Nonconformance Rept 9 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Apr-June 1975,based on Preliminary Schedule of Activities to Be Performed During 1975
ML19329F488
Person / Time
Site: Midland
Issue date: 06/30/1975
From:
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
Shared Package
ML19329F486 List:
References
NUDOCS 8006300694
Download: ML19329F488 (6)


Text

u 3

y O .

, Consumers Power Company Report #9, March 31. 1975 g- Pursuant to Conditions 2 F.B. and 2 F.C. of Construction Permits CPPR-81 O

( and CPPR-82, the following report covers the period April 1,1975 - June 30,1975.

A. Construction work to be performed during the period (based on the preliminary schedule of activities to be performed during 1975)

APRIL 1975 Facility: AUXILIARY BUILDING

1. Continue the installation of formwork, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe, and embedded process pipe for the walls from elevation 599' to elevation 614'.
2. Continue concrete placement for the walls from eleva-tion 599' to elevation 614'.
3. Start the installation of structural steel for the fuel pool slabs at elevation 612' and 618' and the building slab at elevation 614'.

Facility: CONTAINMENT BUILDING #2

1. Continue the installation of formwork and reinforcing steel for the exterior wa' t buttress tendon service shaft walls to elevation 612'.

Facility: CONTAINMENT BUILDING #1

1. Complete the welding of vertical panel seams of the containment liner plate to elevation 672'.
2. Complete the installation of leakchase channels on the containment liner plate panel welds to elevation 644' minimum.
3. Complete the installation of formwork, reinforcing steel, post-tensioning embedments, and concrete placement for the containment exterior wall to elevation 612'-1".
4. Continue the installation of reinforcing steel and post-tensioning embedments for the exterior wall to elevation 632'-5".
5. Start the installation of formwork and reinforcing steel .

for the exterior wall buttress tendon service shaft base slabs.

Facility: TURBINE BUILDING #2

(_. 1. All activities temporarily suspended by rescheduling to meet cash flow limitations.

800830969'

O .

. O C:n umero Pow;r Comprny 2 Rep, ort #9, March 31, 1975 APRIL 1975 (Contd)

Facility: TURBINE Bt'ILDING #1

1. All activities temporarily suspended by rescheduling to meet cash flow limitations.

Facility: YARD STRUCTURES & IMPROVEMENTS

1. All activities temporarily suspended by rescheduling to meet cash flow limitations.

SUBCONTRACTS

1. Continue installation of waterproof membrane for Con-tainment #1 and Auxiliary Building.

MAY 1975 Facility: AUXILIARY BUILDING

1. Continue the installation of formwork, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe and embedded process pipe

, for the valls from elevation 599' to elevation 614'.

2. Continue concrete placement for the walls from eleva-tion 599' to elevation 614'. ,
3. Complete installation of structural steel for the fuel pool slab at elevation 612'; continue installation of structural steel for the fuel pool slab at elevation l 618' and the building slab at elevation 614'.
4. Start the installation of formwork, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe and embedded process pipe for the fuel pool slab at elevation 612' and the build-j ing alab at elevation 614'.

Facility: CONTAINMENT BUILDING #2 l

J

1. Continue the installation of formwork and reinforcing I steel for the exterior vall buttress tendon service shaft valla to elevation 612'.

l

'lacility: - CONTAINMENT BUILDING #1 l

1. Continue the installation of formwork, reinforcing steel, and post-tensioning embedments for the containment ex- l I

% terior vall to elevation 632'-5". l l

1- l

. l

O .

. O C:n um ra Pow:r Comp:nr 3 Report #9, March 31, 1975 MAY 1975 c

Facility: CONTAINMENT BUILDING #1 (Contd)

,2. Complete the installation of formwork, reinforcing steel, and concrete placement for the exterior vall buttress tendon service shaft base slabs.

Facility: _ TURBINE BUILDING #2

1. All activities temporarily suspended by rescheduling to meet cash flow limitations.

Facility: TURBINE BUILDING #1

1. All activities temporarily suspended by rescheduling to meet cash flow limitations.

Facility: _ YARD STRUCTURES & IMPROVEMENTS

1. All activities temporarily suspended by rescheduling to meet cash flow limitations.

SUBCONTRACTS

1. Continue installation of waterproof membrane for Con-tainment #1, Containment #2, and Auxiliary Building.
2. Start the site fabrication and installation of Auxiliary Building field erected tankage (B.R.S. Receiver Tanks,

' ' L.W.S. Receiver Tanks, and L.W.S. Monitor Tank) .

JUNE 1975 l

Facility: AUXILIARY BUILDING l

1. Complete the installation of formwork, embedded metals, reinforcing steel. electrical conduit, grounding cable, sleeves, embedded drain pipe, and embedded process pipe for the walls from elevation 599' to elevation 614'.
2. Complete the concrete placement for the valls from eleva- l tion 599' to elevation 614'. l
3. Continue the installation of structural steel for the fuel pool slab at elevation 618' and the building slab at l elevation 614'.

1

4. Complete the installation of formwork, embedded metals, reinforcing steel, electrical conduit, grounding cable, embedded drain pipe, embedded process pipe, and concrete b placement for the fuel pool slab at elevation 612'.

9

h Consumers Power Company 4 Report #9, March 31, 1975 JUNE 1975 Facility: AUXILIARY BUILDING (Contd)

5. Continue the installation of formwork, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, and embedded drain pipe for the building slab at elevation 614'. -
6. Start concrete placement for the building slab at eleva-tion 614'.

Facility: CONTAINMENT BUILDING #2

1. Complete the installation of formwork, reinforcing steel, and concrete placement for the exterior wall buttress tendon service shaft valls to elevation 612'.

Facility: CONTAINMENT BUILDING #1

1. Complete the installation of formwork, reinforcing steel, and concrete placement for the containment exterior wall to elevation 622'-3". -
2. Continue the installation of formwork, reinforcing steel and post-tensioning embedments for the containment ex-terior wall to elevation 632'-5".
3. Start the installation of formwork, reinforcing steel, and concrete placement for the exterior wall buttress tendon service shaft valls.

Facility: TURBINE BUILDING #2

1. All activities temporarily suspended by rescheduling to meet cash flow limitations. i Facility: TURBINE BUILDING #1 ,
1. All activities temporarily suspended by rescheduling to meet cash flow limitations.

Facility: YARD STRUCTURES & IMPROVEMENTS t

1. All activities temporarily suspended by reccheduling ( '

to meet cash flow limitations.

SUBCONTRACTS

1. Continue installation of waterproof membrane for Con-t, tainment #1, Containment #2, and Auxiliary Building.

'\_

4

O .

. O '

Con:u rra Power Company 5 Report f9, March 31, 1975 JUNE 1975

$UBCONTRACTS (Contd)

2. Continue the site fabrication and installation of .

Auxiliary Building field erected tankage (B.R.S. &

L.W.S. Receiving & Monitor Tanks).

3. Start placement of plant site backfill against Con- -

tainment #1, Containment #2, and Auxiliary Building.

B. Supervisors and Engineers of the Applicant and Architect Engineer with quality related duties who are expected to be on the site during the period April 1 -

June 30. 1975 in addition to those identified in previous reports:

1. Consumers Power Company No additions to last report.
2. Bechtel Power Corporation No additions to last report.
3. U.S. Testing No change from last report.

C. Quality assurance qualifications of supervisors and engineers with site related duties during the period April 1 - June 30, 1975:

Statements of qualifications of all individuals in "B" have been previously submitted. ,

D. Changes The following individuals with quality related duties listed in previous reports are no longer associated with this site:

1. Consumers Power Company No change from last report.
2. Bechtel Power Corporation (due to the' slowdown at the site)

J. C. Aldridge K. O. Anderson H.'L. Boleen R. C. Boothe

< B. W. Breland.

k P. T. Carpenter H. D. Crowe

O . 3 Cogsumers Power Company 6 Report #9, March 31, 1975 Changes (Contd)

O

{ D.

2. Bechtel Power Corporation (due to the slowdown at the site)

H. G. Domschke G. A. Durkee J. C. Fitzgerald H. D. Foster J. F. Gibson C. A. Harris M. W. Hopfenspirger ,

L. J. Johnson l J. J. Lancon i R. G. Lussier I E. J. Manning l N. V. Plante l S. E. Tucker R. E. Uhouse C. C. Williams Further additions or deletions to the list of people who are to be on site during the period April 1 - June 30,1975 will be noted on the next report.