ML18045A077

From kanterella
Jump to navigation Jump to search
301 Final As-Given RO Written Exam with Answer Key - Delay Release 2 Yrs
ML18045A077
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 02/14/2018
From:
NRC/RGN-II
To:
Tennessee Valley Authority
References
50-327/17-301, 50-328/17-301 50-327/OL-17, 50-328/OL-17
Download: ML18045A077 (78)


Text

SQN ILT 1712 NRC Exam

1. Given the following:

- Unit 1 is operating at 100% power.

- 1-SI-IFT-099-90.8A, "Reactor Trip Instrumentation Monthly Functional Test (SSPS) Train A," is in progress.

- Reactor Trip Breaker A (RTA) is open.

Subsequently, conditions occur which meet an automatic reactor trip.

- The reactor fails to trip automatically.

- Operation of the manual reactor trip switch trips the reactor.

Which ONE of the following completes the statements below?

The manual trip switch inputs signals to the (1)

AND the (2) will open.

A. (1) shunt trip and UV coils (2) RTB and BYA breakers B. (1) shunt trip and UV coils (2) RTB only C. (1) shunt trip coil only (2) RTB and BYA breakers D. (1) shunt trip coil only (2) RTB only 1

SQN ILT 1712 NRC Exam

2. Given the following:

- Unit 1 is at 100% power.

- The operating crew has entered AOP-R.05, RCS Leak and Leak Source Identification.

- Charging flow is maximized and pressurizer level is lowering.

- 1-TI-62-71, REGEN HX OUTLET TEMP - LETDOWN has lowered from its steady state value.

In accordance with AOP-R.05, which ONE of the following completes the statement below?

After letdown is manually isolated, operators (1) allowed to start an additional charging pump to stabilize pressurizer level and RCS leakage is from the charging line at point (2) of the drawing below.

A. (1) are (2) X B. (1) are (2) Y C. (1) are NOT (2) X D. (1) are NOT (2) Y 2

SQN ILT 1712 NRC Exam

3. Given the following:

- A large break LOCA occurred.

- Operators have just completed transfer to containment sump.

- A loss of offsite power occurs.

In accordance with ES-1.3, "Transfer to RHR Containment Sump," which one of the following describes the operator actions required for this condition?

A. Place the SI pumps and CCPs in Pull-to-Lock until the RHR pumps have been restarted after the shutdown boards are reenergized.

B. Place the CCPs in Pull-to-Lock until the RHR pumps have been restarted after the shutdown boards are reenergized.

C. Ensure both RHR pumps are started by the blackout sequencers after the diesel generators reenergize the shutdown boards, then restart the SI pumps.

D. Ensure ALL ECCS pumps are started by the blackout sequencers when the diesel generators reenergize the shutdown boards.

3

SQN ILT 1712 NRC EXAM

4. Given the following:

- Unit 1 is in Mode 1 at 30% power

- All 4 RCPs are in service Subsequently, the following reator trip - SI status bistable lights illuminate:

Which ONE of the following completes the statement below?

In-Core average temperature will (1)

AND the above bistable indications (2) result in an AUTOMATIC reactor trip on loop low flow.

A. (1) lower (2) will B. (1) lower (2) will NOT C. (1) rise (2) will D. (1) rise (2) will NOT 4

SQN ILT 1712 NRC Exam

5. Given the following:

- Unit 1 is in Mode 5 with the pressurizer solid.

- Train A RHR is operating in Shutdown Cooling.

- The following alarm is received:

"FCV-74-1/2 TROUBLE OR RHR PRESS HI (M6-C, E-7)"

- Operators are unable to reduce RCS pressure.

- The 1A-A RHR pump is stopped and RCS pressure continues to rise.

Which ONE of the following identifies ...

(1) the minimum RCS Pressure at which FCV-74-1 and 74-2 (RHR SUCTION FROM LOOP 4 HL) will be closed in accordance with AOP-R.03, "RHR System Malfunction" AND (2) the reason for this required action?

A. (1) 380 psig (2) Prevent RCS inventory loss B. (1) 380 psig (2) Prevent over-pressurization of the PRT C. (1) 450 psig (2) Prevent RCS inventory loss D. (1) 450 psig (2) Prevent over-pressurization of the PRT.

5

SQN ILT 1712 NRC RO EXAM

6. Which ONE of the following completes the statements below?

(1) #3 RCP Thermal Barrier Heat Exchanger will automatically isolate when the (1) setpoint is reached AND (2) the CCS flow through the #4 RCP Thermal Barrier Heat Exchanger will (2) ?

(1) (2)

A. Inlet flow > Outlet flow rise B. Inlet flow > Outlet flow isolate C. Outlet flow > Inlet flow rise D. Outlet flow > Inlet flow isolate 6

SQN ILT 1712 NRC Exam

7. Given the following:

- Unit 1 is drawing a bubble in the Pressurizer

- PZR level cold cal is at 100%

- The OATC placed 1-PIC-68-340A, PZR PRESSURE CONTROL in MANUAL and the output failed to 25%

Which ONE of the following completes the statements below?

When the BACKUP HEATERS A and B heater control switches are placed in A-P AUTO from the OFF position they energize due to the (1) .

AND As the PZR liquid is heated for bubble formation letdown flow must be (2) to maintain a constant RCS pressure.

A. (1) pressure control malfunction (2) raised B. (1) pressure control malfunction (2) lowered C. (1) PZR level (2) raised D. (1) PZR level (2) lowered 7

SQN ILT 1712 NRC Exam

8. Given the following:

- Unit 1 is at 98% power.

- A Steam Generator Tube Leak to the #1 SG is in progress.

- The crew has calculated a leak rate of 7 gpm.

- PZR level is stable.

- VCT level is at 12% and lowering.

- AUTO and MANUAL VCT make-up are NOT available.

Which ONE of the following completes the statement below?

In accordance with AOP-R.01, "Steam Generator Tube Leak", the reactor (1) required to be tripped AND Unit 1 (2) in compliance with the primary to secondary leakage specification of TS 3.4.13, "RCS Operational LEAKAGE".

A. (1) is (2) is B. (1) is (2) is NOT C. (1) is NOT (2) is D. (1) is NOT (2) is NOT 8

SQN ILT 1712 NRC Exam

9. Given the following:

- A station blackout has occurred.

- ECA-0.0, "Loss of All AC Power," is in progress.

Which ONE of the following completes the statement below?

Prior to the restoration of AC power, the Pressurizer Power Operated Relief Valves (PORVs) (1) be able to be operated from the MCR AND the PORV Block Valves (2) be able to be operated from the MCR.

A. (1) will (2) will B. (1) will (2) will NOT C. (1) will NOT (2) will D. (1) will NOT (2) will NOT 9

SQN ILT 1712 NRC Exam

10. Given the following:

- Unit 1 has experienced a Loss of all AC.

- ECA-0.0, "Loss of All AC Power," is in progress.

In accordance with EA-250-1, "Load Shed of Vital Loads After Station Blackout",

(1) The maximum time for initial Load Shed actions to be completed is (1) and (2) the SSPS status lights (2) be available.

A. (1) 45 minutes (2) will B. (1) 45 minutes (2) will NOT C. (1) 90 minutes (2) will D. (1) 90 minutes (2) will NOT 10

SQN ILT 1712 NRC Exam

11. Given the following:

- Unit 1 has experienced a Loss of all AC.

- ECA-0.0, "Loss of All AC Power," is in progress.

- EA-250-1, "Load Shed of Vital Loads after Station Blackout," is complete.

- Flex procedures are NOT implemented.

Which ONE of the following identifies the indications that operators will use in accordance with ECA-0.0 to determine the status of CST water supply to the TDAFW pump?

A. CST level on 1-M-2 B. CST level on 2-M-2 C. Condensate Transfer Pump Suction pressure D. TDAFW suction pressure 11

SQN ILT 1712 NRC Exam

12. Given the following:

- Unit 1 & 2 are steady-state at 100% power.

- 125V DC Vital Battery Board IV is inadvertently deenergized.

- All 4 Diesel Generators start.

Which ONE of the following describes an effect this has on the diesel generators?

A. Diesel Generator 2B-B can be shutdown using the EMERGENCY STOP pushbutton on 0-M-26.

B. Diesel Generator 2B-B can be shutdown using the Local Panel EMERGENCY STOP pushbutton at the DG Building.

C. All engine trips except for overspeed on Diesel Generator 2B-B will be disabled and ALL generator trips will remain enabled.

D. All generator trips except for generator differential on Diesel Generator 2B-B will be disabled and ALL engine trips will remain enabled.

12

SQN ILT 1712 NRC Exam

13. Given the following:

- The crew entered AOP-M.01, "Loss of Essential Raw Cooling Water," due to high flow on ERCW Supply Header 2A.

- The leak was isolated by closing 2-FCV-67-223, Hdr 2A to Hdr 1B Isol Valve.

Which one of the following describes the flow path of the ERCW Supply Header to the CCS heat exchangers after the leak is isolated?

[REFERENCE PROVIDED]

2A1/2A2 Hx OB1/OB2 Hx 1A1/1A2 Hx A. 2A ERCW Supply 2B ERCW Supply 1B ERCW Supply Header Header Header B. 2A ERCW Supply ERCW Isolated 1B ERCW Supply Header to Hx Header C. 2A ERCW Supply 2B ERCW Supply ERCW Isolated Header Header to Hx D. ERCW Isolated 2B ERCW Supply 1B ERCW Supply to Hx Header Header 13

SQN ILT 1712 NRC Exam

14. Given the following:

- Unit 1 is in Mode 3 following a manual reactor trip due to a control air line break in the non-essential control air header.

- The crew has implemented AOP-M.02, "Loss of Control Air."

Which ONE of the following completes the statement below?

During the performance of AOP-M.02 local actions are required to control _________ due to the loss of non-essential control air.

A. RCS pressure B. RCS temperature C. SG levels D. PZR level 14

SQN ILT 1712 NRC Exam

15. Which ONE of the following completes the statement below?

In accordance with AOP-P.07, Degraded Grid or Abnormal Voltage Conditions, the latest the transmission operator must be notified is within (1) of (2) .

(1) (2)

A. 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> generator frequency of less than 59.5 Hz B. 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> loss of the automatic generator voltage regulator C. 30 minutes generator frequency of less than 59.5 Hz D. 30 minutes loss of the automatic generator voltage regulator 15

SQN ILT 1712 NRC Exam

16. Given the following:

- Unit 1 was operating at 100% power.

- A Loss Of Coolant Accident (LOCA) outside containment results in RCS Subcooling of 0 oF and pressurizer level at 9%.

- The operating crew is performing ECA-1.2, "LOCA Outside Containment."

Which ONE of the following completes the statements below?

The first component expected to be manipulated in ECA-1.2 is (1) .

Confirmation the LOCA has been isolated would be a rising (2) .

(1) (2)

A. RHR suction from RCS Pressurizer level B. RHR suction from RCS RCS pressure C. RHR Cold Leg Injection Pressurizer level D. RHR Cold Leg Injection RCS pressure 16

SQN ILT 1712 NRC Exam

17. Given the following:

- FR-H.1, "Response to a Loss of Secondary Heat Sink," is in progress.

- All SGs are completely dry and depressurized.

- RCS bleed and feed has been initiated.

- Containment pressure is 2.9 psig and stable.

Subsequently,

- Auxiliary Feedwater (AFW) capability is restored.

- All CETs are LOWERING.

Which ONE of the following completes the statements below?

With AFW restored the crew will feed one SG at (1)

AND Secondary heat sink is considered to be restored at (2) narrow range level.

A. (1) the maximum available rate (2) 10%

B. (1) the maximum available rate (2) 25%

C. (1) 50 - 100 gpm (2) 10%

D. (1) 50 - 100 gpm (2) 25%

17

SQN ILT 1712 NRC Exam

18. Given the following:

- Unit 1 is in Mode 1 with 1A-A RHR pump tagged out.

Subsequently,

- A LOCA occurs and 1B-B RHR pump trips due to a locked rotor.

- The crew transitions to ECA-1.1, "Loss of ECCS Sump Recirculation."

- The conditions at the transition are:

  • RCS pressure is 160 psig
  • Containment pressure is 9.7 psid
  • Containment sump level is 17%

When ALL ECA-1.1 steps to address Containment Spray Pump operation are completed, which ONE of the following identifies the number of Containment Spray Pump(s) that will be running and their suction source?

Number of Pumps Running Suction Source A. 1 RWST B. 1 Containment sump C. 2 RWST D. 2 Containment sump 18

SQN ILT 1712 NRC Exam

19. Given the following:

- Unit 1 is at 80% power and stable.

- Rod control is in Automatic.

- CBD group 1 rods ONLY begin to withdraw continuously with the Urgent Failure Alarm not responding properly to stop movement.

- Operators place rod control in manual and rod withdrawal stops.

- CBD group 1 rods are now 14 steps greater than group 2.

Which ONE of the following completes the statement below?

In accordance with Tech Spec 3.1.4, "Rod Group Alignment Limits," Shutdown Margin is required to be verified __________.

A. immediately B. within a maximum of 15 minutes C. within a maximum of 30 minutes D. within a maximum of 60 minutes 19

SQN ILT 1712 NRC Exam

20. Given the following:

- Unit 1 is at 75% power and stable.

- Pressurizer Level Control Selector Switch (XS-68-339E) is in the 339/335 position, and level control is in automatic.

- Subsequently,

- Temperature input to the PZR level control system fails to 530°F.

Which ONE of the following describes the effect this condition would have on the PZR level control system? (Assume NO operator action)

A. Charging initially rises to 120 gpm then returns to normal and PZR level stabilizes at a higher value.

B. Charging initially lowers to minimum flow and indicated PZR level lowers to 25%

where it stabilizes.

C. Charging lowers to minimum and indicated PZR level lowers until Letdown isolates, then level rises until the reactor trips.

D. Charging rises to 120 gpm and the PZR level rises until the reactor trips.

20

SQN ILT 1712 NRC Exam

21. Given the following:

- Unit 1 is in Mode 6.

- An irradiated assembly is in the manipulator crane and is being transferred from an incore location to the upender.

- The Refueling SRO determines a leak has developed in the Reactor Cavity Seal.

- No assemblies are in the RCCA change fixture.

In accordance with AOP-M.04, "Refueling Malfunctions," which ONE of the following identifies the required action to be taken with the fuel assembly?

A. Place the fuel assembly in the upender and transport to the SFP.

B. Place the fuel assembly in the upender and lower the upender.

C. Place the fuel assembly in the RCCA change fixture.

D. Place the fuel assembly in any core location.

21

SQN ILT 1712 NRC Exam

22. Given the following:

-Unit 1 is operating at 100%

Subsequently, a rise in secondary plant radiation levels with stable charging flow and pressurizer level require the crew to enter AOP-R.01, Steam Generator Tube Leak.

Which one of the following completes the statement below?

In accordance with AOP-R.01, the preferred indication for leak rate monitoring is the (1) radiation monitor AND IF the leak rate stabilizes at an acceptable level the secondary radiation monitor setpoints are raised to (2) .

Note:

Steam Generator Blowdown (SGBD) Radiation Monitor (1-RM-90-120 and 1-RM-90-121)

Condenser Vacuum Exhaust (CVE) Radiation Monitor (1-RM-90-99 and 1-RM-90-119)

A. (1) SGBD (2) provide prompt indication of a rise in leakage B. (1) SGBD (2) allow SGBD release to Con DI C. (1) CVE (2) provide prompt indication of a rise in leakage D. (1) CVE (2) allow SGBD release to Con DI 22

SQN ILT 1712 NRC Exam

23. Given the following:

- Unit 1 turbine load is at 65% power.

- Condenser pressure is 1.8 psia and rising.

- Operators have entered AOP-S.02, "Loss of Condenser Vacuum."

Subsequently, the following indications are observed:

Time Condenser Pressure 0900 2.7 psia 0903 2.9 psia 0905 3.4 psia 0907 3.6 psia Based on the conditions listed above what is the earliest time a Reactor Trip is required in accordance with AOP-S.02?

A. 0900 B. 0903 C. 0905 D. 0907 23

SQN ILT 1712 NRC Exam

24. Given the following:

- Unit 1 is at 100%

- Waste Gas Decay Tank (WGDT) A is in service

- WGDT B is in standby

- WGDT H is on HUT cover gas

- WGDT 'J' is being released Following increased radiation levels in the Auxiliary Building (AB), a pipe leak into the AB is discovered downstream of 0-77-751A, Isolation valve to cover gas header.

Which ONE of the following list the valves that must be repositioned to stop the leak?

NOTE: Assume system lineup is as shown on reference.

[REFERENCE PROVIDED]

A. 0-77-740A, Gas inlet header isolation valve and 0-77-742A, Gas Decay Tank Isol Valve.

B. 0-77-748J, "Isol Valve to Gas Release Header" and 0-77-749, "Gas Tank Discharge Isolation Valve Before HEPA Filter".

C. 0-77-751H, Isolation valve to cover gas header and 0-77-752, Header ISOL to Holdup Tanks.

D. 0-77-740A, Gas inlet header isolation valve, 0-77-739A, "Waste gas Compressor Discharge Valve" and 0-77-739B, "Waste gas Compressor Discharge Valve".

24

SQN ILT 1712 NRC Exam

25. Given the following:

- The Main Control Room has been abandoned.

- The transfer switches per AOP-C.04, "Shutdown from the Auxiliary Control Room," have been placed in the AUX position.

- Aux Control Room alarm "PS-68-336AC RCS PRZR PRESS HI" has just been received .

Which ONE of the following identifies the lowest RCS pressure when the alarm is received and where the PZR Backup heaters will be operated?

RCS Pressure Location A. 2310 psig 6.9 Kv Shutdown Boards 1A-A & 1B-B B. 2310 psig 1-L-10, Auxiliary Control Room C. 2335 psig 6.9 Kv Shutdown Boards 1A-A & 1B-B D. 2335 psig 1-L-10, Auxiliary Control Room 25

SQN ILT 1712 NRC Exam

26. Given the following:

- Unit 1 is operating at 100% power at BOL.

Subsequently, a reactor trip occurs.

- Shutdown Bank 'B' rod G3 remains at 228 steps.

- Control Bank 'D' rod M8 indicates 10 steps.

- Tavg dropped to 529°F and stable.

Which ONE of the following completes the statement below?

In accordance with ES-0.1, "Reactor Trip Response," Emergency Boration is ______ .

A. NOT required B. required due to the RCS temperature ONLY C. required due to the stuck control rods ONLY D. required due to BOTH the RCS temperature and the stuck control rods 26

SQN ILT 1712 NRC Exam

27. Given the following:

- Unit 1 has experienced a reactor trip with a loss of offsite power.

- The operating crew has entered ES-0.2, "Natural Circulation Cooldown."

Which ONE of the following identifies the maximum allowed RCS cooldown rate and the method for dumping steam for the RCS cooldown?

Rate RCS Cooldown Method A. 50°F / hour Atmospheric Relief Valves B. 50°F / hour Steam Dumps C. 100°F / hour Atmospheric Relief Valves D. 100°F / hour Steam Dumps 27

SQN ILT 1712 NRC Exam

28. Given the following:

- Unit 1 is in Mode 3 with the reactor trip breakers open and the RCS at normal operating temperature and pressure.

- The following annunciators alarm:

1-XA-55-5B, B REAC COOL PMPS SEAL LEAKOFF HIGH FLOW 1-XA-55-5B, E REAC COOL PMPS SEAL WATER TEMP HI

- MCR indications for Loop 3 RCP seal parameters are:

Supply 9.6 gpm and stable Leakoff 8.4 gpm and stable Outlet Temperature 178°F and rising slowly

- 1-XA-55-5B, C REAC COOL PMP 3 STANDPIPE LVL HIGH-LOW, is DARK.

- The operating crew enters AOP-R.04, "RCP Malfunctions" and removes the pump from service.

Which ONE of the following identifies...

(1) the RCP seal that has failed, AND (2) how the seal return valve will be positioned following the RCP coastdown?

Seal Failed #1 Seal return valve A. #1 Seal closed B. #1 Seal remain open C. #2 Seal closed D. #2 Seal remain open 28

SQN ILT 1712 NRC Exam

29. Given the following:

- Unit 1 is at 100% power.

- 1-FCV-62-93, Charging Flow Control Valve is in Manual.

- 1-FCV-62-89, Charging Seal Water Flow Control Valve, is operating at 60%

open.

- Due to a positioner failure, 1-FCV-62-89 throttles close, and sticks at the 30% open position.

What effect will this malfunction have on charging pump discharge pressure and RCP seal injection flow?

Charging Pump RCP Seal Discharge Press Injection Flow A. Lowers Rises B. Rises Lowers C. Rises Rises D. Lowers Lowers 29

SQN ILT 1712 NRC Exam

30. Given the following:

- Auto Makeup occurred due to VCT level Subsequently, LT-62-130A, VCT Level (ICS computer point L0112A) failed low to 0%

- The following indications are observed:

Which ONE of the following completes the statements below?

Makeup flow indications for the given controller setpoints (1) as expected and the AUTO Makeup (2) stop automatically.

A. 1) are

2) will B. 1) are
2) will NOT C. 1) are NOT
2) will D. 1) are NOT
2) will NOT 30

SQN ILT 1712 NRC Exam

31. Given the following:

- Unit 1 is in Mode 4 cooling down for a refueling outage.

- RHR is in shutdown cooling mode.

Subsequently,

- A LOCA occurs with RCS temperature at 234°F.

- The operating crew is responding in accordance with AOP-R.02, "Shutdown LOCA," and the following parameters exist:

- RCS temperature (CETs) is 234°F and lowering.

- RCS pressure is 50 psig and lowering.

- The crew is on step 18:

Based on the conditions above which ONE of the following completes the statements below?

Currently, RHR injection (1) required.

AND If RHR injection is required, the time to cool RHR and realign the RHR pump for ECCS (2) a time critical action?

A. (1) is (2) is B. (1) is (2) is NOT C. (1) is NOT (2) is D. (1) is NOT (2) is NOT 31

SQN ILT 1712 NRC Exam

32. Given the following:

- Unit 2 is in Mode 4 cooling down.

- RCS temperature is at 340 °F and slowly lowering.

- RCS pressure is at 340 psig and slowly lowering.

- LTOP is armed.

SI-OPS-068-001.0, "Low Temperature Overpressure Protection," is complete.

Subsequently,

- A Safety Injection occurs on high containment pressure due to a LOCA.

Which ONE of the following completes the statements below?

The RHR pumps (1) auto start.

The SI pumps (2) inject into the RCS.

A. (1) will (2) will B. (1) will (2) will NOT C. (1) will NOT (2) will D. (1) will NOT (2) will NOT 32

SQN ILT 1712 NRC Exam

33. Given the following:

- Unit 1 is at 90% power.

- Due to a leaking PORV, 1-FCV-68-332, BLOCK VLV FOR PORV 334, was closed.

- The following indications are observed:

Which ONE of the following identifies the parameter(s) above, if any, that are procedurally required to be adjusted?

A. PRT pressure ONLY B. PRT temperature ONLY C. BOTH PRT pressure and temperature D. Neither parameter requires adjustment.

33

SQN ILT 1712 NRC Exam

34. Given the following:

- Unit 1 is being cooled down and has been placed in shutdown cooling with 'A' Train RHR in service.

- Annunciator "RHR HX A OUTLET TEMPERATURE HIGH" alarms on 0-XA-55-27B-A, E-6 "Component Cooling."

- Temperature on 1-TI-70-157, "RHR Heat Exchanger 1A Outlet Temperature," reads 120°F and stable.

In accordance with the Annunciator Response Procedure, which ONE of the following completes the statement below?

It is (1) to operate with the CCS temperature leaving the heat exchanger above the alarm setpoint and (2) could be used to lower the CCS temperature.

(1) (2)

A. acceptable lowering RHR heat exchanger bypass flow B. acceptable raising RHR heat exchanger bypass flow C. NOT acceptable lowering RHR heat exchanger bypass flow D. NOT acceptable raising RHR heat exchanger bypass flow 34

SQN ILT 1712 NRC Exam

35. Which ONE of the following identifies the Normal and Alternate power supplies to the C-S CCS Pump?

Normal Alternate A. 6.9 KV Shutdown Board 2B-B 6.9 KV Shutdown Board 1A-A B. 6.9 KV Shutdown Board 1A-A 6.9 KV Shutdown Board 2B-B C. 480V Shutdown Board 2B2-B 480V Shutdown Board 1A2-A D. 480V Shutdown Board 1A2-A 480V Shutdown Board 2B2-B 35

SQN ILT 1712 NRC Exam

36. Given the following:

- Unit 1 is operating at 100% power.

- Pressure Control Channel Selector Switch, 1-XS-68-340D is selected to PT-68-340 & 334 position.

Subsequently, PT-68-334, Pressurizer Pressure Transmitter, fails LOW.

- The operating crew enters AOP-I.04, "Pressurizer Instrument and Control Malfunctions."

Which ONE of the following completes the statements below?

Before any operator actions occur, the failure (1) result in the pressurizer back-up heaters being energized.

When AOP-I.04 performance is completed (2) of the PORVs will be able to automatically open if pressurizer pressure begins rising.

(1) (2)

A. will both B. will only one C. will NOT both D. will NOT only one 36

SQN ILT 1712 NRC EXAM

37. Given the following:

- Unit 2 is in Mode 3 with a cooldown in progress in accordance with 0-GO-7, "Unit Shutdown from Hot Standby to Cold Shutdown."

- The loop spray valve controllers (2-PCV-340B and 340D) have been placed in MANUAL to support maintenance.

Which ONE of the following completes the statements below?

To provide adequate spray flow through the Loop 2 Spray Valve, the minimum RCP alignment is (1) running.

The PZR heater groups C and D (2) required for Technical Specification compliance.

A. (1) #2 RCP and one other (2) are B. (1) #2 RCP and one other (2) are NOT C. (1) #2 RCP ONLY (2) are D. (1) #2 RCP ONLY (2) are NOT 37

SQN ILT 1712 NRC Exam

38. Given the following:

- Unit 1 shutdown is in progress.

- Reactor power is 14% and lowering.

- Intermediate Range NI-36 fails HIGH.

Which ONE of the following identifies how the failure of NI-36 will affect the reactor trip system and the effect the failure will have on the Source Range NIs?

Reactor Trip System Effect on Source Range NIs A. Reactor trip will occur at Source Range NIs will the time of failure. AUTOMATICALLY reinstate.

B. Reactor trip will occur at Source Range NIs will have the time of failure. to be MANUALLY reinstated.

C. Reactor trip will occur if Source Range NIs will the power reduction is AUTOMATICALLY reinstate.

continued.

D. Reactor trip will occur if Source Range NIs will have the power reduction is to be MANUALLY reinstated.

continued.

38

SQN ILT 1712 NRC Exam

39. Given the following:

- Unit 1 is operating in Mode 1.

- Bypass Breaker BYA is closed in preparation for Train-A SSPS testing.

Subsequently,

- Bypass Breaker BYB is inadvertently racked in and closed.

Which ONE of the following identifies the response of the plant?

A. No Reactor Trip or alarm.

B. Reactor will Trip.

C. "Protection System Train-B Trouble" alarm, no Reactor Trip.

D. Bypass Breaker BYB will trip open, no Reactor Trip.

39

SQN ILT 1712 NRC Exam

40. Given the following:

- The operating crew is responding to a loss of 120V AC Vital Instrument Power Board I-I.

- PZR pressure transmitter 1-PT-68-334 (Channel II) fails LOW.

Which ONE of the following describes the plant response?

A. Both trains of SSPS SI master relays would actuate AND both trains of ECCS equipment auto start.

B. Both trains of SSPS SI master relays would actuate BUT only "B" train ECCS equipment auto starts.

C. Only the "B" train SSPS SI master relays would actuate BUT both trains of ECCS equipment auto start.

D. Only the "B" train SSPS SI master relays would actuate AND only "B" train ECCS equipment auto starts.

40

SQN ILT 1712 NRC Exam

41. Given the following:

- Reactor Trip & Safety Injection occurred due to Large Break LOCA on Unit 1.

- Containment Phase B Isolation has occurred.

Which ONE of the following describes the response of the Lower Compartment Coolers?

Running Fans Cooler ERCW Isolation Valves A. Remain on Remain open B. Remain on Will close C. Auto Stop Remain open D. Auto Stop Will close 41

SQN ILT 1712 NRC Exam

42. Which ONE of the following Ice Condenser temperatures is within the optimum range to minimize sublimation, frost buildup, and ice condenser door binding problems?

o A. 18 F B. 21oF C. 24oF D. 27oF 42

SQN ILT 1712 NRC Exam

43. Given the following:

- A large break LOCA occurs on Unit 1.

- 1A-A Containment Spray (CS) Pump is out of service.

- ES-1.3, "Transfer To RHR Containment Sump," has been completed.

- 60 minutes later, the following conditions exist:

- Containment pressure is 10 psig and steady.

- 1B-B CS Pump discharge flow is 4000 gpm.

Which ONE of the following completes the statement below?

Containment spray flow is (1)

AND RHR spray (2) be placed in service.

(1) (2)

A. NORMAL should B. NORMAL should NOT C. LOWER than normal should D. LOWER than normal should NOT 43

SQN ILT 1712 NRC Exam

44. Given the following:

- The #3 SG MSIV failed to close manually when operated during the performance of E-0, "Reactor Trip or Safety Injection."

- EA-1-1, "Closing MSIVs Locally" is complete and all 125v control power fuses for #3 MSIV have been removed.

Which ONE of the following completes the statement below?

The #3 SG MSIV valve position is ____.

A. available at 6K Monitor Lights panel (1-XX-55-6K) ONLY B. available at #3 MSIV Handswitch (1-HS-1-22A) on 1-M-4 ONLY C. NOT available from 6K Monitor Lights panel or #3 MSIV Handswitch D. available from BOTH 6K Monitor Lights panel and #3 MSIV Handswitch 44

SQN ILT 1712 NRC Exam

45. Given the following:

- Unit 1 is stable at 100% power.

- A plant transient has occurred that has affected the SG level control system.

- Ten seconds after the transient began, the following indications are noted on associated loop 1 indications (all other loops are reading the same as loop 1):

Which ONE of the following identifies the Main Feed Reg Valve response at this time and the indication, if any, generating the signal(s) demanding that response? (Assume NO operator action)

A. MFRVs will continue to maintain their current position.

B. MFRVs will modulate open based on SG level indications ONLY.

C. MFRVs will modulate open based on the feed flow / steam flow indications ONLY.

D. MFRVs will modulate open based on BOTH feed flow / steam flow indications AND SG level indications.

45

SQN ILT 1712 NRC Exam

46. Which ONE of the following is the Normal power supply for the Unit 2 TDAFW pump Trip and Throttle valve, 2-FCV-1-51A-S?

A. 125V DC Vital Board I B. 125V DC Vital Board II C. 125V DC Vital Board III D. 125V DC Vital Board IV 46

SQN ILT 1712 NRC Exam

47. Given the following:

- Unit 1 & 2 are operating steady-state at 100%.

- 1B-B 6900V Shutdown Board voltage lowers to 6450V.

- The following alarms are received:

XA-55-26B window C-7, "6900V SD BD 1B-B FAILURE OR BUS UNDERVOLTAGE."

XA-55-1B, window B-6, "6900V SD BD 1B-B FAILURE OR BUS UNDERVOLTAGE/OVERVOLTAGE."

If the voltage remains unchanged, which ONE of the following identifies when the 1B-B 6.9 kV Shutdown Board Normal Feeder Breaker would open?

A. 1.25 seconds B. 9.5 seconds C. 30 seconds D. 300 seconds 47

SQN ILT 1712 NRC Exam

48. Given the following:

- Loss of off site power occurred on Unit 1 resulting in a Reactor Trip and Safety Injection.

- The Emergency Diesel Generators (EDGs) started and EDG 1A-A loaded to 4.6 MWs.

In accordance with AOP-P.01, "Loss of Offsite Power", which ONE of the following describes the operation of EDG 1A-A under this load condition?

A. May operate indefinitely.

B. Must be immediately tripped.

C. May operate for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> before excess EDG load must be reduced.

D. May operate for up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> before excess EDG load must be reduced.

48

SQN ILT 1712 NRC Exam

49. Given the following:

Which ONE of the following identifies ...

1) the failure that caused these indications AND
2) the required operator action in accordance with the alarm response procedure?

A. 1) Vital Charger I has tripped

2) Place Spare Charger 1-S in service to Vital Battery Board I B. 1) Vital Charger I has tripped
2) Place Spare Charger 2-S in service to Vital Battery Board I C. 1) A ground on Vital Battery Board I
2) Locally adjust red flag set point to clear the control room alarm.

D. 1) A ground on Vital Battery Board I

2) Open breakers one at a time on Vital Battery Board I until the ground clears.

49

SQN ILT 1712 NRC Exam

50. Given the following:

- Unit 1 is at 100% power.

- 1B-B CCP is tagged out.

Subsequently,

- A loss of offsite power occurs

- Fifteen (15) seconds after 1A-A 6.9kv Shutdown Board was energized by the 1A-A D/G, the following plant conditions are observed:

- 1A-A CCP is NOT running

- 1A-A AFW pump is NOT running What are the required operator actions to restore the CCP and the AFW pump?

1A-A CCP 1A-A AFW Pump A. Monitor for Automatic Start Monitor for Automatic Start B. Manually Start Manually Start C. Manually Start Monitor for Automatic Start D. Monitor for Automatic Start Manually Start 50

SQN ILT 1712 NRC Exam

51. Given the following:

- Annunciator 0-XA-55-26A, LS-18-3 Main Fuel Oil STG Tank 1 or 2 Low Level, has alarmed.

- The dispatched AUO reports that the No. 2 Fuel Oil Storage Tank (FOST) level is 4.0 feet and lowering and fuel oil is leaking into the FOST moat.

- All other diesel parameters are normal.

Which ONE of the following completes the statement below?

Unit 1 (1) in compliance with LCO 3.8.3, Diesel Fuel Oil, Lube Oil and Starting Air, and the affected diesels (2) have at least 7 days of fuel left.

A. (1) is (2) do B. (1) is (2) do NOT C. (1) is NOT (2) do D. (1) is NOT (2) do NOT 51

SQN ILT 1712 NRC Exam

52. Given the following:

- A release of the Neutralization Tank is in progress from the Condensate DI

- FCV-14-187, Neutralization Tank Outlet Isolation Valve, automatically closes Which ONE of the following conditions could cause the automatic closure of FCV-14-187?

A. Low level in the Neutralization Tank.

B. 0-RM-90-212, Turbine Building Sump Rad Monitor.

C. Hi Rad Signal from 0-RM-90-225, Cond DI Waste Effluent Monitor.

D. 0-FT-27-175, Cooling Tower Blowdown Flow, transmitter fails downscale.

52

SQN ILT 1712 NRC Exam

53. In accordance with AOP-M.01, "Loss of Essential Raw Cooling Water", which ONE of the following completes the statement below?

If running, (1) pumps may experience bearing failure (2) minutes after a loss of ERCW cooling.

A. 1) Containment Spray

2) 10 minutes B. 1) CCPs and SI
2) 10 minutes C. 1) Containment Spray
2) 15 minutes D. 1) CCPs and SI
2) 15 minutes 53

SQN ILT 1712 NRC Exam

54. Given the following:

- Unit 1 is in Mode 3, preparing for reactor startup.

- An air leak on the non-essential air header inside Unit 1 containment has developed.

- 1-FCV-32-110, Nonessential Air to Rx Bldg U-1 Isol, automatically closes.

Which ONE of the following completes the statement below?

As pressure on the header drops to 0 psig, CVCS Letdown Orifice isolation valves will (1) and ERCW TCVs for the Lower Containment Fan Coolers will (2) .

(1) (2)

A. be unaffected fail as is B. be unaffected fail open C. fail closed fail as is D. fail closed fail open 54

SQN ILT 1712 NRC Exam

55. Which ONE of the following completes the statement below regarding Phase B Containment Isolation?

The coincidence for an Automatic Phase B Containment Isolation is (1) bistables AND to initiate a Manual Phase B Containment Isolation, the operator will place a minimum of (2) of the Phase B handswitches on panel 2-M-6 to ACTUATE.

A. (1) 2 of 3 (2) one B. (1) 2 of 3 (2) two C. (1) 2 of 4 (2) one D. (1) 2 of 4 (2) two 55

SQN ILT 1712 NRC Exam

56. Given the following:

- A Small Break LOCA has occurred on Unit 1.

- RCS Subcooling is less than 40oF.

- RCPs are NOT in service.

o o

- All Core Exit T/Cs are between 710 F to 720 F and slowly rising.

- RVLIS Dynamic Range indications (1-LI-68-367 & 370) are 17% and stable.

- RVLIS Lower Range indications (1-LI-68-368 & 371) are 38% and slowly lowering.

Which ONE of the following completes the statements below?

(1) will be used to determine the state of core cooling AND FR-C.1, "Inadequate Core Cooling," (2) be entered.

A. (1) RVLIS Lower Range (2) will B. (1) RVLIS Lower Range (2) will NOT C. (1) RVLIS Dynamic Range (2) will D. (1) RVLIS Dynamic Range (2) will NOT 56

SQN ILT 1712 NRC Exam

57. Given the following:

- Unit 1 is at 100% power.

- Pressurizer Level Control Selector Switch, 1-XS-339E, is selected to the LT-68-339/320 position.

Which ONE of the following failures would result in a reactor trip in the shortest time assuming all systems respond as designed and there is NO operator action?

(Consider each failure to occur independently)

A. 1-LT-68-339 fails LOW B. 1-LT-68-339 fails HIGH C. 1-LT-68-320 fails LOW D. 1-LT-68-320 fails HIGH 57

SQN ILT 1712 NRC Exam

58. Given the following:

- Unit 1 is at 100% power.

- CBD group demand counters read 220 steps.

- CBD Rod D-4 is the highest indicated individual rod position at 218 steps.

- All other Rods in CBD indicate 216 steps.

Subsequently,

- RPI indication for CBD rod H-12 fails to 207 steps.

Which ONE of the following completes the statement below?

Annunciator 1-XA-55-4B D-4, COMPUTER ALARM ROD DEV & SEQ NIS PWR RANGE TILTS is ____________.

A. NOT in alarm B. in alarm due to the Rod to Bank Demand deviation ONLY C. in alarm due to the Rod to Rod deviation ONLY D. in alarm due to BOTH the Rod to Bank Demand and Rod to Rod deviation 58

SQN ILT 1712 NRC Exam

59. Given the following:

- Both Units are in Mode 1

- An alarm is received on 0-M-29, Fire Detection System.

- The CRO determines the alarm to be Cross Zone alarms from Zones 522 and Zone 523, both in Unit 2 Aux Building Supply Duct.

Which ONE of the following identifies ...

(1) how the Aux Bldg Fans are affected AND (2) the requirements for dispatching the Fire Brigade?

A. (1) Only the Aux Bldg Supply fans trip (2) Immediately dispatch the Fire Brigade.

B. (1) Only the Aux Bldg Supply fans trip (2) Confirm the alarms are valid prior to dispatching the Fire Brigade.

C. (1) All Aux Bldg Supply, Exhaust and Fuel Handling Exhaust fans trip (2) Immediately dispatch the Fire Brigade.

D. (1) All Aux Bldg Supply, Exhaust and Fuel Handling Exhaust fans trip (2) Confirm the alarms are valid prior to dispatching the Fire Brigade.

59

SQN ILT 1712 NRC Exam

60. Which ONE of the following is the power supply to the Emergency Gas Treatment System (EGTS) Fan B?

A. Reactor Vent Board 1B-B B. Reactor Vent Board 2B-B C. C & A Vent Board 1B1-B D. C & A Vent Board 2B1-B 60

SQN ILT 1712 NRC Exam

61. Given the following:

- Unit 1 is in Mode 1

- A lower containment purge is in progress RM-90-106 and 1-RM-90-131 indications are rising due to an RCS leak.

Note: 1-RM-90-106, Lower Containment Radiation Monitor 1-RM-90-131, Containment Purge Radiation Monitor Which ONE of the following completes the statement below?

When the High Radiation Setpoint is reached for the (1) Radiation Monitor a Containment Vent Isolation signal will be initiated AND After the Containment Vent Isolation, the 1-RM-90-106 control board reading (2) a valid indication.

A. (1) 1-RM-90-106 (2) is B. (1) 1-RM-90-106 (2) is NOT C. (1) 1-RM-90-131 (2) is D. (1) 1-RM-90-131 (2) is NOT 61

SQN ILT 1712 NRC Exam

62. Given the following:

- Annunciator AR-M12-B, B-5, "0-RA-90-103A FUEL POOL RAD MONITOR HI RAD", alarms.

Which ONE of the following completes the statement below?

In accordance with the annunciator response for AR-M12-B, B-5, an operator will have to manually actuate (1) ABI AND the purpose of the ABI actuation is to (2) .

A. (1) Train A (2) limit dose rates at the site boundary to less than federal limits.

B. (1) Train A (2) ensure any ABSCE boundary release is monitored by a PAM qualified radiation monitor.

C. (1) Train B (2) limit dose rates at the site boundary to less than federal limits.

D. (1) Train B (2) ensure any ABSCE boundary release is monitored by a PAM qualified radiation monitor.

62

SQN ILT 1712 NRC Exam

63. Given the following:

- Unit 1 is at 100% power.

- A reactor trip is initiated by operator action.

- Reactor Trip Breaker A (RTA) does NOT open.

Which ONE of the following identifies the response of the steam dump system?

The steam dumps will maintain the RCS Tavg at (1) with the (2) controller.

A. (1) 549°F (2) reactor trip B. (1) 549°F (2) load rejection C. (1) 552°F (2) reactor trip D. (1) 552°F (2) load rejection 63

SQN ILT 1712 NRC Exam

64. Which ONE of the following completes the statement below?

Before a liquid radwaste release can occur, the tank to be released must be recirculated for a minimum of (1) to prevent (2) .

A. 1) 30 minutes

2) obtaining a sample that is not representative of the tank contents B. 1) 30 minutes
2) the need for the process rad monitor(s) to be flushed prior to the release C. 1) 60 minutes
2) obtaining a sample that is not representative of the tank contents D. 1) 60 minutes
2) the need for the process rad monitor(s) to be flushed prior to the release 64

SQN ILT 1712 NRC Exam

65. Given the following:

- Both units are operating at 100% power.

- Control air system pressure begins to drop.

Which ONE of the following identifies...

(1) the pressure setpoint that the 0-PCV-33-4, "Service Air isolation from Control Air", will close AND (2) the expected position of 0-FCV-32-82, "Train A Control Air Supply Valve," if the air pressure is stabilized at 73 psig?

0-PCV-33-4 0-FCV-32-82 A. 88 psig Open B. 88 psig Closed C. 77 psig Open D. 77 psig Closed 65

SQN ILT 1712 NRC Exam

66. Given the following:

- Unit 1 at 100% power with Boric Acid Tank (BAT) A aligned.

- RWST Boric Acid concentration is 2550 ppm.

Which ONE of the following identifies BAT A Volume and Boric Acid Concentration that will meet Functionality requirements for TR 8.1.1, Borating Systems - Operating?

[REFERENCE PROVIDED]

A. 9600 gallons at 6500 ppm B. 9400 gallons at 6575 ppm C. 9250 gallons at 6775 ppm D. 9750 gallons at 6375 ppm 66

SQN ILT 1712 NRC Exam

67. Given the following:

- A Unit 2 automatic Safety Injection occurred 1 minute ago.

Which ONE of the following completes the statement below?

The indicated valve position for 0-FCV-67-152 (1) as expected AND the indicated valve position for 2-FCV-67-146 (2) as expected.

A. (1) is (2) is B. (1) is (2) is NOT C. (1) is NOT (2) is D. (1) is NOT (2) is NOT 67

SQN ILT 1712 NRC Exam

68. Which ONE of the following completes the statement below?

Spent Fuel Pool temperature alarms __________.

A. on Unit 1 ONLY B. on Unit 2 ONLY C. on BOTH Units D. locally ONLY 68

SQN ILT 1712 NRC Exam

69. Given the following:

- "PNL 1-M-7 Trouble" annunciator on 1-XA-55-1C is lit due to a blown fuse on 1-M-7 Preferred Power Rack .

- This is the first time the fuse has blown.

- A 'like-for-like' replacement fuse matching the installed fuse is available.

In accordance with OPDP-7, "Fuse Control" which ONE of the following completes the statements below?

A WO to 'troubleshoot the circuit' (1) required prior to the fuse replacement.

The Control Room Operator (CRO) (2) allowed to perform the fuse replacement.

A. (1) is (2) is B. (1) is (2) is NOT C. (1) is NOT (2) is D. (1) is NOT (2) is NOT 69

SQN ILT 1712 NRC Exam

70. While performing a cooldown on Unit 1 from Mode 3 to Mode 4 the following parameters were logged:

Time RCS Temp PZR LIQ Space Temp 0200 553°F 650°F 0230 527°F 606°F 0300 505°F 560°F 0330 447°F 494°F 0400 402°F 440°F Which ONE of the following completes the statement below?

RCS cooldown limits (1) exceeded AND PZR cooldown limits (2) exceeded.

A. (1) were (2) were B. (1) were (2) were NOT C. (1) were NOT (2) were D. (1) were NOT (2) were NOT 70

SQN ILT 1712 NRC Exam

71. In accordance with EPIP-15, "Emergency Exposure Guidelines," which ONE of the following individuals must authorize emergency exposure limits in excess 10CFR20 limits?

A. RP Manager B. Plant Manager C. Site Vice President D. Site Emergency Director 71

SQN ILT 1712 NRC Exam

72. Given the following:

- Unit 1 is in Mode 6, with core reload in progress.

- The Shutdown Monitor was last reset when the count rate was 6 cps.

- As the 20th fuel assembly is being set in the core, both source range monitor count rates begin rising.

Which ONE of the following listed 'count rates' is the lowest that would result in 1-X-55-4B, B-1, SOURCE RANGE HI FLUX AT SHUTDOWN being in alarm AND where the SOURCE RANGE HI FLUX AT SHUTDOWN alarm can be reset once counts have dropped below the alarm setpoint?

A. (1) 13 cps (2) 1-M-4 B. (1) 13 cps (2) 1-M-13 C. (1) 19 cps (2) 1-M-4 D. (1) 19 cps (2) 1-M-13 72

SQN ILT 1712 NRC Exam

73. Given the following:

- Reactor power is 100%.

- A reactor trip setpoint has been exceeded.

- Both the reactor and turbine will not trip via their respective control room trip switches.

Which ONE of the following identifies the immediate operator actions that the OATC and the CRO will perform per FR-S.1 "Nuclear Power Generation / ATWS?"

OATC CRO A. Maintain auto or manual rod Close main turbine governor insertion at max achievable rate. valves using the VPL or, if they cannot be closed, close MSIVs and MSIV bypass valves.

B. Maintain auto or manual rod Reduce turbine load using insertion at max achievable rate. turbine load controls at 200% per minute or, if controls do not respond, close MSIVs and MSIV bypass valves.

C. Initiate emergency boration from Close main turbine governor either the BAT or RWST. valves using the VPL, or if they cannot be closed, close MSIVs and MSIV bypass valves.

D. Initiate emergency boration from Reduce turbine load using either the BAT or RWST. turbine load controls at 200% per minute or, if controls do not respond, close MSIVs and MSIV bypass valves.

73

SQN ILT 1712 NRC Exam

74. Given the following:

Which ONE of the following completes the statements below?

In accordance with EPM-4, "User's Guide," 1-PR-1-2 "SG PRESSURE" (1) a Post Accident Monitoring (PAM) indication and 1-PI-1-2A "SG-1 PRESSURE" (2) a PAM indicator.

A. (1) is (2) is B. (1) is (2) is NOT C. (1) is NOT (2) is D. (1) is NOT (2) is NOT 74

SQN ILT 1712 NRC Exam

75. Given the following:

- Unit 1 was operating at 100% power when a LOCA occurs.

- Safety Injection automatically initiated but the reactor failed to trip and the operating crew was unable to trip the reactor from the MCR handswitches.

- FR-S.1, "Nuclear Power Generation/ATWS," has been entered.

- During performance of FR-S.1 Step 3, Check AFW status, the following conditions exist:

- Containment pressure is 3.0 psig and rising.

- RCS pressure is 1230 psig and dropping.

- Reactor power is 9% and dropping.

Which ONE of the following completes the statement below?

The RCPs (1) be tripped because (2) .

(1) (2)

A. are required to of the small break LOCA design basis requirements B. are required to the normal running support systems are not satisfied C. should NOT Immediate Operator Actions have not been completed D. should NOT reduced RCS heat removal could challenge fuel integrity 75

References for 1712 NRC RO Exam

1. Steam Tables
2. Mollier Diagram
3. 1, 2 - 47W845-2, Mechanical Flow Diagram ERCW
4. 1, 2 - 47W830-4, Mechanical Flow Diagram Waste Disposal
5. TRM Figure 8.1.1-1, Boric Acid Tank Limits Based on RWST Boron Concentration

Answers

  1. ID Points 0 1 007 EK2.02 1 1.00 A 2 009 EA2.02 602 1.00 C 3 011 EK2.02 3 1.00 B 4 015AK1.05 204 1.00 D 5 025 AK3.02 105 1.00 C 6 026 AA1.06 6 1.00 D 7 027 AK1.02 207 1.00 C 8 038 EG2.2.42 208 1.00 B 9 055 EA2.04 9 1.00 B 10 056 AG2.4.34 210 1.00 B 11 057 AA1.05 111 1.00 D 12 058 AK3.01 12 1.00 B 13 062 EA2.03 113 1.00 C 14 065 AK3.08 114 1.00 D 15 077AG2.4.20 415 1.00 D 16 W/E04 EK2.1 216 1.00 D 17 W/E05 EK1.2 317 1.00 D 18 W/E11 EA1.3 118 1.00 A 19 001 AG2.2.39 19 1.00 D 20 028 AK2.02 20 1.00 B 21 036 AK2.01 21 1.00 D 22 037AK3.05 222 1.00 C 23 051 AA2.02 223 1.00 C 24 060AA2.0.3 24 1.00 C 25 068 AA1.12 125 1.00 A 26 024 AK3.01 26 1.00 B 27 W/E09 EK1.2 327 1.00 A 28 003A2.02 28 1.00 A 29 003 K6.02 29 1.00 C 30 004 A3.09 230 1.00 B 31 005K5.02 131 1.00 C 32 006 G2.4.9 332 1.00 B 33 007 A1.03 133 1.00 B 34 008 A1.02 134 1.00 B 35 008 K2.02 135 1.00 C 36 010 K6.01 36 1.00 C 37 010G2.1.23 337 1.00 D 38 012A4.04 38 1.00 D 39 012K4.08 139 1.00 B 40 013 A4.01 40 1.00 B 41 022 A4.04 141 1.00 D 42 025 K5.02 42 1.00 A 43 026 K3.02 143 1.00 C 44 039G2.2.44 844 1.00 A 45 059 K4.08 345 1.00 C 46 061 K2.01 46 1.00 A 47 062 A3.05 47 1.00 D 48 062 K1.02 48 1.00 C

Answers

  1. ID Points 0 49 063 A2.01 149 1.00 C 50 064 A3.07 50 1.00 C 51 064 K6.08 151 1.00 A 52 073K4.01 52 1.00 C 53 076 K1.19 53 1.00 B 54 078K3.02 154 1.00 D 55 103 K1.02 155 1.00 D 56 002K1.07 556 1.00 A 57 011K5.13 57 1.00 A 58 014K3.02 158 1.00 B 59 086 K4.03 59 1.00 C 60 027 K2.01 60 1.00 C 61 029 A3.01 161 1.00 D 62 033A1.02 162 1.00 A 63 041K6.03 163 1.00 C 64 068 A2.02 64 1.00 C 65 079 A4.01 65 1.00 A 66 G2.1.25 66 1.00 C 67 G2.1.31 367 1.00 C 68 G2.2.4 168 1.00 A 69 G2.2.20 469 1.00 C 70 G2.2.38 270 1.00 B 71 G2.3.4 71 1.00 D 72 G2.3.13 172 1.00 D 73 G2.4.1 173 1.00 A 74 G2.4.17 474 1.00 A 75 G2.4.20 75 1.00 D SECTION 1 ( 75 items) 75.00