MONTHYEARML23342A1162024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML22347A2732022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML21012A4282021-01-13013 January 2021 Security Inspection Plan ML20017A2412020-01-15015 January 2020 Security Inspection Plan for Oyster Creek Generating Station - 2020 IR 05000219/20170062018-02-28028 February 2018 Annual Assessment Letter for Oyster Creek Nuclear Generating Station (Reports 05000219/2017006 05000219/2017402 and 05000219/2017501) IR 05000219/20170052017-08-28028 August 2017 Updated Inspection Plan Report 05000219 2017005 with Report 22 IR 05000219/20160062017-03-0101 March 2017 Annual Assessment Letter for Oyster Creek Nuclear Generating Station (Report 05000219/2016006) with Report 22 ML16235A0792016-08-31031 August 2016 Mid Cycle Assessment Letter 2016-005 IR 05000219/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Oyster Creek Nuclear Generating Station (Inspection Report 05000219/2015006) IR 05000219/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Oyster Creek Nuclear Generating Station (Report 05000219/2015005) ML15239A4742015-08-28028 August 2015 54(p) Eval IR 05000219/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Oyster Creek Nuclear Generating Station (Report 05000219/2014001) IR 05000219/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000219-14-006 IR 05000219/20130012014-03-0404 March 2014 ROP-14 2013 Oyster Creek Nuclear Generating Station Annual Assessment Letter, Report 05000219-13-001, and Inspection Plan IR 05000219/20120012013-03-0404 March 2013 Annual Assessment Letter for Oyster Creek Nuclear Generating Station (Report 05000219/2012001) IR 05000219/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Oyster Creek Nuclear Generating Station (Report 05000219/2012006) IR 05000219/20110012012-03-0505 March 2012 Annual Assessment Letter for Oyster Creek Generating Station (Report 05000219/2011001) ML1124401172011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Oyster Creek Nuclear Generating Station IR 05000219/20100012011-03-0404 March 2011 Annual Assessment Letter for Oyster Creek Generating Station, EOC-11 (Report 05000219/2010001) ML1024406162010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Oyster Creek ML1006212562010-03-0303 March 2010 Annual Performance Review and Inspection Plan - Oyster Creek 2009 EOC Letter and Report 22 (5000219-10-001) ML0914703562009-05-0606 May 2009 License Renewal Outage Commitments Inspection Plan 2 ML0914703552009-05-0606 May 2009 License Renewal Outage Commitments Inspection Plan 2 ML0914606132009-05-0606 May 2009 Inspection Cover Sheet, Report No. 50-219-08-007, Facility: Oyster Creek, with Handwritten Notes ML0914606122009-05-0606 May 2009 Inspection Cover Sheet, Report No. 50-219-08-007, Facility Oyster Creek IR 05000219/20090012009-03-0404 March 2009 Annual Assessment Letter - Oyster Creek Generating Station (05000219-09-001) ML0915403162008-10-23023 October 2008 Inspection Cover Sheet, Facility: Oyster Creek, with Handwritten Notes ML0914606812008-10-23023 October 2008 E-mail from J. Richmond of USNRC to Various, Regarding Oc License Renewal Inspection Plan ML0914606192008-10-22022 October 2008 E-mail from J. Richmond of USNRC to M. Modes of USNRC, Regarding Oc Lri Inspection Plan, Rev. 2 ML0824705692008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan for Oyster Creek IR 05000219/20080012008-03-0303 March 2008 (05000219-08-001), Annual Assessment Letter, EOC 2007 ROP8 ML0805900142008-02-27027 February 2008 Notification of Triennial Fire Protection Baseline Inspection ML0734706102007-12-13013 December 2007 ROP 8 - Oyster Creek - Change to Inspection Plan, 12/13/07 ML0724309392007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan ML0706105922007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Oyster Creek Station (05-219-07-001) ML0706004472006-10-31031 October 2006 1R21 Outage - NRC Inspection Question Log Complied by Amergen (12 Pages) ML0624401992006-08-31031 August 2006 Mid-cycle Performance Review and Inspection Plan - Oyster Creek Nuclear Plant ML0606604692006-03-0606 March 2006 3/06/2006 - Oyster Creek Pre-Inspection Cover Sheet and Inspection Plan for License Renewal ML0606201302006-03-0202 March 2006 2006-001 Annual Assessment Letter - Oyster Creek Generating Station (Report 05-219/2006001) ML0524207272005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Oyster Creek Nuclear Power Plant ML0518801352005-07-0707 July 2005 Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML0406308112004-03-0303 March 2004 2003-04 Annual Assessment Letter - Oyster Creek ML0713401642003-09-0505 September 2003 Post Strike Briefing Including Oyster Creek Post Strike (Reintegration) Inspection Plan August 12, 2003 ML0323906832003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for Oyster Creek Nuclear Generating Station ML0713401622003-08-21021 August 2003 Post Strike Monitoring Activities - Updated 8/21/03 ML0713401562003-08-12012 August 2003 Post Strike (Reintegration) Inspection Plan, August 12, 2003 ML0713401532003-08-0707 August 2003 Post Strike (Reintegration) Inspection Plan Draft IR 05000219/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Oyster Creek Generating Station (Report 50-219/02-01) ML0610206381990-11-26026 November 1990 Drywell Containment, Attachment 1 to Letter Dated 04/07/2006 2024-01-09
[Table view] Category:Letter
MONTHYEARIR 07200015/20244012024-10-30030 October 2024 NRC Independent Spent Fuel Storage Installation Security Inspection Report No. 07200015/2024401 ML24303A2822024-10-29029 October 2024 License Termination Plan Supplemental Submittal for Technical Bases Documents ML24284A1972024-10-10010 October 2024 Cover Letter Oyster Creek, License Termination Plan Acceptance Review ML24269A0462024-10-0404 October 2024 Cover Letter for Oyster Creek Nuclear Generating Station, License Amendment Request, License Termination Plan, Acceptance Review Request for Additional Information ML24274A0822024-09-25025 September 2024 Independent Spent Fuel Storage Installation Security Plan, Training Qualification Plan, Safeguards Contingency Plan, Revisions 1 and 2 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000219/20240022024-09-0505 September 2024 – NRC Inspection Report 05000219/2024002 and 07200015/2024001 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24214A0372024-08-0101 August 2024 License Amendment Request to Revise Renewed Facility Operating License to Add License Condition 2.C.(18) to Include License Termination Plan Requirements ML24179A1842024-07-23023 July 2024 June 20, 2024, Clarification Call on Preapplication Readiness Assessment of the Holtec Decommissioning International License Termination Plan ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000219/20240012024-05-14014 May 2024 Decommissioning Intl, LLC Oyster Creek Nuclear Generating Station - NRC Inspection Report No. 05000219/2024001 ML24120A0412024-04-29029 April 2024 Annual Radioactive Environmental Operating Report for 2023 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 ML24120A0402024-04-29029 April 2024 Annual Radioactive Effluent Release Report for 2023 ML24094A2142024-04-19019 April 2024 Preapplication Readiness Assessment of the Holtec Decommissioning International License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) ML24089A2492024-03-29029 March 2024 Reply to Notice of Violation EA-2024-024 ML24085A7902024-03-28028 March 2024 – Preapplication Readiness Assessment of the License Termination Plan ML24081A2882024-03-21021 March 2024 Request Preliminary Review and Feedback on Chapter 6 of the Draft License Termination Plan ML24046A1242024-02-29029 February 2024 – NRC Inspection Report 05000219/2023003 ML24033A3272024-02-0202 February 2024 Request Preliminary Review and Feedback on Chapter 5 of the Draft License Termination Plan ML23342A1162024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 IR 05000219/20230022023-11-0909 November 2023 EA-23-076 Oyster Creek Nuclear Generating Station - Notice of Violation and Proposed Imposition of Civil Penalty - $43,750 - NRC Inspection Report No. 05000219/2023002 ML23286A1552023-10-13013 October 2023 Defueled Safety Analysis Report (DSAR) ML23249A1212023-09-0606 September 2023 – NRC Inspection Report 05000219/2023002, Apparent Violation (EA-23-076) ML23242A1162023-08-30030 August 2023 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Report – January 1, 2021 Through December 31, 2022 ML23214A2472023-08-22022 August 2023 – NRC Inspection Report 05000219/2023002 IR 05000219/20230012023-05-31031 May 2023 – NRC Inspection Report No. 05000219/2023001 IR 07200015/20234012023-05-16016 May 2023 – NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2023401 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 ML23114A0872023-04-24024 April 2023 Annual Radioactive Environmental Operating Report for 2022 ML23114A0912023-04-24024 April 2023 Annual Radioactive Effluent Release Report for 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000219/20220022023-02-0909 February 2023 NRC Inspection Report No. 05000219/2022002 ML23031A3012023-02-0808 February 2023 Discontinuation of Radiological Effluent Monitoring Location in the Sewerage System ML23033A5052023-02-0202 February 2023 First Use Notification of NRC Approved Cask RT-100 ML23025A0112023-01-24024 January 2023 LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML22347A2732022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22297A1432022-12-15015 December 2022 Part 20 App G Exemption Letter L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 IR 07200015/20224012022-12-0606 December 2022 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2022401 (Letter & Enclosure 1) ML22280A0762022-11-0202 November 2022 Us NRC Analysis of Holtec Decommissioning Internationals Funding Status Report for Oyster Creek, Indian Point and Pilgrim Nuclear Power Station ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22286A1402022-10-13013 October 2022 NRC Confirmatory Order EA-21-041 IR 05000219/20220012022-08-11011 August 2022 NRC Inspection Report 05000219/2022001 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages 2024-09-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 March 3, 2008 Mr. Charles Chief Nuclear Officer and Senior Vice President
Exelon Generation Company, LLC
200 Exelon Way, KSA 3-E
Kennett Square, PA 19348
SUBJECT: ANNUAL ASSESSMENT LETTER - OYSTER CREEK NUCLEAR GENERATING STATION (REPORT 05000219/2008001)
Dear Mr. Pardee:
On February 12, 2008, the NRC staff completed its performance review of Oyster Creek
Nuclear Generating Station (Oyster Creek). Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through
December 31, 2007. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A
separate letter designated and marked as "Official Use Only-Security Information" will include
the security cornerstone review and resultant inspection plan.
Oyster Creek plant performance for the last two quarters of 2007 was within the Licensee
Response column of the NRC Action Matrix, based on all inspection findings being classified as
very low safety significance (Green) and all PIs indicating performance at a level requiring no
additional NRC oversight (Green). No substantive cross cutting issues were identified in any of
the three cross cutting areas.
Oyster Creek performance for the first and second quarters of 2007 was within the Regulatory
Response column of the NRC Action Matrix based on one inspection finding being classified as
having low to moderate safety significance (White) in the Emergency Preparedness (EP)
Cornerstone. The White finding involved Oyster Creek staff not recognizing that plant
parameters met emergency action level (EAL) thresholds during an event in August 2005. The
NRC completed a supplemental inspection in accordance with Inspection Procedure 95001 in
June 2007 to review actions taken by AmerGen to address the White EP finding, and concluded
that AmerGen appropriately identified the r oot causes and adequately implemented corrective actions for this issue. As a result, plant performance was restored to the Licensee Response
column of the NRC Action Matrix.
Based on current plant performance, we plan to conduct reactor oversight process (ROP)
baseline inspections at Oyster Creek. In addition, we will also conduct inspections related to
the independent spent fuel storage installation. The enclosed inspection plan details the inspections, less those related to physical protection scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of
any scheduling conflicts and personnel availability issues well in advance of inspector arrival
onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last nine months of the inspection plan are tentative and may be revised
at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRC's "Rules and Practices," a copy of this letter and
its enclosure will be made available electronically for public inspection in the NRC Public
Document Room or from the Publicly Avail able Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-
rm/adams.html (The Public Electronic Reading Room).
The NRC is currently evaluating the scope and frequency of all the baseline inspection
procedures. If the results of the evaluation, or any other circumstances, cause us to change the
inspection plan, we will contact you to discuss the change as soon as possible. Please contact
Dr. Ronald Bellamy at 610-337-5200 with any questions you may have regarding this letter or
the inspection plan.
Sincerely,/RA/ David C. Lew, Director Division of Reactor Projects
Docket Nos. 50-219
License Nos. DPR-16
Enclosure:
Oyster Creek Nuclear Generating Station Inspection/ Activity Plan
cc w/encl:
Chief Operating Officer, AmerGen
Site Vice President, Oyster Creek Nuclear Generating Station, AmerGen
Plant Manager, Oyster Creek Generating Station, AmerGen
Regulatory Assurance Manager Oyster Creek, AmerGen
Senior Vice President - Nuclear Services, AmerGen
Vice President - Mid-Atlantic Operations, AmerGen
Vice President - Operations Support, AmerGen
Vice President - Licensing and Regulatory Affairs, AmerGen
Director Licensing, AmerGen
Manager Licensing - Oyster Creek, AmerGen
Vice President, General Counsel and Secretary, AmerGen
T. O'Neill, Associate General C ounsel, Exelon Generation Company J. Fewell, Assistant General Counsel, Exelon Nuclear
Correspondence Control Desk, AmerGen
J. Matthews, Esquire, Morgan, Lewis & Bockius LLP
Mayor of Lacey Township