|
---|
Category:ARCHIVE RECORDS
MONTHYEARML20081J6641983-06-29029 June 1983 News Articles Discussing Facility Const Completion Dates ML20081G1011983-06-0808 June 1983 Slide Presentation Entitled, Overview of Midland Independent Design & Const Verification Program, Presented to P Keshishian & G Gower ML20151H3771983-04-22022 April 1983 Record of 830331 Telephone Discussion Re Use of Appropriate ASME Code.Util Proposes to Use App F of 1980 ASME Code for Qualification of Pressurizer Support Lugs Rather than 1968 ASME Code Used for All Other Components ML20079R2391983-03-14014 March 1983 Press Release Discussing Pier 9 Excavation,Divers Working in Pond,Welder Certification Program,Circulating Water Pump Motors Testing,Cable Reinsp & Work Support Evaporator Testing ML20080E6751983-02-24024 February 1983 News Article, Wrongful Discharge Suit Names Consumers, Zack ML20081J7671982-12-28028 December 1982 News Articles Entitled, Test of Emergency Plans at Nuclear Plant Postponed & More Delays Mark Yr for Nuclear Plant Project ML20235B7191982-09-10010 September 1982 Partially Deleted Nonconformance Rept of Welding at Plant. Socket Welds Found to Be Below Listed Requirements Should Be Processed in Listed Manner ML20081J8251982-08-19019 August 1982 Midland Review, Vol 1,Number 39.Supporting Documentation Encl ML20094H4851982-07-13013 July 1982 Audit Rept M01-602-2 Re Audit Conducted at Zack Co on 820517-20 ML20094H4901982-05-14014 May 1982 Audit Rept M0-601-2 Re Audit Conducted of Zack Co on 820419- 22 to Verify Zack Co Compliance W/Program Requirements as Defined in Zack QA Manual,Plant QC Procedures & Weld Procedure Specs.Related Info Encl ML20126L9691981-05-18018 May 1981 Telcon on 810518 W/Util & Vendor Re Permanent Plant Dewatering ML20004E0361981-04-30030 April 1981 Selected Viewgraphs from 810430 Meeting ML20004F2481981-04-15015 April 1981 Slide Presentation Entitled Fire Protection Design. ML19347D0271981-03-0505 March 1981 Slide Presentation Re Final Design Review Presentation at 810326 Meeting of Util Design Review Board.Responses to NRC Questions Encl ML20062K9881980-12-0505 December 1980 Viewgraphs Presented at 801205 Meeting ML19345B7121980-10-29029 October 1980 Slide Presentation for 801029 Meeting Re Operator Training & Qualification ML19351G2371980-08-29029 August 1980 Slide Presentation for 800829 Meeting in Midland,Mi Re Request for Relief from NRC Position Requiring Addl Borings & Tests of Plant Fill ML20125B8061979-11-15015 November 1979 Audit on 791105-15 of Small Pipe Design & Stress Groups, Including QA Findings.Qa Requests,Mgt Corrective Action Repts,Nonconformance Repts & Other Supporting Documentation Encl ML19252A0371979-09-25025 September 1979 Nonconformance Rept for Aug 1979.Rept Consists of Bechtel Nonconformance Repts & Log,Status Book,Qa Discrepancy Repts, Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19263C7611979-02-22022 February 1979 Monthly Nonconformance Rept for Jan 1979 ML20197D3691978-11-22022 November 1978 Nonconformance Rept for Oct 1978.Rept Consists of Bechtel Nonconformance Repts & Log,Status Book,Qa Discrepancy Repts, Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329G3461978-10-25025 October 1978 Nonconformance Rept for Sept 1978 Consisting of Nonconformance Rept Log on Open Items,Quality Action Requests,B&W Repts of Nonconformity & Util Nonconformance Repts Written or Closed During Month ML19331A2621978-07-31031 July 1978 Nonconformance Rept for Jul 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F0551978-06-30030 June 1978 Nonconformance Rept for June 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F0221978-05-31031 May 1978 Nonconformance Rept for May 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E8831978-04-30030 April 1978 Nonconformance Rept for Apr 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19331A2291978-03-31031 March 1978 Nonconformance Rept for Mar 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F1901978-02-28028 February 1978 Nonconformance Rept for Feb 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F1891978-01-31031 January 1978 Nonconformance Rept for Jan 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19331A2141977-12-31031 December 1977 Nonconformance Rept for Dec 1977.rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19331A2421977-12-31031 December 1977 Nonconformance Rept for Dec 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5211977-12-31031 December 1977 Nonconformance Rept 19 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Oct-Dec 1977.Resumes of Bechtel Corp & Util Engineers Encl ML19329E8871977-11-30030 November 1977 Nonconformance Rept for Nov 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F0311977-10-31031 October 1977 Nonconformance Rept for Oct 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformane Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings Mgt Corrective Action Repts Written or Closed During Month ML19329F0181977-09-30030 September 1977 Nonconformance Rept for Sept 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5491977-09-30030 September 1977 Nonconformance Rept 18 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Jul-Sept 1977.Resumes of Bechtel Corp & Util Engineers Encl ML19329E9401977-08-31031 August 1977 Nonconformance Rept for Aug 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19331A2331977-07-31031 July 1977 Nonconformance Rept for Jul 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5091977-06-30030 June 1977 Nonconformance Rept 17 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Apr-June 1977. Resumes of Bechtel Corp & Util Engineers Encl ML19329E8801977-05-31031 May 1977 Nonconformance Rept for May 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19331A2631977-04-30030 April 1977 Nonconformance Rept for Mar & Apr 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book,Qa Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Months ML19329F5621977-03-31031 March 1977 Nonconformance Rept 16 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Jan - Mar 1977.Resumes of Bechtel Corp & Util Engineers Encl ML19331A2281977-02-28028 February 1977 Nonconformance Rept for Feb 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E9051977-01-31031 January 1977 Nonconformance Rept for Jan 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5571976-12-31031 December 1976 Nonconformance Rept 15 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Oct - Dec 1976.Resumes of Bechtel Corp & Util Engineers Encl ML19329E8851976-11-30030 November 1976 Nonconformance Rept for Nov 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E9201976-10-31031 October 1976 Nonconformance Rept for Oct 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Finding & Mgt Corrective Corrective Action Repts Written or Closed During Month ML19329E9921976-09-30030 September 1976 Nonconformance Rept for Sept 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5531976-09-30030 September 1976 Nonconformance Rept 14 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Jul - Sept 1976.Resumes of Bechtel Corp & Util Engineers Encl ML19329E9721976-08-31031 August 1976 Nonconformance Rept for Aug 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month 1983-06-08
[Table view] Category:LICENSEE INTERNAL NON-CONFORMANCE REPORT
MONTHYEARML19252A0371979-09-25025 September 1979 Nonconformance Rept for Aug 1979.Rept Consists of Bechtel Nonconformance Repts & Log,Status Book,Qa Discrepancy Repts, Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19263C7611979-02-22022 February 1979 Monthly Nonconformance Rept for Jan 1979 ML20197D3691978-11-22022 November 1978 Nonconformance Rept for Oct 1978.Rept Consists of Bechtel Nonconformance Repts & Log,Status Book,Qa Discrepancy Repts, Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329G3461978-10-25025 October 1978 Nonconformance Rept for Sept 1978 Consisting of Nonconformance Rept Log on Open Items,Quality Action Requests,B&W Repts of Nonconformity & Util Nonconformance Repts Written or Closed During Month ML19331A2621978-07-31031 July 1978 Nonconformance Rept for Jul 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F0551978-06-30030 June 1978 Nonconformance Rept for June 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F0221978-05-31031 May 1978 Nonconformance Rept for May 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E8831978-04-30030 April 1978 Nonconformance Rept for Apr 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19331A2291978-03-31031 March 1978 Nonconformance Rept for Mar 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F1901978-02-28028 February 1978 Nonconformance Rept for Feb 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F1891978-01-31031 January 1978 Nonconformance Rept for Jan 1978.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19331A2421977-12-31031 December 1977 Nonconformance Rept for Dec 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5211977-12-31031 December 1977 Nonconformance Rept 19 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Oct-Dec 1977.Resumes of Bechtel Corp & Util Engineers Encl ML19331A2141977-12-31031 December 1977 Nonconformance Rept for Dec 1977.rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E8871977-11-30030 November 1977 Nonconformance Rept for Nov 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F0311977-10-31031 October 1977 Nonconformance Rept for Oct 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformane Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings Mgt Corrective Action Repts Written or Closed During Month ML19329F5491977-09-30030 September 1977 Nonconformance Rept 18 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Jul-Sept 1977.Resumes of Bechtel Corp & Util Engineers Encl ML19329F0181977-09-30030 September 1977 Nonconformance Rept for Sept 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E9401977-08-31031 August 1977 Nonconformance Rept for Aug 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19331A2331977-07-31031 July 1977 Nonconformance Rept for Jul 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5091977-06-30030 June 1977 Nonconformance Rept 17 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Apr-June 1977. Resumes of Bechtel Corp & Util Engineers Encl ML19329E8801977-05-31031 May 1977 Nonconformance Rept for May 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19331A2631977-04-30030 April 1977 Nonconformance Rept for Mar & Apr 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book,Qa Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Months ML19329F5621977-03-31031 March 1977 Nonconformance Rept 16 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Jan - Mar 1977.Resumes of Bechtel Corp & Util Engineers Encl ML19331A2281977-02-28028 February 1977 Nonconformance Rept for Feb 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E9051977-01-31031 January 1977 Nonconformance Rept for Jan 1977.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5571976-12-31031 December 1976 Nonconformance Rept 15 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Oct - Dec 1976.Resumes of Bechtel Corp & Util Engineers Encl ML19329E8851976-11-30030 November 1976 Nonconformance Rept for Nov 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E9201976-10-31031 October 1976 Nonconformance Rept for Oct 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Finding & Mgt Corrective Corrective Action Repts Written or Closed During Month ML19329E9921976-09-30030 September 1976 Nonconformance Rept for Sept 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5531976-09-30030 September 1976 Nonconformance Rept 14 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Jul - Sept 1976.Resumes of Bechtel Corp & Util Engineers Encl ML19329E9721976-08-31031 August 1976 Nonconformance Rept for Aug 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E9891976-07-31031 July 1976 Nonconformance Rept for Jul 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5451976-06-30030 June 1976 Nonconformance Rept 13 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Apr-June 1976 Resumes of Bechtel Corp & Util Engineers Encl ML19329E9151976-06-30030 June 1976 Nonconformance Rept for June 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E9391976-05-31031 May 1976 Nonconformance Rept for May 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E9271976-04-30030 April 1976 Nonconformance Rept for Apr 1976.Rept Consists of Bechtel Nonconformancee Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E8791976-03-31031 March 1976 Nonconformance Rept for Mar 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5461976-03-31031 March 1976 Nonconformance Rept 12 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Jan-Mar 1976.Resumes of Bechtel Corp & Util Engineers Encl ML19331A2231976-02-29029 February 1976 Nonconformance Rept for Feb 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E9211976-01-31031 January 1976 Nonconformance Rept for Jan 1976.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F5361975-12-31031 December 1975 Nonconformance Rept 11 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Oct-Dec 1975.Resumes of Bechtel Corp & Util Engineers Encl ML19329F0191975-10-31031 October 1975 Nonconformance Rept for Oct 1975.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F4941975-09-30030 September 1975 Nonconformance Rept 10 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Jul-Sept 1975.Resumes of Bechtel Corp & Util Engineers Encl ML19329E8661975-09-30030 September 1975 Nonconformance Rept for Sept 1975.Rept Consists of Bechtel Nonconformance Rept & Log,Status Book,Qa Discrepancy Repts, Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19320A4681975-08-31031 August 1975 Nonconformance Rept for Aug 1975.Rept Consists of Bechtel Nonconformance Repts & Log,Status Book,Qa Discrepancy Repts, Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E8991975-07-31031 July 1975 Nonconformance Rept for Jul 1975.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329F4881975-06-30030 June 1975 Nonconformance Rept 9 Per Condition 2 of CPPR-81 & CPPR-82 Re Const Work Performed During Apr-June 1975,based on Preliminary Schedule of Activities to Be Performed During 1975 ML19320A4731975-05-31031 May 1975 Nonconformance Rept for May 1975.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month ML19329E8981975-04-30030 April 1975 Nonconformance Rept for Apr 1975.Rept Consists of Bechtel Nonconformance Repts,Nonconformance Rept Log & Status Book, QA Discrepancy Repts,Quality Audit Findings & Mgt Corrective Action Repts Written or Closed During Month 1979-09-25
[Table view] |
Text
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
(}' C:nsumers Pow r Compar
- / R:psrt #10, Juns 30,19ss
, '{ *
~-) !
Pursuant to Conditions 2 F.B. and 2 F.C. of Construction Permits CPPR-81 and CPSR-8'2, the following report covers the period July 1 - September 30, 1975.
,s A. Construction work to be performed during the period.
JULY 1975 Facility: AUXILIARY BUILDING
- 1. Continue the installation of formwork, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe, and embedded process pipe for the walls from elevation 599' to elevation 614' .
- 2. Continue concrete placement for the walls from eleva-tion 599' to elevation 614'.
- 3. Continue the installation of structural steel for the fuel pool slabs at elevation 612' and 618' and the building elevated slab at elevation 614'.
- 4. Start the installation of for= work, decking embedded metals, reinforcing steel, electrical conduit, ground-ing cable, sleeves, embedded drain pipe and embedded process pipe for the fuel pool slabs at elevation 612' and 618' and the building elevated slab at elevation 614'.
- 5. Start the installation of structural backfill, under-ground electrical duct banks, grounding cable, and. mud mat concrete for the building slab-on-grade at eleva-tion 614 ' .- l l
Facility: CONTAIIDENT BUILDING #2 '
I
- 1. Continue the alignment, tack-veld, production welding, and leakchase installation for the dome liner plate sections.
Facility: CONTAI?DfE'TT BUILDING #1 -
- 1. Ccatinue the installation of reinforcing steel and post-tensioning embedments for the exterior wall to elevation 632'-5".
^
, 2. Continue the installation of formwork and reinforcing
(
~'
steel for the exterior wall buttress tendon service shaf ts and the tendon gallery access shaf t to eleva-tion 612'.
- 3. Continue concrete placement for the exterior wall buttress tendon service shafts and the tendon gallery access shaft to elevation 612'. i k
8006300703
. C,pr.umor$ Pow;rC'"cny ( -
l( f 2 R port #10, Juns 30, 1975 u : .
Facility: TURBINE BUILDING #2
- 1. All construction activities temporarily suspended to
. r. . meet cash flow limitations.
' Facility: TURBIPE BUILDING #1
- 1. All Construction activities temporarily suspended to meet cash flow limitations.
Facility: YARD STRUCTURES & IMPROVEMENTS
- 1. See Subcontracts. All other construction activities temporarily suspended to meet cash flow limitations.
SUBCONTRACTS
- 1. Continue the installation of waterproof membrane for Auxiliary Building, Containment #1, and Containment #2.
- 2. Continue the place =ent of site backfill around the north portions of the Auxiliary Building, Containment #1 and Containment #2 to elevation 610' maximum.
- 3. Start the installation of trackwork into the existing warehouse arha.
- 4. Start placement of ba ckfill materials for cooling pond dike construction.
- 5. Continue the site fabrication of Auxiliary Building field erected tankage (B.R.S. Receiver Tanks, L.W.S. Receiver Tanks, and L.W.S. Monitor Tank).
AUGUST 1975 Facility: AUXILIARY BUILDING
- 1. Continue the installation of formwork, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe, and embedded process pipe for the walls from elevation 599' to elevation 614'.
- 2. Continue concrete placement for the walls from elevation 599' to elevation 614'.
- 3. Complete the installation of structural steel for the fuel pool slabs at elevation 612' and 618' and the build-j ing elevated slab at elevation 614'. ll s-9 _
o ,.
. Q h:um;r,e P;wir C uny 3
R; port #10, Juna bd, 1975 i
- 4. Continue the installation of formwork, decking, embedded c, metals, reinforcing steel, cicetrical conduit, grounding
- ( cable, sleeves, embedded drain pipe, and embedded process pipe for the fuel pool slabs at elevation 612' and 618',
and the building elevated slab at elevation 614'.
- 5. Start concrete placement for the fuel pool slab at elevation 612' and the building elevated slab at eleva-tion 614'.
- 6. Continue the installation of structural backfill, under-ground electrical ductbahks, grounding cable, and mud mat concrete for the building slab-on-grade at elevation 614'.
Facility: CONTAINMENT BUILDING #2
- 1. Con'tinue the alignment, tack-veld, production welding, and leakchase installation for the doms liner plate sections.
- 2. Complete the installation of reinforcing steel, post-tensioning embedments, and formwork for the exterior wall to elevation 662'-11". ,
- 3. Complete the concrete placement for the exterior wall to elevation 662'-11".
- 4. Continue the installation of reinforcing steel, post-tensioning embedments, and formwork for the exterior 9
wall to elevation 673'-1". i Facility: CONTAINMENT BUILDING #1
- l. Complete the installation of reinforcing steel, post -
tensioning embedments and formwork for the exterior wall to elevation 632'-5".
- 2. Complete the concrete placement for the exterior wall to elevation 632'-5".
- 3. Complete the installation of formwork and reinforcing steel for the exterior vall buttress tendon service shafts and the tendon gallery access shaft to elevation 612'.
- 4. Complete concrete placement for the exterior wall buttress tendon service shafts and the tendon '
gallery access shaft to elevation 612'.
Facility: TURBINE LLILDING #2
- 1. All construction activities temporarily suspended to meet cash flow limitations.
h 4
e 4
, C~num;ra Power C nny . A 4
. R: port #10, Juni L',1975 V a
AUGUST 1975 (Contd) .
Facility: TURBINE BUILDING #1
( l. All construction activities temporarily suspended to meet cash flow limitations.
Facility: YARD STRUCTURES & IMPROVDfENTS
- 1. See Subcontracts. All other construction activities temporarily suspended to meet cash flow limitations. -
SUBCONTRACTS
- 1. Continue the installation of waterproof membrane for Auxiliary Building and Containment #1.
- 2. Continue the placement of site backfill around the north portions of the Auxiliary Building, Containment #1, and Containment #2 to elevation 610' maximum.
- 3. Continue the installation of trackwork into the existing warehouse area.
- 4. Continue placement of backfill materials for cooling pond dike construction. l
- 5. Continue the site fabrication of Auxiliary Build-ing field erected tankage (B.R.S. Receiver Tanks, L.W.S. Receiver Tanks, and L.U.S. Monitor Tanks). )
SEpTDiBER 1975 Facility: AUXILIARY BUILDING
- 1. Complete the installation of formwork, embedded metals, l reinforcing steel, electrical conduit, grounding cable, .
l sleeves, embedded drain pipe, and embedded process pipe I for the walls from elevation 599' to elevation 614 ' .
- 2. Complete concrete placement for the walls from elevation 599' to elevation 614'.
- 3. Continue the installation of structural steel for the elevated slab at elevation 614'.
- 4. Continue the installation of formwork, decking, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe, and embedded process pipe for the fuel pool slab at elevation 618' and the building elevated slab at elevation 614'.
C6;umer!a P:w:r C 'Iny - O 5 R: port #10, Junn 30', 1975 t
~
SEPTE5fBER 1975 (Contd)
- 5. Complete the installation of structural backfill and under-e' ground electrical ductbanks for the slab-on-grade at eleva-
-' tion 614'.
- 6. Continue the installation of mud mat concrete and start the installation of waterproof membrane and wear slab concrete for the slab-on-grade at elevation 614'.
Facility: CONTAIIDIENT EUILDING #2
- 1. Continue the alignment, tack-weld, production welding, and Icakchase installation for the dome liner plate sections.
- 2. Complete the installation of reinforcing steel, post-tensioning embedments, and formwork for the exterior wall to elevation 673'-1".
- 3. Complete the concrete placement for the exterior wall to elevation 673'-1".
Facility: CONTAIMIENT BUILDING #1
- 1. See Subcontracts. All other construction activities ;
temporarily suspended to meet cash flow limitations.
- ' Facility
- TURBINE BUILDING #2 O 1
- 1. All construction activities temporarily suspended to meet cash flow limitations.
Facility: -- TURBINE BUILDING-#1m---~~
- 1. All Construction activities temporarily suspended .
to meet cash flow limitations.
Facility: YARD STRUCTURES & IMPROVEMENTS
- 1. See Subcontracts. All other construction activities temporarily suspended to meet cash flow limitations.
SUBCONTRACTS ,
- 1. Continue the installation of waterproof membrane l
. for Auxiliary Building and Containment #1. l l
- 2. Continue the placement of site backfill around
( the north portions of the Auxiliary Building I
and Containment #1 to elevation 606'.
l( .
- 3. Complete the installation of trackwork into the l existing warehouse area.
' - Critumir's Powzr C'~nny
.. Rspert #10, Juna 'ad,1975 O 6 i
SUBCONTRACTS (Contd)
- 4. Continue placement of backfill materials for cooling pond dike construction.
- 5. Continue the site fabrication of Auxiliary Building field erected tankage (B.R.S. Receiver Tanks, L.W.S. Receiver Tanks, and L.W.S. Monitor Tanks).
B. Supervisors and engineers of the applicant and architect-engineer with quality-related duties who are expected to be on the site during the period July 1 -
September 30, 1975 in addition to those identified in previous reports:
- 1. Consumers Power Company No additions to last report.
- 2. Bechtel Power Corporation J. F. Newgen, Project Superintendent
- 3. U.S. Testing No change from last report.
C. Quclity assurance qualifications of supervisors and engineers with site-related duties during the period July 1 - September 30, 1975:
Statements of qualifications o,f individuals listed in "B" above are attached hereto.
D. Changes The following individuals with quality related duties listed in previous reports are no longer associated with this site:
- 1. Consumers Power Company M. E. N' Haem
- 2. Bechtel Power Corporation l W. J. Key ~~
R. E. Sevo E. E. Felton Further additions or deletions to the list of people with quality-related duties who are to be onsite during the period July 1 - Septe=ber 30, 1975 vill be noted on the next report.
t 4
w O
- c.. .
- c. .
O r.
kesume of Joel F. flewgen s
Bachelor of Science, Civil Engineering, Stariford University, 1961.
Master of Science, Civil Engineering, Construction Institute, Stanford University 1965.
Military: Officer in U. S. flavy, Active 1961 to 1964, currently UCDR US?! Reserve.
Assigned as Project Superintendent, February 1975 to date.
Previous positions include: Field Superintendent at Midland Project June 1973 to February 1975; Project Field Engineer, Palisades Project, October 1971 to June 1973; Asst. Project Field Engineer, Mechanical and QC, Point Beach Project, April 1970 to October 1971.
Total of ten years-experience with Bechtel on large power plants.
O
e e
5
- ^ . C;n um?.rrs Pow r Compan .
kd' Report #10 June 30,19)s>
Pursuant to Conditions 2 F.B. and 2 F.C. of Construction Permits CPPR-81 and'CPPR-82, the following report covers the period July 1 - September 30, 1975.
A. Construction work to be performed during the period.
JULY 1975 Facility: AUXILIARY BUILDING
- 1. Continue the installation of formwork, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe, and embedded process pipe for the walls f rom elevation 599' to elevation 614' . .
- 2. Continue concrete placement for the valls from eleva-tion 599' to elevation 614'.
- 3. Continue the installation of structural steel for the fuel pool slabs at elevation 612' and 618' and the building elevated slab at elevation 614'.
- 4. Start the installation of formwork, decking 2mbedded metals, reinforcing steel, electrical conduit, ground-
, ing cable, sleeves, embedded drain pipe and embedded
- process pipe for the fuel pool slabs at elevation 612' and 618' and the building elevated slab at elevation 614'.
- 5. Start the installation of structural backfill, under-ground electrical duct banks, grounding cable, and mud mat concrete for the building slab-on-grade at eleva-tion 614 ' . .
Facility: CONTAIIDENT BUILDING #2
- 1. Continue the alignment, tack-weld, production welding, and leakchase installation for the dome liner plate sections.
Facility: CONTAIt0ENT BUILDINC #1
- 1. Continue the installation of reinforcing steel and post-tensioning embedments for the exterior wall to elevation 632'-5".
- 2. Continue the installation of formwork and reinforcing steel for the exterior wall buttress tendon service shafts and the tendon gallery access shaft to eleva-tion 612'.
- 3. Continue concrete placement for the exterior wall buttress tendon service shafts and the tendon gallery access shaft to elevation 612'.
C:~
n sum;ri Pow;r Co^my . 2
. Ripor t #10, Juna 30,'1975 t
Facility: TURBINE BUILDING #2
- 1. All construction activities temporarily suspended to e' meet cash flow limitations.
r .
Facility: TURBINE BUILDING #1
- 1. All Construction activities temporarily suspended to meet cash flow limitations.
Facility: YARD STRUCTURES & IMPROVE >ENTS
- 1. See Subcontracts. All other construction activities temporarily suspended to meet cash flow limitations.
SUBCONTRACTS
- 1. Continue the installation of waterproof me=brane for Auxiliary Building, Containment #1, and Containment #2.
- 2. Continue the placement of site backfill around the north portions of the Auxiliary Building, Containment #1 and Containment #2 to elevation 610' maximum.
s
- 3. Start the installation of trackwork into the existing warehouse area lh
- 4. Start placement of ba ckfill materials for cooling pond dike construction. , _
- 5. Continue the site fabrication of Auxiliary Building field erected tankage (B.R.S. Receiver Tanks, L.W.S. Receiver Tanks,.and L.W.S. Monitor
AUGUST 1975 Facility: AUXILIARY BUILDING
- 1. Continue the installation of for= work, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe, and embedded process pipe for the walls from elevation 599' to elevation 614'. .
- 2. Continue concrete placement for the walls from elevation 599' to elevation 614 ' .
- 3. Complete the installation of structural steel for the fuel pool slabs at elevation 612' and 618' and the build-(, ing elevated slab at elevation 614'.
C.;1ysum:rd Pow;r Cc ny .
3
. Rcport #10, Juna 3b,' 1975 '
e AUGUST 1975 (Contd) -
- 4. Continue the installation of formwork, decking, embedded metals, reinforcing steel, electrical conduit, grounding s cable, sleeves, embedded drain pipe, and embedded process pipe for the fuel pool slabs at elevation 612' and 618',
and the building elevated slab at elevation 614'.
- 5. Start concrete placement for the fuel pool slab at elevation 612' and the building elevated slab at eleva-tion 614'.
- 6. Continue the installation of structural backfill, under-
- ground electrical ductbanks, grounding cable, and mud mat concrete for the building slab-on-grade at elevation 614'.
Facility: CONTAIN'4ENT BUILDING #2
- 1. Continue the alignment, tack-weld, production velding, and leakchase installation for the dome liner plate sections.
, 2. Cs ,plete the installation of reinforcing steel, post-ten.ioning embedments, and formwork for the exterior
, vall to elevation 662'-11".
- 3. Complete the concrete placement for the exterior wall to elevation 662'-11".
- 4. Continue the installation of reinforcing steel, post- I s tensioning embedments, and formwork for the exterior wall to elevation 673'-1".
Facility: CONTAIN>ENT BUILDING #1, -- - --
- 1. Complete the installation of' reinforcing steeli pose' ~
tensioning embedments and fortwork for the exterior wall to elevation 632'-5".
- 2. Complete the concrete placement for the exterior wall to elevation 632'-5".
- 3. Co=plete the installation of formwork and reinforcing steel for the exterior wall buttress tendon service shafts and the tendon gallery access shaft to elevation l 612'. l l
- 4. Conplete concrete placement for the exterior wall l
l buttress tendon service shafts and the tendon l gallery access sha"ft to elevation 612'.
Facility: TURBINE BUILDING #2
- 1. All construction activities temporarily suspend d to j
meet cash flow limitations.
U-1C n:um:;re$ Pcw:r Comny
\q 4
.. R: port #10, Jun; 3 s 1975 * /
s AUGUST 1975 (Contd)
Facility: TURBINE BUILDING #1
( l. All construction activities temporarily suspended to meet cash flow limitations.
Facility: YARD STRUCTURES & IMPROVEMENTS
- 1. See Subcontracts. All other construction activities temporarily suspended to meet cash flow limitations.
SUBC01TTRACTS
- 1. Continue the installation of waterproof membrane for Auxiliary Building and Containment #1.
. 2. Continue the placement of site backfill around the north portions of the Auxiliary Building, l Containment #1, and Containment #2 to elevation i 610' maximum.
- 3. Continue the installation of trackwork into the existing warehouse area.
- 4. Continue placement of backfill materials for cooling pond dike construction.
f
- 5. Continue the site fabrication of Auxiliary Build- 1 i
ing field erected tankage (B.R.S. Receiver Tanks, l L.W.S. Receiver Tanks, and L.W.S. Monitor Tanks). l l
SEPTEMBER 1975 Facility: AUXILIARY BUILDING
- 1. Complete the installation of formwork, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe, and embedded process pipe for the walls from elevation 599' to elevation 614'.
- 2. Complete concrete placement for the walls from elevation 599' to elevation 614'.
- 3. Continue the installation of structural steel for the elevated slab at elevation 614' . '
- 4. Continue the installation of f ormwork, decking, embedded metals, reinforcing steel, electrical conduit, grounding cable, sleeves, embedded drain pipe, and embedded process pipe for the fuel pool slab at elevation 618' and the l
building elevated slab at elevation 614'.
(_
b
. . . . n Cocn.um;rs Pcw;r Co ,ny . /~' 5
- R port #10, Junt 30',' 1975 s
. SEPTEMBER 1975 (Contd)
- 5. Complete the installation of structural backfill and under-ground electrical ductbanks for the slab-on-grade at eleva-h tion 614'.
- 6. Continue the installation of mud mat concrete and start the installation of waterproof membrane and wear slab concrete for the slab-on-grade at elevation 614'.
Facility: CONTAItaENT BUILDING #2
- 1. Continue the alignment, tack-weld, production welding, and leakchase installation for the dome liner plate sections.
- 2. Complete the installation of reinforcing steel, post-tensioning cabedments, and formwork for the exterior wall to elevation 573'al".
- 3. Complete the concrete placement for the exterior wall to elevation 673'-1".
l Facility: CONTAIIBENT BUILDING #1
- 1. See Subcontracts. All other construction activities temporarily suspended to meet cash flow limitations.
g s.
Facility: TURBINE EUILDINC #2 ~
l
- 1. All construction activities temporarily suspended to meet cash flow limitations.
Facility: TUP 3INE RUILDING #1
- 5. All Construction activities temporarily suspended to meet cash flow limitations.
Facility: _ YARD STRUCTURES & IMPROVEFENTS
- 1. See Subcontracts. All other construction activities 1
temporarily suspended to meet cash flow limitations. 1 SUBCONTRACTS l
- 1. Continue the installation of waterproof membrane I for Auxiliary Building and Containment #1. i 1
- 2. Continue the placement of site backfill around-the north portions of the Auxiliary Building and Containment #1 to elevation 606'.
l
(_, 3. Complete the installation of trackwork into the existing warehouse area.
Co'nsum;rs' Pow r Ce^tny 6 S RCport #10, Jun2 3u; 1975
.]
\--
s -
SEPTEMBER 1975 -
SUBCONTRACTS (Contd) r'
- 4. Continue placement of backfill materials for cooling pond dike construction.
- 5. Continue the site fabrication of Auxiliary Building field erected tankage (B.R.S. Receiver Tanks, L.W.S. Receiver Tanks, and L.W.S. Monitor Tanks).
B. Supervisors and engineers of the applicant and architect-engineer with quality- ,
related duties who are expected to be on the site during the period July 1 September 30, 1975 in addition to those identified in previous reports:
- 1. C,nsumers Power Company No additions to last report.
- 2. Bechtel Power Corporation J. F. Newgen, Project Superintendent
- 3. U.S. Testing C.
No change from last report.
lh Quality assurance qualifications of supervisors and engineers with site-relcted duties during the period July 1 -September 30, 1975:
Statements of qualifications of individuals listed in "B" above are attached hereto.
D. Changes The following individuals with quality related duties listed in previous reports are no longer associated with this site:
- 1. Censumers Power Company
~
M. E. D' Haem
- 2. Bechtel Power Corporation W. J. Key R. E. Sevo E. E. Felton Further additions or deletions to the list of people with quality-related duties who are to be onsite during the period July 1 - September 30, 1975 will be no on the next report.
- )
(_.
2
'..;~; ..- -
- o. .
o p .
t .
Resume of Joel F. Newgen Bachelor of Science, Civil Engineering, Stanford University, 1961.
Master of Science, Civil Engineering, Construction Institute, Stanford University 1965.
Military: Officer in U. S. Navy, Active 1961 to 1964, currently LCDR USN Reserve.
Assigned as Project Superintendent, February 1975 to date.
Previous positions include: Field Superintendent at Midland Project June 1973 to February 1975; Project Field Engineer, Palisades Project, October 1971 to June 1973; Asst. Project Field Engineer, Mechanical and QC, Point Beach Project, April 1970 to October 1971.
Total of ten years experience with Bechtel on large power plants.
1 I
l l
I 4
L O
,