Letter Sequence Acceptance Review |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
Results
Other: ML18254A097, ML18254A131, ML18282A035, ML18323A059, ML18323A661, ML18323A690, ML19095A457, ML19095A458, ML19095A461, ML19095A463, ML19095B359, ML19116A066, ML19120A239, ML19154A058, ML19164A156, ML19164A157, ML19170A275, ML19176A276
|
MONTHYEARML19095A4612009-04-0808 April 2009 License Transfer Conforming Amendment Project stage: Other RA-18-034, Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv)2018-03-22022 March 2018 Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) Project stage: Request RA-18-053, Update to Spent Fuel Management Plan2018-05-21021 May 2018 Update to Spent Fuel Management Plan Project stage: Request RA-18-087, Response to Request for Additional Information (RAI) Related to Post-Shutdown Decommissioning Activities Report2018-09-24024 September 2018 Response to Request for Additional Information (RAI) Related to Post-Shutdown Decommissioning Activities Report Project stage: Response to RAI RA-18-083, Certification of Permanent Removal of Fuel from the Reactor Vessel for Oyster Creek Nuclear Generating Station2018-09-25025 September 2018 Certification of Permanent Removal of Fuel from the Reactor Vessel for Oyster Creek Nuclear Generating Station Project stage: Request ML18275A1162018-09-28028 September 2018 Notification of Revised Post-Shutdown Decommissioning Activities Report and Revised Site-Specific Decommissioning Cost Estimate for Oyster Creek Nuclear Generating Station Project stage: Request ML18253A2212018-10-0404 October 2018 Request for Withholding Information from Public Disclosure - 8/31/18 Affidavit Executed by Andrew Ryan, Holtec International, Related to Proprietary Enclosure 2A to the License Transfer Application Project stage: Withholding Request Acceptance ML18254A0972018-10-16016 October 2018 Letter, Notice of Application for Order Approving Direct Transfer of License and Conforming Amendment to Oyster Creek Environmental Protection LLC and Holtec Decommissioning International LLC Project stage: Other ML18254A1312018-10-16016 October 2018 FRN, Notice of Application for Order Approving Direct Transfer of License and Conforming Amendment to Oyster Creek Environmental Protection LLC and Holtec Decommissioning International LLC Project stage: Other ML18302A2232018-10-29029 October 2018 Comment (1) of Brain Kube on Oyster Creek Nuclear Generating Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML18306A8662018-11-0101 November 2018 Sierra Club New Jersey Chapter Comments and Request for Public Hearing Project stage: Request ML18282A0352018-11-0909 November 2018 Application for Order Approving Direct Transfer of Renewed Facility License and Conforming License Amendment to Oyster Creek Environmental Protection, LLC and Holtec Decommissioning International, LLC Project stage: Other ML18323A5612018-11-16016 November 2018 Letter from Senator Cory Booker Requesting for Extension of Comment Period Project stage: Request ML18324A7762018-11-18018 November 2018 Comment (2) of Alfred Decker on Oyster Creek Nuclear Generating Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML18323A0592018-11-26026 November 2018 Correction Letter - Application for Approval of Transfer of License and Conforming Amendment Project stage: Other ML18334A2152018-11-30030 November 2018 Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) Project stage: Request ML18323A6612018-12-0404 December 2018 Federal Register Notice to Reopen the Comment Period - Notice of Application for Order Approving Direct Transfer of Renewed Facility License and Conforming License Amendment Project stage: Other ML18323A6902018-12-0404 December 2018 Letter, Reopen the Comment Period - Notice of Consideration of Approval of Transfer of Renewed Facility Operating License and Conforming Amendment, and Opportunity for a Hearing Project stage: Other ML18362A0952018-12-23023 December 2018 Comment of Gary Defranco of Trans Tech Industries on Oyster Creek Nuclear Generating Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19003A2422018-12-28028 December 2018 Comment of Donald Weigl on Oyster Creek Nuclear Generating Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19004A0752019-01-0303 January 2019 Comment of Janet Tauro on Oyster Creek Nuclear Generating Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19010A3082019-01-0909 January 2019 Comment from Amy Goldsmith on Behalf of Clean Water Action on Oyster Creek Nuclear Generating Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19108A0122019-04-17017 April 2019 Notification of Change in Review Schedule - Oyster Creek License Transfer Application (L-2018-LLM-0002) Project stage: Acceptance Review ML19108A0132019-04-17017 April 2019 Notification of Change in Review Schedule - Oyster Creek License Transfer Application (L-2018-LLM-0002) Project stage: Acceptance Review ML19116A0662019-04-26026 April 2019 April 26, 2019 Notification_ Change in Review Schedule - Oyster Creek License Transfer Application (L-2018-LLM-0002) Project stage: Other ML19120A2392019-04-30030 April 2019 Clarification: Number of Hearing Requests-Oyster Creek License Transfer Application L-2018-LLM-0002 Project stage: Other ML19136A0562019-05-16016 May 2019 Draft Conforming Amendment Review - Cover Pages Appendix a and B- Oyster Creek License Transfer Application L-2018-LLM-0002 - Attachment to Email Project stage: Draft Other ML19136A0552019-05-16016 May 2019 Draft Conforming Amendment Review - Cover Pages Appendix a and B- Oyster Creek License Transfer Application L-2018-LLM-0002 - Email to Exelon Project stage: Draft Other ML19154A0582019-05-31031 May 2019 E-mail Response from State of New Jersey Dated May 31, 2019, Notification-and-Request-Oyster Creek License Transfer Application L-2018-LLM-0002 Project stage: Other NRC-2018-0237, Comment from Paul Dressler of the Concerned Citizens for Lacey Coalition, Regarding the Oyster Creek Nuclear Plant License Transfer Application2019-06-0707 June 2019 Comment from Paul Dressler of the Concerned Citizens for Lacey Coalition, Regarding the Oyster Creek Nuclear Plant License Transfer Application Project stage: Request ML19109A1972019-06-0707 June 2019 Notice of Significant Licensing Action - Proposed Issuance of an Order Approving a License Transfer Application for Which a Hearing Has Been Requested Project stage: Approval ML19095B3592019-06-11011 June 2019 Letter to Exelon Oyster Creek Exemption to Use Decommissioning Trust Fund for Spent Fuel Mgmt Fonsi Letter Project stage: Other ML19129A3192019-06-12012 June 2019 Exemption to Onsite Property Damage Insurance (10 CFR 50.54(w)(1)) Project stage: Request ML19129A3632019-06-12012 June 2019 Exemption to Offsite Property Damage Insurance (10 CFR 140.11 (a)(4)) Project stage: Request ML19169A1062019-06-18018 June 2019 Commission Memorandum and Order (CLI-19-06) Project stage: Request ML19170A2752019-06-20020 June 2019 Hdi Exemption to Use Decommissioning Trust Fund for Spent Fuel Management and Site Restoration Project stage: Other ML19095A4572019-06-20020 June 2019 License Transfer SER Project stage: Other ML19095A4632019-06-20020 June 2019 License Transfer Letter- to Exelon Project stage: Other ML19113A2042019-06-20020 June 2019 Issuance of Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv)(L-2018-LLM-0002) Project stage: Approval ML19095A4582019-06-20020 June 2019 Order License Transfer Project stage: Other ML19176A2762019-06-25025 June 2019 Notification of Expected Date of Transfer of Ownership of Nuclear Unit to Oyster Creek Environmental Protection, LLC; Notification of Satisfactory Documentary Evidence of Insurance; and Notification of Receipt of All Required Regulatory App Project stage: Other ML19164A1572019-07-0101 July 2019 Conforming Amendment Cover Letter Project stage: Other ML19164A1562019-07-0101 July 2019 Conforming Amendment No. 297 to License DPR-16 Project stage: Other ML19164A1552019-07-0101 July 2019 License Transfer Conforming Amendment Project stage: Request 2018-09-24
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML22335A2802022-11-0404 November 2022 11-4-2022 Email Transmitting Draft Questions Pertaining to Pilgrim ISFSI Exemption Request ML22270A0422022-09-26026 September 2022 Acknowledgement Email for Holtecs Request for Reporting Exemption with Regards to the Pilgrim ISFSI Annual Radioactive Effluent Release Report (Docket No. 05000293) ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22007A2602021-12-0606 December 2021 E-mail from P. Obrien, Holtec, to A. Snyder, NRC, on Pilgrim Effluent Discharge ML21287A6192021-10-14014 October 2021 E-mail from S. Phillips, MEMA, to A. Snyder, NRC, Pilgrim Nuclear Power Station, Commonwealth of Massachusetts Consultation Response to Amendment Review for Emergency Preparedness ML21266A2512021-09-23023 September 2021 Consultation with Commonwealth of Massachusetts Regarding Proposed Amendment Application for Emergency Plan and Emergency Action Levels ML21266A2772021-09-23023 September 2021 HDI Clarification of Exemption Requested from 10 CFR 20, Appendix G, Section Iii.E ML21267A0012021-09-23023 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E Acceptance Review ML21257A3832021-09-15015 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Follow-on Request Re Request for Additional Information 2 Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Pl ML21211A5912021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21211A5162021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Physical Security Plan ML21200A2352021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21200A1522021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim Isfi Only Physical Security Plan ML21176A1842021-06-25025 June 2021 Email from HDI Regarding Pilgrim Nuclear Power Station Training ML21180A0582021-06-17017 June 2021 Email from Region I Regarding Pilgrim Nuclear Power Station Inspection - EA-13-132 ML21097A0402021-04-0606 April 2021 E-Mail Consult with Commonwealth of Mass Re - Amendment Application - Physical Security Plan for the Pilgrim Nuclear Power Station L-20-092, Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B,2020-12-10010 December 2020 Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B, L-20-096, Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 20102020-12-10010 December 2020 Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 2010 ML20328A2982020-11-16016 November 2020 Response from Commonwealth of Massachusetts on No Significant Hazard for Pilgrim ISFSI Amendment to Address ISFSI II Dated November 16, 2020 ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20266G4032020-09-22022 September 2020 Acceptance Review Email - Request for Approval of HDI Fleet Decommissioning Quality Assurance Program, Revision 0 ML20163A6802020-06-11011 June 2020 Confirmation of the Scope of the Requested Regulatory Relief for Pilgrim Security Qualifications ML20280A1912020-04-17017 April 2020 Request for Additional Information- Clarifying Information for Pilgrim ISFSI Physical Security Amendment Application ML20269A3542020-03-0505 March 2020 CFR 26.717 Reports 2019 Transmittal Email ML19336A0302019-11-27027 November 2019 OEDO-15-00479 - Re 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding ML19336A0332019-11-26026 November 2019 OEDO-15-00479 - E-mail to Petitioner - 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding (CAC No. MF6460; EPID L-2015-CRS-0002)- Issuance of Final Director'S Decision ML19331A1952019-11-21021 November 2019 NRR E-mail Capture - (External_Sender) Pilgrim Nuclear Power Station - Commonwealth Consultation Response - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1732019-11-12012 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Cyber Security Plan ML19331A1642019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1792019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Emergency Planning Exemption CY-19-007, LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station2019-11-0404 November 2019 LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station ML19275H1962019-09-24024 September 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Consult with Commonwealth - Amendment Regarding Permanently Defueled Technical Specifications (PDTS) ML19239A0372019-08-26026 August 2019 E-mail from Entergy Dated August 26, 2019, Notification of Pilgrim License Transfer ML19239A0262019-08-23023 August 2019 LTR-19-0330 Janet Azarovitz, E-mail a Plea for More Time and Reasonable Discussion Including the Citizens of the Commonwealth in the Sale of the Pilgrim Nuclear Power Station ML19234A2072019-08-20020 August 2019 LTR-19-0328 Lawrence Delafield, President, Six Ponds Improv Assoc., Plymouth, Ma, Ltr Requests NRC to Postpone Consideration of Transferring the Licenses for the Pilgrim Nuclear Power Until the NRC Has Answered Concerns by Pilgrim Watch, Se ML19232A4032019-08-20020 August 2019 LTR-19-0322 Diane Turco, Director, Cape Downwinders, Massachusetts, Letter/E-mail Requests Suspension of the Pilgrim License Transfer from Entergy to Holtec Until the Adjudicatory Hearing Is Held and Raised Contentions Are Resolved ML19308A9942019-08-19019 August 2019 Entergy Nuclear Operations, Inc. Confirmatory Order Rescission Supplemental Information ML19226A3912019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Decommissioning Trust Fund Exemption (Holtec) ML19226A3962019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Conforming Amendment in Support of Pilgrim License Transfer Application ML19226A1212019-08-13013 August 2019 OEDO-15-00479-2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Status (CAC No. MF6460; EPID L-2015-CRS-0002) ML19227A1032019-08-0707 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Draft Wording for Potential Condition of License Transfer Order ML19207B3662019-07-26026 July 2019 NRR E-mail Capture - Pilgrim - RAI Direct and Indirect Transfer of Lic.; Conforming Lic. Amend.; Req. for Exemption 10 CFR 50.82(A)(8)(I)(A) for Holtec Decom. International, Llc ML19176A3452019-06-25025 June 2019 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Information (OEDO-15-00479) (CAC No. MF6460; EPID L-2015-CRS-0002) ML19154A0652019-06-0303 June 2019 NRR E-mail Capture - Pilgrim - Permanent Cessation of Power Operations ML19154A5242019-06-0303 June 2019 NRR E-mail Capture - RAI - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML19161A2122019-05-20020 May 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of License Amendment Request to Remove Cyber Security Plan Requirements ML19123A0332019-05-0101 May 2019 NRR E-mail Capture - Logbook Entry: 05/01/2019 Endangered Species Report Regarding a Confirmed Sighting of North Atlantic Right Whale(S) (Balaena Glacialis) ML19122A4912019-04-29029 April 2019 NRR E-mail Capture - Logbook Entry: 04/29/2019 Regarding the Confirmed Sighting of Ten North Atlantic Right Whales (Balaena Glacialis) ML19108A2372019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 50.54(w)(1) - On-Site Property Damage Insurance ML19108A2362019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 140.11(a)(4) - Primary and Secondary Liability Insurance 2022-09-26
[Table view] |
Text
From: Snyder, Amy To: Helker, David P:(GenCo-Nuc)
Cc: Richard.Gropp@exeloncorp.com
- Frederick.Bonnett@exeloncorp.com
- Jeffrey.Dostal@exeloncorp.com
- P.Cowan@holtec.com
- sterdis@cdi-decom.com
- Cruz Perez, Zahira
- Lamb, John
- Watson, Bruce
- Pham, Bo;Bowers, Anthony
- Conway, Kimberly
- Carter, Ted
- Turtil, Richard
Subject:
NOTIFICATION OF CHANGE IN REVIEW SCHEDULE - Oyster Creek License Transfer Application (L-2018-LLM-0002)Date: Wednesday, April 17, 2019 4:37:00 PM Mr. Helker:
By letter dated August 31, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18243A489), Exelon Generation Company, LLC (Exelon), Oyster Creek Environmental Protection, LLC (OCEP) and Holtec Decommissioning International, LLC (HDI) (the Applicants) submitted an Application for Order Approving Direct Transfer of Renewed Facility Operating License and General License and Proposed Conforming License Amendment for Oyster Creek Nuclear Generating Station (Oyster Creek) and the Oyster Creek Independent Spent Fuel Storage Installation.
On September 27, 2018 (ADAMS Accession No. ML18270A021), you were provided the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this license transfer application and conforming amendment requests.
In this correspondence, you were informed that the "NRC metric is to complete 90-percent of all operating reactor licensing actions within 1 year and 100-percent of all operating reactor licensing actions within 2 years"; the NRC acknowledged that the "... Applicants have requested that the NRC complete this proposed license transfer application by May 1, 2019"; and that the "NRC staff will endeavor to complete this review on the Applicants' requested schedule."
Also, in the September 27, 2018 correspondence, NRC informed Exelon that "[i]f there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager."
The NRC believes that we have met this commitment to communicate with Exelon per the interactions on March 19, 2019 at the monthly project status call in which it was communicated that the financial safety evaluation input was delayed and that the review schedule may be impacted, as well as other numerous subsequent emails and NRC project manager conversations with you from March 12 through April 16, 2019 regarding the risk to the review schedule due to the delay in the safety evaluation input from the NRC's financial review branch and the possible delays due to the fact there are three hearing requests that are still in the process of being dispositioned.
As communicated separately to you and later to Exelon senior management on the monthly status call yesterday, April 16, 2019, the revised schedule for completion of this review is August 15, 2019.
The schedule change is based on the NRC staff's reevaluation of the schedule due to this delay and the schedule could change due to hearing-related activities.
In accordance with 10 CFR 2.390 of the NRC's "Agency Rules of Practice and Procedure,"
a copy of this email will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.
If you have any questions, please contact me at (301) 415-6822.
Sincerely, A Amy Amy Snyder, Senior Project Manager Reactor Decommissioning Branch (RDB)
Division of Decommissioning, Uranium Recovery, and Waste Programs (DUWP)
Office of Nuclear Material Safety and Safeguards (NMSS)
U.S. Nuclear Regulatory Commission (NRC)
Washington, D.C.
20555 Office: (301) 415-6822 Fax: (301) 415-5369 Mail Stop: T5-A10 Location: T5-D48 E-mail: amy.snyder@nrc.gov