ML19329F536

From kanterella
Revision as of 19:12, 31 January 2020 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Nonconformance Rept 11 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Oct-Dec 1975.Resumes of Bechtel Corp & Util Engineers Encl
ML19329F536
Person / Time
Site: Midland
Issue date: 12/31/1975
From:
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
Shared Package
ML19329F531 List:
References
NUDOCS 8006300735
Download: ML19329F536 (9)


Text

.

. ... Con:ua ra Pow:r Comp:ny Rrport #11, S:ptember 30, 1975

[ Pursuant to Conditions 2 F.B. and 2 F.C. of Construction Permits CPPR-81 and CPPR-82, I d the following report covers the period October 1 - December 31, 1975.

A. Construction work to be performed during the period:

OCTOBER 1975 Facility: AUXILIARY BUILDING

1. Continue the installation of structural steel for the elevated slab at elavation 614'.
2. Continue the installation of formwork, decking, embedded

, metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe and embedded process pipe for the building elevated slab at elevation 614' and fuel pool slab at elevation 618'.

3. Complete the installation of mud-mat concrete, waterproof membrane and wear slab concrete for the slab-on-grade at elevation 614'.
4. Start the installation of formwork, reinforcing steel, electrical conduit, grounding cable and embedded drain

,, piping for the slab-on-Grade at elevation 614'.

\

(

t is Facility: CONTAINMENT BUILDING #2

1. Continue the alignment, tack-weld, production welding I and leakchase installation for the dome liner plate I sections.
2. Begin the repair and final coating of the in-place con-tainment liner plate from elevation 593 ' to elevation 673 '.
3. Resume the installation of formwork, reinforcing steel and the placement of concrete for the buttress tendon service shafts and the tendon gallery access shaft above l elevation 612'.,

Facility: CONTAINMENT BUILDING #1

1. Continue the installation of leakchase on the in place containment liner plate from elevation 633' to elevation 671'.
2. Resume the alignment, tack-weld, production velding and n leakchase installation for the elevation 673' to elevation K j 753' containment liner plate assembly panels.

800630073g

. m

.2 ,

)~ . Facility: TURBINE BUILDING #2 j ( j

1. See Subcontracts. All other construction activitics temporarily suspended to meet cash flow limitations.

Facility: TURBINE BUILDING #1 ,

1. All construction activities temporarily suspended to meet cash flow limitations.

Facility:, YARD STRUCTURES & IMPROVEMEITIS

. 1. See Subcontracts. All other construction activities temporarily suspended to meet cash flow limitations.

SUBCONTRACTS

- 1. Continue the installation of waterproof membrane for Auxiliary Building and Containment Building #1.

2. Complete the placement of site backfill around the gss north portions of the Auxiliary Building and Contain-(( _

,) ment Buildings 60 elevacion 606*.

3. Continue placement of backfill for cooling pond dike construction.
4. Continue the site assembly and start installation of Auxiliary Building field erected tankage (B.R.S.

Receiver Tanks, L.W.S. Receiver Tanks and L.W.S.

Monitor Tanks).

5. Continue installation of Class A warehouse superstructure and HVAC equipment.

NOVEMBER 1975 Facility: AUXILIARY BUILDING

1. Complete the installation of structural steel for the elevated slab at elevation 614'.
2. Continue the installation of'formwork, decking, embedded

- metal, reinf,rcing steel, electrical conduit, grounding l l (/s cable, sleeves, embedded drain pipe and embedded process

( ,) pipe for the building elevated slab at elevation 614' and the fuel pool above elevation 618'.

3 . -l

.  ;

~ ~'T 3. Continue the installation of formwork, reinforcing 1

( [m /

\ steel, electrical conduit, grounding cable and embedded I drain piping for the slab-on-grade at elevation 614'.

4. Continue the placement of concrete for the elevated slab at elevation 614'. Slab-on-grade at elevation 614' and the fuel pool above elevation 618'. ,

' Facility: CONTAINMENT BUILDING #2

1. Continue the alignment, tack-weld, production welding and Icakchase installation for the dome liner plate sections.
2. Complete the repair and final coating of the in-place containment liner plate from elevation 593' to elevation 673'. .
3. Continue the installation of formwork, reinforcing steel and the placement of concrete for the buttress tendon service shafts and the tendon gallery access shaft above elevation 612'.
4. Start installation of the Equipment Hatch penetration t' lowet sectivu.

Facility: CONTAIN%fENT BUILDING #1

1. Complete the installation of leakchase on the in-place containment liner plate from elevation 633' to elevation 671'.
2. Continue the alignment, tack-weld, production welding and leakchase installation for the elevation 673' to elevation 753' containment liner plate assembly ' panels.

Facility: TURBINE BUILDING #2

1. All construction activities temporarily suspended to meet cash flow limitations.

Facility: TURBINE BUILDING #1

1. All construction activities temporarily suspended to meet cash flow limitations.

(h'

\_

l

_ _ -- - - - , . . _ . , - - - . . ' - - -- . . ?

, .4 .

~

/'"s YARD STRUCTURES & IMPROVEENTS

{, {(./i Facility:

1. See Subcontracts. All other construction activities temporarily suspended to meet cash flow limitations.

SUBCONTRACTS ~ ,

1. Complete the site assembly and installation of Auxiliary Building field erected tankage (B.R.S.

Receiver Tanks, L.W.S. Receiver Tanks and L.W.S.

Monitor Tanks).

2. Complete. installation of. Class A warehouse and HVAC

. equipment.

DECEMBER 1975 Facility: AUXILIARY BUILDING

1. Complete the installation of formwork, decking, embedded metal, reinforcing steel, electrical conduit,

. grounding cable, sleeves, and embedded drain pipe for

>k(<-~s) the elevated sla'u at elevnLivi. 614'.

2. Continue the installation of formwork, decking, embedded metal, reinforcing steel and embedded process piping for the fuel pool to elevation 613't.
3. Complete the installation of formwork, embedded metal, reinforcing steel, electrical conduit, grounding cable and embedded drain pipe for the slab-on-grade at elevation 614' east of 5.3 column line.
4. Complete the placement of concrete for the elevated slab at elevation 614' and the slab-on-grade at elevation 614 '

east of 5.3 column line.

5. Continue the placement of concrete in the fuel pool area above elevation 618' .

Facility: CONTAINMENT BUIP ING #2

1. Continue the alignment, tack-weld, production welding and leakahase installation for the dome liner plate sections.
2. Complete the installation of formwork, reinforcing steel k/~S
s. ) and the placement of concrete for the buttress tendon service shafts and the tendon gallery access shaft to elevation 634'.

m ~

, 5

  • 7% 3. Complete installation of the Equipment Hatch penetration

( )

lower section. -

Facility: CONTAINMENT BUILDING #1

1. Continue the alignment, tack-weld, production welding and leakchase installation for the elevation 673' to elevation 753' containment liner plate assembly panels.

Facility: TURBINE BUILDING #2

. 4

1. All construction activities temporarily suspended to meet cash flow limitations.

Facility:' TURBINE BUILDING #1

1. All construction activities temporarily suspended to meet cash flow limitations.

Facility: YARD STRUCTURES & IMPROVEMENTS

(( N

l. All construction activities temporarily suspended to meet cash flow limitations.

SUBCONTRACTS

1. No activity.

B. Supervisors and engineers of the applicant and architect-engineer with quality related-duties who are expected to be onsite during the period October 1 -

December 31, 1975 in addition to those identified in previous reports:

. 1. Consumers Power Company FMSouthworth Director of Project Quality Assurance Services s

2. Bechtel Power Corporation

'DL0sborn- Quality Control Engineer (Civil)

.RCBennett Quality Control Engineer (Civil)

3. U.S. Testing lh x No change from last report.

k, -

.. 6'

- (-( C. Quality Assurance qualifications of supervisors and engineers with site-related duties during the period October 1 - December 31, 1975:

Statements of qualifications of individuals listed in "B" above are attached hereto.

D. . Changes Consumers Power Company FMSouthworth has replaced GSKeeley as Director of Project Quality Assurance Services. Mr. Keeley has become Midland Project Manager replacing WEKessler.

Further additions or deletions to the list of people with quality-related duties who are to be onsite during the period October 1 - December .31,1975 will be noted on the next report.

O t

j i

l l

i

(~--) ,

1

L. . _ __

= d

EDUCATIONAL & PR,0FESSIONAL QUALIFICATIONS & EXPERIENCE

  • Fred M. Southworth l ((_ >
1. My name is Fred M. Southworth and I presently reside at 2317 DeLange Dr. S.E., Grand Rapids, Michigan 49506.
2. Education Monroe High School graduate - 1938, Monroe, Michigan.

BSME - 1942, Michigan State College.

3. Achieved P.E. status - 1954.
4. Work Experience Sequence

- Babcock & Wilcox Co. - Cadet Engineer - June 1942 to June 1943 -

Service and erection exposure; propositions and contracts at New York offices; shop exposure at Barberton, Ohio

- U.S. Navy Ensign - Bureau of Aeronautic - Assembly and Repair Shops at U.S. Navy 14, Barbers Point Oahu, T.H.; Lockheed - Vega Shops;

. Cal. Tech. Pasadena -- June 1943 to March 1946.

Discharged as Lt. (j g) .

- Commercial Printing (f amily business), Monroe, Mich. -- Nov 1946 to Nov 1947

- Kelsey Hayes Wheel Co. , Plant Engineering, Power Plant Services at

' [)

\~ / Monroe, Mich. -- Nov 1947 to Feb 1949.

- Consumers Power Co. -- Feb 1949 to present:

J. C. Weadock Plant - Lab Analyst, Efficiency Group -- Feb 1949 to Jan 1953; Gen. Office - Jackson - Gen. Engineer, varied experience assignments -

Jan 1953 to July 1954; B. C. Cobb Plant - Gen. Engineer, Engineering and supervisory assignments -

July 1954 to Oct 1958; B. C. Cobb Plant - Asst. Plant Supt., Muskegon, Mich-- Oct 1958 to July 1962; Eastern Region - Asst. Supt., Seginaw, Mich. --

July 1962 to Feb 1965; Southern Region - Asst. Supt., Battle Creek, Mich. --

Feb 1965 to Feb 1967; Western Region - Supt., Grand Rapids, Mich. --

Feb 1967 to Aug 1975; Gen. Office - Jackson - Director, Project Quality Assurance Services -

Aug 1975 to present.

5. Member Grand Rapids Engineers Club.

Phi Lambda Tau - An MSU local Engineering Honorary Group.

1 kr 1 0-l 9/23/75 i

--- . .4,.

. - - . - , , .~w-., -- . -.r.------- - A---~-- +

...~

Rodney C. Bennett Quality Control Civil Engineer Bechtel Power Corp.

Education: High School Graduate.

2.5 Days cement and concrete seminar at Aetna Cement Company, Essexville, Michigan Experience: 3 Years in QC on D. E. Karn Plant Units 3 & 4 for Townsend an,d Bottum.

Fave performed concrete placement, structural steel, and civil related inspection.

In addition to civil inspection have also performed ual ding and =chani cal inspection.

s

$. -w g _ , . . _ _ .

', .- Bechtel PowerCorporation m

(w.1 m

)

Daryle L. Osborn Quality Control Engineer Civil Discipline Bechtel Power Corporation Mr. Osborn graduated from the University of Toledo with a Bachelor's of Science Pagree in Civil Engineering.

Mr. Osborn worked for 3.5 yearc for Testing Service Corp. in the Chicago, Illinois area. IIe was the Quality Control Engineer on numerous projects inspecting the concrete, soils, end steel work operations. lle was a Soils Engineer directing soil e,xploration programs and some report writing.

Mr. Osborn worked for one year in the San Francisco Home Office of Bechtel Power Corp. in the Construction / Quality Control Department. llis work in-cluded the writing of Master Inspection Plans developed from Project Specifications and Recognized Standards (ASTM, ACI, etc) and the review of Engineering Documents.

N_)

e

/

<  ;

P

. .._,m,- - . . . _ _ . - _ _ - - . . - - - - - ~ - - - - - '~ ~ ~ - ~ ~ - - -