ML22322A107
| ML22322A107 | |
| Person / Time | |
|---|---|
| Site: | Sequoyah |
| Issue date: | 11/18/2022 |
| From: | Tom Stephen Division of Reactor Safety II |
| To: | Garner G Tennessee Valley Authority |
| References | |
| 50-327/23-301, 50-328/23-301 | |
| Download: ML22322A107 (4) | |
Text
November 18, 2022 Tennessee Valley Authority ATTN: Mr. Gary Garner Training Manager Sequoyah Nuclear Plant P. O. Box 2000 Soddy-Daisy, TN 37384-2000
SUBJECT:
SEQUOYAH NUCLEAR PLANT - NOTIFICATION OF LICENSED OPERATOR RETAKE INITIAL EXAMINATION 05000327/2023301 AND 05000328/2023301
Dear Mr. Garner:
During a telephone conversation on November 17, 2022, between Mr. A. Forsha, Lead Operations Instructor, and Mr. J. Viera, Senior Operations Engineer, arrangements were made for the administration of a retake operator licensing examination at the Sequoyah Nuclear Plant.
Administration of the written examination is scheduled for the week of March 13, 2023.
As agreed during the telephone conversation, your staff will prepare the written examination based on the guidelines in Revision 12 of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The NRCs regional office will discuss with your staff any changes that might be necessary before the examinations are administered.
The written examination outline was provided to your staff on November 15, 2022. The written examination and supporting reference material identified in NUREG-1021, Examination Standard (ES)-2.1, Preparing for Operator Licensing Initial Examinations, will be due by January 20, 2023. Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 55.40(b)(3), an authorized representative of the facility licensee shall approve the examination before it is submitted to the NRC for review and approval. All materials shall be complete and ready to use. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required materials, or the submittal of inadequate or incomplete materials, may cause the examination to be cancelled or rescheduled.
To conduct the requested written examination, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-4.3, Administering Written Examinations.
ES-1.2, Guidelines for Taking NRC Examinations, contains a number of NRC guidelines for the written examinations and operating tests as they are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver or excusal requests (if any) (Office of Management
G. Garner 2
and Budget (OMB) control number 3150-0090) at least 60 days before the first examination date (if possible). Contact Mr. Viera to determine the method for submission of the waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB control number 3150-0090) and medical certifications (OMB control number 3150-0024) should be submitted at least 30 days before the first examination date. If the NRC does not receive the preliminary applications at least 30 days before the examination date, a postponement may be necessary. Final, signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.
Although the guidelines for waiver or excusal requests call for their receipt at least 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early as possible in the process (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the facility licensee to the NRC are not binding. Submittals addressing waivers or excusals, or both, should be in writing (i.e.,
using NRC Form 398, Personal Qualifications StatementLicensee, or as directed by Mr.
Viera when contacting him to determine the method for submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.
Paperwork Reduction Act Statement This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the OMB, approval number 3150-0018.
The burden to the public for these voluntary information collections is estimated to average 2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination or response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. Send comments regarding this information collection to the FOIA, Library, and Information Collections Branch (T6-A10M), U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the OMB reviewer at: OMB Office of Information and Regulatory Affairs (3150-0018), Attn:
Desk Officer for the Nuclear Regulatory Commission, 725 17th Street, NW Washington, DC 20503; e-mail: oira_submission@omb.eop.gov.
Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information, unless the document requesting or requiring the collection displays a currently valid OMB control number.
In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, a copy of this letter and its enclosures will be available electronically for public inspection through the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible on the NRCs Web site at http://www.nrc.gov/reading-rm/adams.html.
G. Garner 3
Thank you for your cooperation in this matter. Mr. Forsha has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Viera at (404) 997-4643, (Internet E-mail:
Joseph.Viera@nrc.gov ), or me at (404) 997-4703, (Internet E-mail:
Thomas.Stephen@nrc.gov).
Sincerely,
/RA/
Thomas Stephen, Chief Operations Branch 1 Division of Reactor Safety Docket Nos.: 50-327, 50-328 License Nos.: DPR-77, DPR-7
G. Garner 4
SUBJECT:
SEQUOYAH NUCLEAR PLANT - NOTIFICATION OF LICENSED OPERATOR RETAKE INITIAL EXAMINATION 05000327/2023301 AND 05000328/2023301 dated November 18, 2022
- See previous page for concurrence PUBLICLY AVAILABLE NON-PUBLICLY AVAILABLE SENSITIVE NON-SENSITIVE ADAMS:
Yes ACCESSION NUMBER ML22322A107 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII/DRS/OB RII/DRS/OB RII/DRS/OB NAME D Egelstad J. Viera T. Stephen DATE 11/ 17 /2022 11/17/2022 11/18 /2022 DOCUMENT NAME: 2023-301 Sequoyah Retake Corporate Notification Letter.docx