IR 05000440/2018003
From kanterella
Revision as of 19:10, 12 June 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
ML18313A054 | |
Person / Time | |
---|---|
Site: | Perry |
Issue date: | 11/08/2018 |
From: | Billy Dickson NRC/RGN-III/DRP/B2 |
To: | Hamilton D FirstEnergy Nuclear Operating Co |
References | |
IR 2018003 | |
Download: ML18313A054 (20) | |
Similar Documents at Perry | |
---|---|
Category:Inspection Report
MONTHYEARIR 05000440/20240052024-08-22022 August 2024
[Table view]Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2024005) IR 05000440/20240022024-08-0808 August 2024 Integrated Inspection Report 05000440/2024002 IR 05000440/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000440/2024401 IR 05000440/20240112024-06-17017 June 2024 Fire Protection Team Inspection Report 05000440/2024011 IR 05000440/20240012024-04-24024 April 2024 Integrated Inspection Report 05000440/2024001 IR 05000440/20230062024-02-28028 February 2024 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2023006) IR 05000440/20230042024-01-30030 January 2024 Integrated Inspection Report 05000440/2023004 IR 05000440/20234022024-01-10010 January 2024 Cyber Security Inspection Report 05000440/2023402 IR 05000440/20230112023-11-28028 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000440/2023011 IR 05000440/20234032023-11-27027 November 2023 Security Baseline Inspection Report 05000440/2023403 IR 05000440/20230032023-10-11011 October 2023 Integrated Inspection Report 05000440/2023003 IR 05000440/20234012023-08-28028 August 2023 Public - Perry Nuclear Power Plant Security Baseline Inspection Report 05000440/2023401 IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) IR 05000440/20230022023-08-0202 August 2023 Integrated Inspection Report 05000440/2023002 IR 05000440/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection Report 05000440/2023010 IR 05000440/20230012023-05-0404 May 2023 Integrated Inspection Report (05000440/2023001) IR 05000440/20220062023-03-0101 March 2023 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2022006) IR 05000440/20224062023-02-13013 February 2023 Material Control and Accounting Program Inspection Report 05000440/2022406 IR 05000440/20220042023-02-10010 February 2023 Integrated Inspection Report 05000440/2022004; and 07200069/2022001 and Exercise of Enforcement Discretion IR 05000440/20223012023-01-24024 January 2023 05000440/2022301 IR 05000440/20224052022-12-20020 December 2022 Security Baseline Inspection Report 05000440/2022405 (Cover Letter Only) IR 05000440/20220032022-11-0808 November 2022 Integrated Inspection Report 05000440/2022003 IR 05000440/20225012022-10-17017 October 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000440/2022501 IR 05000440/20220102022-09-29029 September 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000440/2022010 IR 05000440/20220052022-08-26026 August 2022 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2022005) IR 05000440/20220022022-08-0808 August 2022 Integrated Inspection Report 05000440/2022002 IR 05000440/20224202022-08-0404 August 2022 Security Baseline Inspection Report 05000440/2022420 - Cover Letter IR 05000440/20224022022-07-21021 July 2022 Security Baseline Inspection Report 05000440/2022402 IR 05000440/20224042022-06-0909 June 2022 Security Baseline Inspection Report 05000440/2022404 IR 05000440/20220012022-05-12012 May 2022 Integrated Inspection Report 05000440/2022001 IR 05000440/20210062022-03-0202 March 2022 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2021006) IR 05000440/20224012022-02-17017 February 2022 Security Baseline Inspection Report 05000440/2022401 IR 05000440/20210042022-02-11011 February 2022 Integrated Inspection Report 05000440/2021004 IR 05000440/20224032022-02-0909 February 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000440/2022403 IR 05000440/20210132022-01-10010 January 2022 Biennial Problem Identification and Resolution Inspection Report 05000440/2021013 IR 05000440/20210102021-12-0101 December 2021 Triennial Fire Protection Inspection Report 05000440/2021010 IR 05000440/20210032021-11-12012 November 2021 Integrated Inspection Report 05000440/2021003 IR 05000440/20214022021-10-27027 October 2021 Security Baseline Inspection Report 05000440/2021402 IR 05000440/20210122021-09-30030 September 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000440/2021012 IR 05000440/20210052021-09-0101 September 2021 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2021005) IR 05000440/20210022021-08-12012 August 2021 Integrated Inspection Report 05000440/2021002 IR 05000440/20210012021-06-10010 June 2021 NRC Inspection of Temporary Instruction 2515/194, Inspection of the Licensee'S Implementation of Industry Initiative Associated with the OPC Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01)-Inspection Report 0 ML21132A0952021-05-12012 May 2021 Integrated Inspection Report 05000440/2021001 IR 05000440/20213012021-04-0808 April 2021 NRC Initial License Examination Report 05000440/2021301 IR 05000440/20200062021-03-0404 March 2021 Annual Assessment Letter Perry Nuclear Power Plant (Report 05000440/2020006) IR 05000440/20200042021-02-12012 February 2021 Integrated Inspection Report 05000440/2020004 IR 05000440/20200102020-12-0303 December 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000440/2020010 IR 05000440/20204032020-12-0101 December 2020 Security Baseline Inspection Report 05000440/2020403 IR 05000440/20200032020-11-12012 November 2020 Integrated Inspection Report 05000440/2020003 and 07200069/2020001 IR 05000440/20205012020-10-16016 October 2020 Emergency Preparedness Biennial Exercise Inspection Report 05000440/2020501 2024-08-08 Category:Letter MONTHYEARL-24-179, License Renewal Application for the Perry Nuclear Power Plant Revision 0 - Supplement 52024-10-21021 October 2024
[Table view]License Renewal Application for the Perry Nuclear Power Plant Revision 0 - Supplement 5 L-24-208, License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2)2024-10-0202 October 2024 License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2) ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-207, License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 12024-09-16016 September 2024 License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 1 ML24225A0512024-09-13013 September 2024 Issuance of Alternative Request VR-9, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML24256A0872024-09-11011 September 2024 Fws to NRC, Concurrence with Endangered Species Act Nlaa Determinations for Perry License Renewal L-24-201, Spent Fuel Storage Cask Registration2024-09-0909 September 2024 Spent Fuel Storage Cask Registration ML24249A0882024-09-0606 September 2024 Letter to Rickey Armstrong, President_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0782024-09-0606 September 2024 Ltr. to Kenneth Meshigaud, Chairperson, _ Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0752024-09-0606 September 2024 Letter to Charles Diebold, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24166A0172024-09-0606 September 2024 Ltr. to Glenna Wallace, Chief, Eastern Shawnee Tribe of Oklahoma; Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24250A0412024-09-0606 September 2024 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected ML24247A0212024-09-0606 September 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Perry License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment (Consultation Code: 2024-0006782) ML24249A0762024-09-0606 September 2024 Letter to Douglas Lankford, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0862024-09-0606 September 2024 Letter to Regina Gasco-Bentley, Chairperson_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr L-24-200, License Renewal Application for Revision to Supplement 4 for Editorial Corrections2024-09-0505 September 2024 License Renewal Application for Revision to Supplement 4 for Editorial Corrections ML24228A1702024-09-0303 September 2024 Ltr to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24228A1712024-09-0303 September 2024 Ltr to Brian Dickens, EPA-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24240A1482024-08-27027 August 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24239A7782024-08-26026 August 2024 Aging Management Audit - Perry Unit 1 - License Renewal Application August 26 2024 L-24-190, Spent Fuel Storage Cask Registration2024-08-26026 August 2024 Spent Fuel Storage Cask Registration IR 05000440/20240052024-08-22022 August 2024 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule L-24-174, Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information2024-08-15015 August 2024 Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information L-24-178, License Renewal Application Revision O - Supplement 42024-08-0808 August 2024 License Renewal Application Revision O - Supplement 4 IR 05000440/20240022024-08-0808 August 2024 Integrated Inspection Report 05000440/2024002 L-24-189, License Renewal Application for Revision O - Supplement 12024-08-0707 August 2024 License Renewal Application for Revision O - Supplement 1 L-24-171, Spent Fuel Storage Cask Registration2024-07-30030 July 2024 Spent Fuel Storage Cask Registration ML24150A2022024-07-25025 July 2024 Letter to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-License Renewal Scoping Summary Rpt L-24-108, License Renewal Application, Revision 0 - Supplement 32024-07-24024 July 2024 License Renewal Application, Revision 0 - Supplement 3 05000440/LER-2024-003, Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage2024-07-15015 July 2024 Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage IR 05000440/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000440/2024401 L-24-020, License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 22024-06-27027 June 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 2 05000440/LER-2024-002, Reactor Water Clean Up Leak Detection Loss of Safety Function2024-06-27027 June 2024 Reactor Water Clean Up Leak Detection Loss of Safety Function L-24-036, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-27027 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models 05000440/LER-2024-001, Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition2024-06-20020 June 2024 Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition IR 05000440/20240112024-06-17017 June 2024 Fire Protection Team Inspection Report 05000440/2024011 ML24157A3782024-06-0606 June 2024 – Revised Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 ML24141A1632024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-116, Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification2024-05-16016 May 2024 Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification L-24-085, Nudear Power Plant, Submittal of Emergency Plan, Revision 622024-05-0606 May 2024 Nudear Power Plant, Submittal of Emergency Plan, Revision 62 L-24-103, Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams2024-05-0202 May 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams ML24117A1222024-04-26026 April 2024 Confirmation of Initial License Examination IR 05000440/20240012024-04-24024 April 2024 Integrated Inspection Report 05000440/2024001 L-24-096, Submittal of Annual Radiological Environmental Operating Report2024-04-22022 April 2024 Submittal of Annual Radiological Environmental Operating Report L-24-097, Submittal of 2023 Annual Radiological Effluent Release Report2024-04-22022 April 2024 Submittal of 2023 Annual Radiological Effluent Release Report ML24095A3282024-04-19019 April 2024 License Renewal Revised Schedule Letter L-24-083, Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification2024-04-15015 April 2024 Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification L-24-066, Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency2024-04-15015 April 2024 Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency 2024-09-09 |
Inspection Report - Perry - 2018003 | |||||||||
---|---|---|---|---|---|---|---|---|---|
|
Text
/RA/
OFFICIAL RECORD COPY
Code of Federal Regulations