Examination 05000327/2016301 and 0500328/2016301, October 15, 2015, Sequoyah Nuclear Plant - Notification of Licensed Operator
ML15293A533
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 10/20/2015
From: McCoy G J
Division of Reactor Safety II
To: Shea J W
Tennessee Valley Authority
References
50-327/16-301, 50-328/16-301
Download: ML15293A533 (3)


See also: IR 05000327/2016301

Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 October 20, 2015 Joseph W. Shea Vice President, Nuclear Licensing

Tennessee Valley Authority

1101 Market Street, LP 3D-C

Chattanooga, TN 37402

SUBJECT: SEQUOYAH NUCLEAR PLANT - NOTIFICATION OF LICENSED OPERATOR INITIAL EXAMINATION 05000327/2016301 AND 05000328/2016301 Dear Mr. Shea: In a telephone conversation on October 15, 2015, between Mr. Michael Buckner, Operations

Initial Lead Examiner, and Mr. Phillip Capehart, Senior Operations Engineer, arrangements

were made for the administration of licensing examinations at Sequoyah Nuclear Plant. The operating test is scheduled to be administered during the weeks of March 7 and March 14, 2016. The written examination is scheduled to be administered the week of March 21, 2016. The on-site preparatory week is scheduled for the week of February 8, 2016.

As agreed during the telephone conversation, your staff will prepare both the operating test and

written examination based on the guidelines in Revision 10 of NUREG-1021, "Operator

Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory Commission (NRC) regional office will discuss with your staff any changes that might be necessary before the examinations are administered. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination.

To meet the above schedule, it will be necessary for your staff to furnish the operating test outline by December 9, 2015. Mr. Capehart provided the written examination outline to your staff in April, 2015. The operating test, written examination, and the supporting reference

materials identified in Attachment 3 to ES-201 will be due by January 8, 2016. Pursuant to Title

10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized

representative of the facility licensee shall approve the outline, examination, and test before

they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use.

We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in

receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.

To conduct the requested written examinations and operating tests, it will be necessary for your

staff to provide adequate space and accommodations in accordance with ES-402, and to make

the simulation facility available on the dates noted above. In accordance with ES-302,

J. Shea 2 your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final. Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications, medical certifications, and waiver requests (if any) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least

14 days before the first examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget (OMB) under approval number 3150-0018, which expires on April 30, 2016. The public reporting burden for this collection of information is estimated to average 2500

hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including

suggestions for reducing the burden, to the Information and Records Management Branch (T-6

F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet

electronic mail to infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.

The NRC may neither conduct nor sponsor, and a person is not required to respond to, an

information collection, unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of the NRC's document

system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room). Thank you for your cooperation in this matter. Mr. Buckner has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Capehart at (404) 997-4483, (Internet E-mail:

Phillip.Capehart@nrc.gov), or me at (404) 997-4551, (Internet E-mail: Gerald.McCoy@nrc.gov). Sincerely, /RA/ Gerald J. McCoy, Chief Operations Branch 1 Division of Reactor Safety

Docket Nos.: 50-327, 50-328

License Nos.: DPR-77, DPR-79

cc: Distribution Via Listserv

J. Shea 2 your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.

Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications, medical certifications, and waiver requests (if any) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget (OMB) under approval number 3150-0018, which expires on April 30, 2016. The public reporting burden for this collection of information is estimated to average 2500 hours0.0289 days <br />0.694 hours <br />0.00413 weeks <br />9.5125e-4 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.

The NRC may neither conduct nor sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room).

Thank you for your cooperation in this matter. Mr. Buckner has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Capehart at (404) 997-4483, (Internet E-mail: Phillip.Capehart@nrc.gov), or me at (404) 997-4551, (Internet E-mail: Gerald.McCoy@nrc.gov). Sincerely, /RA/ Gerald J. McCoy, Chief Operations Branch 1

Division of Reactor Safety

Docket Nos.: 50-327, 50-328 License Nos.: DPR-77, DPR-79 cc: Distribution Via Listserv PUBLICLY AVAILABLE NON-PUBLICLY AVAILABLE SENSITIVE NON-SENSITIVE ADAMS: Yes ACCESSION NUMBER:_______________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE PGC1 VIA EMAIL GJM1 NAME CAPEHART MCCOY DATE 10/19/2015 10/20/2015 10/ /2015 10/ /2015 10/ /2015 10/ /2015 10/ /2015 E-MAIL COPY? YES NO YES NO YESN YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: G:\OLEXAMS\SEQUOYAH EXAMINATIONS\INITIAL EXAM 2016-301\CORRESPONDENCE\SEQUOYAH 2016301 150 DAY LETTER.DOCX