy Arnold* l&M Daniel Hunt* l&M Laura Fletcher*
l&M *Participated by telephone Enclosure
SUBJECT:
SUMMARY
OF APRIL 10, 2018, MEETING WITH INDIANA MICHIGAN POWER COMPANY REGARDING DONALD C. COOK NUCLEAR PLANT, UNIT NOS. 1 AND 2 DATED APRIL 26, 2018 DISTRIBUTION PUBLIC LPL3 Reading RidsAcrs_MailCTR Resource RidsNrrDorllpl3 Resource RidsOpaMail Resource PMNS Resource RidsNrrLASRohrer Resource RidsRgn3MailCenter Resource RidsNrrPmDCCook Resource RidsNrrDorl Resource RidsNrrDlpPfpb Resource RidsOgcGchea Resource ADAMS Accession No: ML18109A069 OFFICE DORL/LPL3-1
/PM DORL/LPL3-1/LA DLP/PFPB/BC DORL/LPL3-1
/BC NAME ADietrich SRohrer ABowers DWrona DATE 4/23/18 4/23/18 4/23/18 4/26/18 OFFICIAL RECORD COPY DORL/LPL3-1
/PM ADietrich 4/26/18