2014 Annual Assessment Letter for Millstone Power Station, Units 2 and 3, (Report 05000336/2014001 and 05000423/2014001)(w/Inspection Plan)
ML15057A399
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 03/04/2015
From: Ho Nieh
Division Reactor Projects I
To: Heacock D
Dominion Resources
McKinley R
References
IR 2014001
Download: ML15057A399 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 March 4, 2015

Mr. David Heacock President and Chief Nuclear Officer Dominion Resources 5000 Dominion Boulevard

Glen Allen, VA 23060-6711

SUBJECT: ANNUAL ASSESSMENT LETTER FOR MILLSTONE POWER STATION, UNITS 2 AND 3 (REPORT 05000336/2014001 AND 05000423/2014001)

Dear Mr. Heacock:

On February 10, 2015, the U. S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review for Millstone Power Station (Millstone), Units 2 and 3. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014 through December 31, 2014. This letter informs

you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, Millstone operat ed in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Millstone Unit 2 during the most recent assessment period was within the Licensee Response

Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., Green) safety significance, and all PIs demonstrated that your performance was within the nominal, expected range (i.e, Green).

The NRC determined the performance at Millstone Unit 3 was within the Regulatory Response Column of the ROP Action Matrix as communicated to you in a letter dated October 20, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14294A220). This letter detailed the final significance determination of a White finding related to the identification and correction of conditions adverse to quality for the turbine-driven auxiliary feedwater pump.

Therefore, in addition to ROP baseline inspections at Millstone Unit 3, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure (IP) 95001, "Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area," after notification of your readiness for this inspection. This IP is conducted to provide assurance that the root causes and contributing causes of risk significant performance issues are understood, the extent of condition and cause were identified, and the corrective actions are sufficient to prevent recurrence. The NRC will also perform IP 60855.1, "Operation of an Independent Spent Fuel Storage Installation (ISFSI) at Operating Plants," IP 60855, "Operation of an ISFSI," IP 71003, "License Renewal Inspection (Phase 2)," for Millstone Unit 2, and IP 92702, "Follow-up on Corrective Actions for Violations and Deviations," for a Notice of Violation regarding feedwater isolation valve issues at Millstone Unit 3. Additionally, the NRC has not yet finalized the significance of an apparent violation identified during security inspection 2014201. This issue was the subject of a regulatory conference on February 17, 2015, and the final safety significance determination may affect the NRC's assessment of plant performance and the enclosed inspection plan.

The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.

In accordance with Title 10 of the Code of Federal Regulations , Part 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Mr. Raymond McKinley at 610-337-5150 with any questions you have regarding this letter.

Sincerely,

/RA/ Ho K. Nieh Director Division of Reactor Projects

Docket Nos. 50-336 and 50-423 License Nos. DPR-65 and NPF-49

Enclosure: Millstone Inspection/Activity Plan

cc w/encl: Distribution via ListServ

ML15057A399 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME SShaffer/SWS RMcKinley/RRM HNieh/HKN DATE 02/24/15 02/24/15 02/25/15

Page 1 of 2 02/03/2015 09:10:24 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on Site MillstoneInspection / Activity Plan 01/01/2015-06/30/201671124.08-RADWASTE 1 2, 3 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 01/12/2015 01/16/2015 CDBI-COMPONENT DESIGN BASIS INSPECTION 8 2, 3 IP Component Design Bases Inspection7111121 03/30/2015 04/03/2015 2, 3 IP Component Design Bases Inspection7111121 04/13/2015 04/17/2015 2, 3 IP Component Design Bases Inspection7111121 04/27/2015 05/01/2015 71003-U2 LR COMMITMENTS PHASE 2 INSP 4 2 IP Post-Approval Site Inspection for License Renewal 71003 05/04/2015 05/08/2015 2 IP Post-Approval Site Inspection for License Renewal 71003 05/18/2015 05/22/20159/7EXAM-U3 INITIAL OL EXAM 4 3 FY15-MS3 INITIAL OPERATOR LICENSING EXAM U01903 08/10/2015 08/14/2015 3 FY15-MS3 INITIAL OPERATOR LICENSING EXAM U01903 09/07/201509/11/201571124-RADIATION SAFETY INSPECTION - REMP 1 2, 3 IP Radiological Environmental Monitoring Program71124.07 05/18/2015 05/22/2015 ISFSI-ISFSI LOADING INSPECTION 2 2 IP Operation Of An ISFSI 60855 05/18/2015 05/22/2015 2 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 05/18/2015 05/22/20157111111B-U3 REQUAL INSP W/ P/F RESULTS 2 3 IP Licensed Operator Requalification Program7111111B 08/24/2015 08/28/201571124-RADIATION SAFETY INSPECTION - ALARA 1 2 IP Occupational ALARA Planning and Controls71124.02 07/27/2015 07/31/2015 EP-EP PROGRAM INSPECTION 1 2, 3 IP A lert and Notification System Testing7111402 08/10/2015 08/14/2015 2, 3 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 08/10/2015 08/14/2015 2, 3 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 08/10/2015 08/14/2015 92702-92702 FOR FEEDWATER ISOLATION VALVES NOV 1 3 IP Followup On Corrective Actions For Violations And Deviations 92702 08/10/2015 08/14/201571124-RADIATION SAFETY INSPECTION 1 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 10/05/2015 10/09/20157111108P-U2 INSERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 10/12/2015 10/23/201571124-RADIATION SAFETY INSPECTION - DOSE 1 2, 3 IP Occupational Dose Assessment71124.0411/16/201511/20/2015 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.

Page 2 of 2 02/03/2015 09:10:24 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on Site MillstoneInspection / Activity Plan 01/01/2015-06/30/201671124-RADIATION SAFETY INSPECTION - DOSE 1 2, 3 IP Performance Indicator Verification7115111/16/201511/20/2015 ISI-U3 INSERVICE INSPECTION 1 3 IP Inservice Inspection Activities - PWR7111108P 04/18/2016 04/29/2016 BI-RADIOLOGICAL SAFETY - RAD HAZARDS O 1 2, 3 IP A dverse Weather (Site/Imminent)7111101-Imminent 04/25/2016 04/29/2016 2, 3 IP Occupational ALARA Planning and Controls71124.02 04/25/2016 04/29/2016 2, 3 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 04/25/2016 04/29/2016 BI-RADIOLOGICAL SAFETY - AIRBORNE 1 2, 3 IP Occupational ALARA Planning and Controls71124.02 05/23/2016 05/27/2016 2, 3 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 05/23/2016 05/27/2016 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.