| title = IR 05000275-08-501, and IR 05000323-08-501, on 11/31/2008, for Diablo Canyon Power Plant Units 1 and 2 - Emergency Preparedness Annual Inspection Report
| title = IR 05000275-08-501, and IR 05000323-08-501, on 11/31/2008, for Diablo Canyon Power Plant Units 1 and 2 - Emergency Preparedness Annual Inspection Report
| author name = Shannon M P
| author name = Shannon M
| author affiliation = NRC/RGN-IV/DRS/PSB-1
| author affiliation = NRC/RGN-IV/DRS/PSB-1
| addressee name = Conway J T
| addressee name = Conway J
| addressee affiliation = Pacific Gas & Electric Co
| addressee affiliation = Pacific Gas & Electric Co
| docket = 05000275, 05000323
| docket = 05000275, 05000323
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:rch 13, 2009
[[Issue date::March 13, 2009]]


Mr. John Senior Vice President &
==SUBJECT:==
Chief Nuclear Officer Pacific Gas and Electric Company P.O. Box 3 Mail Code 104/6/601 Avila Beach, CA 93424
DIABLO CANYON POWER PLANT UNITS 1 AND 2 - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT 05000275/2008501 AND 05000323/2008501
 
SUBJECT: DIABLO CANYON POWER PLANT UNITS 1 AND 2 - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT 05000275/2008501 AND 05000323/2008501


==Dear Mr. Conway:==
==Dear Mr. Conway:==
Line 31: Line 28:
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).


Sincerely,/RA/
Sincerely,
/RA/
Michael P. Shannon, Chief Plant Support Branch-1 Division of Reactor Safety  
Michael P. Shannon, Chief Plant Support Branch-1 Division of Reactor Safety  


Dockets: 50-275; 50-323 Licenses: DPR-80; DPR-82  
Dockets: 50-275; 50-323 Licenses: DPR-80; DPR-82  


Pacific Gas and Electric Company - 2 -
UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 EAST LAMAR BLVD, SUITE 400ARLINGTON, TEXAS 76011-4125 Pacific Gas and Electric Company - 2 -
cc:
cc:
Sierra Club San Lucia Chapter ATTN: Andrew Christie P.O. Box 15755 San Luis Obispo, CA 93406  
Sierra Club San Lucia Chapter ATTN: Andrew Christie P.O. Box 15755 San Luis Obispo, CA 93406  

Revision as of 01:25, 12 July 2019

IR 05000275-08-501, and IR 05000323-08-501, on 11/31/2008, for Diablo Canyon Power Plant Units 1 and 2 - Emergency Preparedness Annual Inspection Report
ML090721123
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 03/13/2009
From: Shannon M
Plant Support Branch-1
To: Conway J
Pacific Gas & Electric Co
References
IR-08-501
Download: ML090721123 (4)


Text

rch 13, 2009

SUBJECT:

DIABLO CANYON POWER PLANT UNITS 1 AND 2 - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT 05000275/2008501 AND 05000323/2008501

Dear Mr. Conway:

On December 31, 2008, the Nuclear Regulatory Commission (NRC) staff completed its annual inspection of the Emergency Preparedness Program at the Diablo Canyon Power Plant, Units 1 and 2. This inspection began on January 1, 2008. Issuance of this letter closes NRC Inspection Report 05000275/2008501 and 05000323/2008501. Observations and findings in these areas were provided in the quarterly integrated reports for your site.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Michael P. Shannon, Chief Plant Support Branch-1 Division of Reactor Safety

Dockets: 50-275; 50-323 Licenses: DPR-80; DPR-82

UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 EAST LAMAR BLVD, SUITE 400ARLINGTON, TEXAS 76011-4125 Pacific Gas and Electric Company - 2 -

cc:

Sierra Club San Lucia Chapter ATTN: Andrew Christie P.O. Box 15755 San Luis Obispo, CA 93406

Nancy Culver San Luis Obispo Mothers for Peace P.O. Box 164 Pismo Beach, CA 93448

Chairman San Luis Obispo County Board of Supervisors 1055 Monterey Street, Suite D430 San Luis Obispo, CA 93408

Truman Burns\Robert Kinosian California Public Utilities Commission 505 Van Ness Ave., Rm. 4102 San Francisco, CA 94102

Diablo Canyon Independent Safety Committee Attn: Robert R. Wellington, Esq.

Legal Counsel 857 Cass Street, Suite D Monterey, CA 93940

Director, Radiological Health Branch State Department of Health Services P.O. Box 997414 (MS 7610)

Sacramento, CA 95899-7414

City Editor The Tribune 3825 South Higuera Street P.O. Box 112 San Luis Obispo, CA 93406-0112

James D. Boyd, Commissioner California Energy Commission 1516 Ninth Street (MS 31)

Sacramento, CA 95814

Pacific Gas and Electric Company - 3 -

James R. Becker, Site Vice President &

Station Director Diablo Canyon Power Plant P.O. Box 56 Avila Beach, CA 93424

Jennifer Tang Field Representative United States Senator Barbara Boxer 1700 Montgomery Street, Suite 240 San Francisco, CA 94111

Chief, Radiological Emergency Preparedness Section FEMA Region 9 1111 Broadway, Suite 1200 Oakland, CA 94607-4052

Pacific Gas and Electric Company - 4 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov) Deputy Regional Administrator (Chuck.Casto@nrc.gov) DRP Director (Dwight.Chamberlain@nrc.gov) DRP Deputy Director (Anton.Vegel@nrc.gov) DRS Director (Roy.Caniano@nrc.gov) DRS Deputy Director (Troy.Pruett@nrc.gov) Senior Resident Inspector (Michael.Peck@nrc.gov) Resident Inspector (Tony.Brown@nrc.gov) Branch Chief, DRP/B (Vincent.Gaddy@nrc.gov) Senior Project Engineer, DRP/B (Rick.Deese@nrc.gov) DC Site Secretary (Agnes.Chan@nrc.gov) Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) RidsNsirDso@nrc.gov

SUNSI Review Completed: ___Y___ ADAMS: Yes No Initials: __lmb____ Publicly Available Non-Publicly Available Sensitive Non-Sensitive C:PSB1 MPShannon /RA/ 3/13/09 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax