ML20212N980

From kanterella
Revision as of 04:40, 5 May 2021 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Requests That NRC Approval Date for 860703 Tech Spec Change Re Reactor Water Storage Tank/Accumulator Boron Concentration Be Changed to 861031
ML20212N980
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 08/27/1986
From: Mcdonald R
ALABAMA POWER CO.
To: Rubenstein L
Office of Nuclear Reactor Regulation
References
TAC-61876, TAC-61877, NUDOCS 8609020115
Download: ML20212N980 (1)


Text

Milling Address Alibama Power Company 600 North 18th Street Post Office Dox 2641 Birmingham, Alabama 35291 Telephone 205 783-6090 R. P. Mcdonald Senior Vice President Flintndge Building gg g u s.w ,c w .w August 27, 1986 Docket Nos. 50-348 50-364 Director, Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Attention: Mr. L. S. Rubenstein Gentlemen:

Joseph M. Farley Nuclear Plant - Units 1 and 2 Proposed RWST/ Accumulators Boron Concentration Increase Technical Specification Change By letter of July 3,1986. Alabama Power Company submitted the subject Technical Specification Change and requested NRC approval by September 2, 1986. As a result of conversations with the NRC Farley Project Manager, the requested NRC approval date is to be changed to October 31, 1986 with Unit 1 implementation approval to be changed to during Modes 5 and 6 of the eighth refueling outage. The requested Unit 2 implementation during Modes 5 and 6 of the fifth refueling outage should remain unchanged.

If you have any questions, please advise.

Respectfully submitted, hlb h &

R. P. Mcdonald RPM /J AR : dst-D-T.S ,5 cc: Mr. L. B. Long Dr. J. N. Grace  %

Mr. E. A. Reeves Mr. W. H. Bradford Dr. C. E. Fox geol 8609020115 860827 DR ADOCKOSoog8