ML102950581: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 16: | Line 16: | ||
=Text= | =Text= | ||
{{#Wiki_filter:/ \K)Buried Pipe Program BNE Presentation Corporate Program Engineer: Jim Melchionna Oct 21 2009 BNE Questions* .Overall view of your program* .What piping systems are included in the program?* What materials are involved in the program (ss, aluminum, etc.)?What methods are used for inspecting the underground piping?What success has the program had in finding leaks or near-leaks? | {{#Wiki_filter:/ \ | ||
What changes have been made to the program due. to recent industry events (Oyster Creek, Peach Bottom, etc.)? How is Salem and Hope Creek the same/different from the programs used at the stations that are experiencing leaks?* What changes to the program due you expect as a result of license renewal?Are there any specific inspections being planned during the Salem 2 outage and the spring Hope Creek outage that are a direct result of license renewal? | K) | ||
Overall View Of Buried Piping Program (BPP)* PSEG has an established Buried Piping Program* BPP consists of corrosion control, monitoring, and mitigation elements BPP is comprised of other "subset" programs 89-13, NJAC (Discharge Prevention and Response Program DPRP), American Nuclear Insurance° BPP Procedures | Buried Pipe Program BNE Presentation Corporate Program Engineer: Jim Melchionna Oct 21 2009 | ||
& T&RMs are in place-ER-AA-5400 BPP Guide-ER-AA-5400-1002 BPP Examination Guide-ER-AA-5400-1003 BPP PI's Overall View Of Buried Piping Program (BPP) (cont'd)* BPP Basis document, Risk Ranking, & database are in place for both Salem and Hope Creek stations* Salem and Hope Creek have performed various non-intrusive and opportunistic visual inspections. | |||
* Actively involved in industry:-PSEG is member of EPRI's Buried Piping Issues Group (BPIG)-INPO representatives attend BPIG meetings and provide insight/input on their focus-PSEG benchmarking: | BNE Questions | ||
Dresden 2008 (INPO Strength 2007)* Palo Verde (planned early 2010)-PSEG BPP process modeled after NACE RP 0502 Overall View Of Buried Piping Program (BPP) (cont'd)Salem & Hope Creek BPP Managers have attended EPRI's BPP Manager training* Station BPP Health Reports/Pl's | * .Overall view of your program | ||
-Trial issuance 3 rd Qtr 200.9-Official issuance 4th Qtr 2009° BPP Manager Cert Guide (Qual Card) issuance 4Q09 Overall View Of Buried Piping Program (BPP)(cont'd)PSEG Program Process StepD One P re-assessmentAnalysis | * .What piping systems are included in the program? | ||
......... -Should ;the systerm be. pa rt .of th e B P P pipgin:g'. | * What materials are involved in the program (ss, aluminum, etc.)? | ||
program?D.ata Collection Where are the anomalies? | What methods are used for inspecting the underground piping? | ||
Identify Susceptibe 1Step > Three.syteslnspectj.-iighs | What success has the program had in finding leaks or near-leaks? | ||
~ | What changes have been made to the program due. to recent industry events (Oyster Creek, Peach Bottom, etc.)? How is Salem and Hope Creek the same/different from the programs used at the stations that are experiencing leaks? | ||
*___iatiZonneons | * What changes to the program due you expect as a result of license renewal? | ||
-~ie What is the Examr fre Seletionrequired? | Are there any specific inspections being planned during the Salem 2 outage and the spring Hope Creek outage that are a direct result of license renewal? | ||
CreateUp e St-rength | |||
Piping systems in the program Hope Creek: Auxiliary Boiler FO Storage, Aux Steam, Building Sewage, Chemical Waste, CW Acid Injection, CW Hypo chlorination, CW, CST, Cooling Tower Blow down Dechlorination, Cooling Tower Blow down, Demin Water Make-up/Storage. | Overall View Of Buried Piping Program (BPP) | ||
& Transfer, DFO Storage & Transfer, Domestic Water, FP, FW, Hydrogen/Oxygen Water Chemistry, Control Air, Normal Drains, Oily Waste, Process Radiation Monitoring, Service Compressed Air, Service Gases, SW, SW Dechlorination, Storm Drainage Piping systems in the program (Cont'd)Salem: CW, SW, FW, Storm Drains, FP, Demineralized Water, Condensate Polishing, Station Air, Control Air, Fuel Oil (Gas Turbine, House Heating Boilers, TSC Emergency. | * PSEG has an established Buried Piping Program | ||
Diesel Generator, Emergency Diesel Generators, Fire Pump Diesels, Circulating Water Intake Heating Boiler, & Service Water Intake Hot Air Furnace), Hypo Chlorination, Liquid Waste, Potable Water, Fresh Water, Auxiliary Feed water, Sanitary Drains (Non-Rad Drains) | * BPP consists of corrosion control, monitoring, and mitigation elements BPP is comprised of other "subset" programs 89-13, NJAC (Discharge Prevention and Response Program DPRP), American Nuclear Insurance | ||
Materials involved in the program Hope Creek:* Carbon Steel, Cast Iron, Cement Lined Ductile Iron, Cement Lined Carbon Steel, Copper, Fiberglass, Plastic, Pre-stressed. | ° BPP Procedures & T&RMs are in place | ||
Concrete, Pre.stressed Concrete Embedded Cylinder, Reinforced Concrete, and Stainless Steel Salem:* Carbon Steel, Cast Iron, Cast Steel,' Cement Lined Ductile Iron, Cement.Lined Carbon Steel, Copper, PVC, Pre-stressed Concrete, Pre-stressed Concrete Embedded Cylinder, and Stainless Steel Methods used for inspecting the underground piping* Opportunistic | - ER-AA-5400 BPP Guide | ||
& Focused both used* Current InDirect Methods available-Guided Wave*, C-Scan*, DCVG*, ACVG* Current Direct methods available-'UT*, RFTC* LFET, Pig, BEM*, Visual* | - ER-AA-5400-1002 BPP Examination Guide | ||
-Tracer Gas, Acoustic Monitoring, Drop Test*, N2 Pressure Decay*, | - ER-AA-5400-1003 BPP PI's | ||
Overall View Of Buried Piping Program (BPP) (cont'd) | |||
* BPP Basis document, Risk Ranking, & database are in place for both Salem and Hope Creek stations | |||
* Salem and Hope Creek have performed various non-intrusive and opportunistic visual inspections. | |||
* Actively involved in industry: | |||
- PSEG is member of EPRI's Buried Piping Issues Group (BPIG) | |||
- INPO representatives attend BPIG meetings and provide insight/input on their focus | |||
- PSEG benchmarking: | |||
Dresden 2008 (INPO Strength 2007) | |||
* Palo Verde (planned early 2010) | |||
- PSEG BPP process modeled after NACE RP 0502 | |||
Overall View Of Buried Piping Program (BPP) (cont'd) | |||
Salem & Hope Creek BPP Managers have attended EPRI's BPP Manager training | |||
* Station BPP Health Reports/Pl's | |||
- Trial issuance 3 rd Qtr 200.9 | |||
- Official issuance 4th Qtr 2009 | |||
° BPP Manager Cert Guide (Qual Card) issuance 4Q09 | |||
Overall View Of Buried Piping Program (BPP) | |||
(cont'd) | |||
PSEG Program Process StepD One P re-assessmentAnalysis | |||
......... -Should ;the piping* systerm be. pa rt .of th e B P P pipgin:g'. | |||
program? | |||
D.ata Collection Where are the anomalies? | |||
Identify Susceptibe 1Step > Three. | |||
syteslnspectj.-iighs ~ DirectEx amiin ati rl | |||
-Evaluate, Indirec tExamn Method? | |||
Susepjtible Systems Adetil Sererity of integrity? | |||
*___iatiZonneons"For Step LýCom lete Risk 1ioritize Exa*" Post Asess"me nt. | |||
the Progra rn. iethod; A's.ses m ent -Has L iyerit. been suc.- ssfu]I? | |||
Indirectxam ToolExcavte -~ie What is the Examr fre ,qUency. | |||
Seletionrequired? | |||
CreateUp e "E. St-rength | |||
.a . lu...ati ..n Basis .Docdum~ent r -t: | |||
(NACE Recommended Practice 05.02-2002) | |||
Piping systems in the program Hope Creek: | |||
Auxiliary Boiler FO Storage, Aux Steam, Building Sewage, Chemical Waste, CW Acid Injection, CW Hypo chlorination, CW, CST, Cooling Tower Blow down Dechlorination, Cooling Tower Blow down, Demin Water Make-up/Storage. & Transfer, DFO Storage & Transfer, Domestic Water, FP, FW, Hydrogen/Oxygen Water Chemistry, Control Air, Normal Drains, Oily Waste, Process Radiation Monitoring, Service Compressed Air, Service Gases, SW, SW Dechlorination, Storm Drainage | |||
Piping systems in the program (Cont'd) | |||
Salem: | |||
CW, SW, FW, Storm Drains, FP, Demineralized Water, Condensate Polishing, Station Air, Control Air, Fuel Oil (Gas Turbine, House Heating Boilers, TSC Emergency. Diesel Generator, Emergency Diesel Generators, Fire Pump Diesels, Circulating Water Intake Heating Boiler, & Service Water Intake Hot Air Furnace), | |||
Hypo Chlorination, Liquid Waste, Potable Water, Fresh Water, Auxiliary Feed water, Sanitary Drains (Non-Rad Drains) | |||
Materials involved in the program Hope Creek: | |||
* Carbon Steel, Cast Iron, Cement Lined Ductile Iron, Cement Lined Carbon Steel, Copper, Fiberglass, Plastic, Pre-stressed. Concrete, Pre.stressed Concrete Embedded Cylinder, Reinforced Concrete, and Stainless Steel Salem: | |||
* Carbon Steel, Cast Iron, Cast Steel,' Cement Lined Ductile Iron, Cement.Lined Carbon Steel, Copper, PVC, Pre-stressed Concrete, Pre-stressed Concrete Embedded Cylinder, and Stainless Steel | |||
Methods used for inspecting the underground piping | |||
* Opportunistic & Focused both used | |||
* Current InDirect Methods available | |||
- Guided Wave*, C-Scan*, DCVG*, ACVG | |||
* Current Direct methods available | |||
-'UT*, RFTC* LFET, Magnetic Flux Leakage, Tethered Pig, BEM*, Visual* | |||
* Other Assessment techniques | |||
- Tracer Gas, Acoustic Monitoring, Sahara, Gravity Drop Test*, N2 Pressure Decay*, Leak Rate*, GPR* | |||
Fiberscope* | |||
* Has been used at PSEG | |||
*What success has the program had in finding leaks or near-leaks? | *What success has the program had in finding leaks or near-leaks? | ||
* No leaks have been identified since inception of BPP 89-13 program has noted ID degradation of Nuclear header Bell & Spigot (B&S) joints via visual exams & NDE (Salem & Hope Creek)Installed WEKO seals in 3 of 4 Salem Nuclear Supply Headers B&S joints° Cleaned and Epoxy Coated Salem Unit 2 SW Nuclear Discharge Header B&S Joints° SW manned visual inspections have revealed Salem TGA header ID lining degradation | * No leaks have been identified since inception of BPP 89-13 program has noted ID degradation of Nuclear header Bell & Spigot (B&S) joints via visual exams & NDE (Salem & Hope Creek) | ||
* Hope Creek Buried CW to Cooling Tower lines-RFTC completed, degradation assessment complete-Repair priorities established, options presented, repairs scheduled What success has the program had in finding leaks or near-leaks? (Cont'd)Inspections completed to date Opportunistic:. | Installed WEKO seals in 3 of 4 Salem Nuclear Supply Headers B&S joints | ||
Inspections completed at both Salem and Hope Creek* Salem FO (SW/CW Boilers), Control Air, Liquid Waste, Dewatering line, FP, SW External (12 Nuc Header)* Hope Creek FP, Domestic Water, Building Sewage Focused (As a result of Risk Ranking/BPP implementation): | ° Cleaned and Epoxy Coated Salem Unit 2 SW Nuclear Discharge Header B&S Joints | ||
-GUL (aka Guided Wave) completed on. Hope Creek CST 2/4/8/12/20" stainless steel lines, 4" DFO (coated carbon steel), Rad Waste (3" stainless steel).-C-Scan completed on Hope Creek 4" DFO line (coated carbon steel)4"/6" FP (Ductile Iron), 6" Domestic Water (mortar lined ductile iron), 18" Oily Waste (cement-lined ductile iron)-RFTC Of Hope Creek CW Buried PCCP What changes have. been made to the program due to recent industry events?* More thorough and detailed prejob briefs & walk downs with inspectors | ° SW manned visual inspections have revealed Salem TGA header ID lining degradation | ||
-Detailed drawing reviews with inspectors | * Hope Creek Buried CW to Cooling Tower lines | ||
-Field walk downs with inspectors | - RFTC completed, degradation assessment complete | ||
* Closer contact with industry peers° Added requirement in all excavation orders to:-Contact Buried Piping program manager for inspection of excavated piping -gives us an engineer with "Eyes On"-Perform soil sampling on all excavations involving buried piping* Exercising more rigor in post inspection analysis related to Guided Wave How is Salem and Hope Creek the same/different from the programs used at.the stations that are experiencing leaks? | - Repair priorities established, options presented, repairs scheduled | ||
G- Newer. Gen GUL Enhanced Technology Wave, 8 channel Circumferential Resolution Guided wave, (16 channel)Inspection details Vague or inaccurate Detailed piping details provided, onsite detailed discussions on walk downs conducted with inspectors drawing details How is Salem and Hope Creek the same/different from the programs used at the stations that'are experiencing leaks? ( Cont'd.)Deltas -Leaking Indian Point Salem Indian Point 2 AFST Line Material Carbon Steel (Coated) Carbon Steel (Coated)Piping Coal tar coating Coal tar coating Protection Leakage/Inspection Yes -due to coating No identified leakage. Salem Unit 2 Aux failure and subsequent Feed lines excavated in 1994 -piping in metal degradation excellent condition Fill Poor -Fill contained Engineered foreign material, weld rod, metal pieces How is Salem and Hope Creek the same/different from the programs used at the stations that are experiencing leaks?(Cont'd)The elements of the program that select the buried piping scope and perform the risk ranking are essentially the same The indirect inspection techniques are currently available to anyone in the industry from a variety of sources, however:-PSEG:* Conducts up to date reviews of Guided Wave Technology prior to each inspection as GUL technology is an emerging technology 0 Conducts reviews of proposed NDE vendors to evaluate their performance at other utilities prior to issuance of a contract* PSEG conducts onsite prejob planning using familiarization and walk downs prior to conducting these inspections | |||
* Guided Wave companies now asked to have results reviewed &validated by independent Level 2 Guided Wave analyst Whatchanges to the program due you expect as a result of License Renewal?* The Buried & Buried, Non-Steel Piping inspection program will be enhanced to include:-Adding at least one opportunistic or focused excavation and inspection for inspection of specific piping materials (as well as the Salem buried piping SS bellows between the containment and FHB) within a span of 10 years prior to period of extended operation (PEO) as well as within the first 10 years of operation after the PEO.-Guidance for inspection of concrete aging affects Salem U2 and -HC are currently not within the, 10 years to PEO Are there any specific inspections being planned during 2R17 & RF16 that are a direct result of License Renewal (LR)?Salem Unit 2 and Hope Creek are not within the 10 years of the PEO, therefore no LR related inspections are scheduled for 2R1 7 or RF16 as a direct result of LR Focused inspections are scheduled in 2R18, 1.R20 & RF16 as a result of the BPP implementation based on risk ranking | What success has the program had in finding leaks or near-leaks? (Cont'd) | ||
Inspections completed to date Opportunistic:. | |||
Inspections completed at both Salem and Hope Creek | |||
* Salem FO (SW/CW Boilers), Control Air, Liquid Waste, Dewatering line, FP, SW External (12 Nuc Header) | |||
* Hope Creek FP, Domestic Water, Building Sewage Focused (As a result of Risk Ranking/BPP implementation): | |||
- GUL (aka Guided Wave) completed on. Hope Creek CST 2/4/8/12/20" stainless steel lines, 4" DFO (coated carbon steel), Rad Waste (3" stainless steel). | |||
- C-Scan completed on Hope Creek 4" DFO line (coated carbon steel) 4"/6" FP (Ductile Iron), 6" Domestic Water (mortar lined ductile iron), 18" Oily Waste (cement-lined ductile iron) | |||
- RFTC Of Hope Creek CW Buried PCCP | |||
What changes have. been made to the program due to recent industry events? | |||
* More thorough and detailed prejob briefs & walk downs with inspectors | |||
- Detailed drawing reviews with inspectors | |||
- Field walk downs with inspectors | |||
* Closer contact with industry peers | |||
° Added requirement in all excavation orders to: | |||
- Contact Buried Piping program manager for inspection of excavated piping - gives us an engineer with "Eyes On" | |||
- Perform soil sampling on all excavations involving buried piping | |||
* Exercising more rigor in post inspection analysis related to Guided Wave | |||
t How is Salem and Hope Creek the same/different from the programs used at.the stations that are experiencing leaks? | |||
Deltas - Leaking Oyster Creek Hope Creek OC CST Lines Material Carbon Steel (Coated) Stainless Steel Aluminum Piping Coal tar coating Corrosion resistant material Protection Portions encapsulated with foam & | |||
secondary piping Pipe Age Installed 1969 1981 Fill Unknown - Excavated Engineered (easy drainage, non-wicking) many times Inspection Older Generation. G- Newer. Gen GUL Enhanced Technology Wave, 8 channel Circumferential Resolution Guided wave, (16 channel) | |||
Inspection details Vague or inaccurate Detailed piping details provided, onsite detailed discussions on walk downs conducted with inspectors drawing details | |||
How is Salem and Hope Creek the same/different from the programs used at the stations that'are experiencing leaks? ( Cont'd.) | |||
Deltas - Leaking Indian Point Salem Indian Point 2 AFST Line Material Carbon Steel (Coated) Carbon Steel (Coated) | |||
Piping Coal tar coating Coal tar coating Protection Leakage/Inspection Yes - due to coating No identified leakage. Salem Unit 2 Aux failure and subsequent Feed lines excavated in 1994 - piping in metal degradation excellent condition Fill Poor - Fill contained Engineered foreign material, weld rod, metal pieces | |||
How is Salem and Hope Creek the same/different from the programs used at the stations that are experiencing leaks? | |||
(Cont'd) | |||
The elements of the program that select the buried piping scope and perform the risk ranking are essentially the same The indirect inspection techniques are currently available to anyone in the industry from a variety of sources, however: | |||
- PSEG: | |||
* Conducts up to date reviews of Guided Wave Technology prior to each inspection as GUL technology is an emerging technology 0 Conducts reviews of proposed NDE vendors to evaluate their performance at other utilities prior to issuance of a contract | |||
* PSEG conducts onsite prejob planning using familiarization and walk downs prior to conducting these inspections | |||
* Guided Wave companies now asked to have results reviewed & | |||
validated by independent Level 2 Guided Wave analyst | |||
Whatchanges to the program due you expect as a result of License Renewal? | |||
* The Buried & Buried, Non-Steel Piping inspection program will be enhanced to include: | |||
- Adding at least one opportunistic or focused excavation and inspection for inspection of specific piping materials (as well as the Salem buried piping SS bellows between the containment and FHB) within a span of 10 years prior to period of extended operation (PEO) as well as within the first 10 years of operation after the PEO. | |||
- Guidance for inspection of concrete aging affects Salem U2 and -HC are currently not within the, 10 years to PEO | |||
N Are there any specific inspections being planned during 2R17 & RF16 that are a direct result of License Renewal (LR)? | |||
Salem Unit 2 and Hope Creek are not within the 10 years of the PEO, therefore no LR related inspections are scheduled for 2R1 7 or RF16 as a direct result of LR Focused inspections are scheduled in 2R18, 1.R20 & RF16 as a result of the BPP implementation based on risk ranking}} |
Latest revision as of 07:22, 13 November 2019
ML102950581 | |
Person / Time | |
---|---|
Site: | Salem, Hope Creek |
Issue date: | 10/21/2009 |
From: | Melchionna J - No Known Affiliation |
To: | NRC Region 1 |
References | |
FOIA/PA-2010-0334 | |
Download: ML102950581 (18) | |
Text
/ \
K)
Buried Pipe Program BNE Presentation Corporate Program Engineer: Jim Melchionna Oct 21 2009
BNE Questions
- .Overall view of your program
- .What piping systems are included in the program?
- What materials are involved in the program (ss, aluminum, etc.)?
What methods are used for inspecting the underground piping?
What success has the program had in finding leaks or near-leaks?
What changes have been made to the program due. to recent industry events (Oyster Creek, Peach Bottom, etc.)? How is Salem and Hope Creek the same/different from the programs used at the stations that are experiencing leaks?
- What changes to the program due you expect as a result of license renewal?
Are there any specific inspections being planned during the Salem 2 outage and the spring Hope Creek outage that are a direct result of license renewal?
Overall View Of Buried Piping Program (BPP)
- PSEG has an established Buried Piping Program
- BPP consists of corrosion control, monitoring, and mitigation elements BPP is comprised of other "subset" programs 89-13, NJAC (Discharge Prevention and Response Program DPRP), American Nuclear Insurance
° BPP Procedures & T&RMs are in place
- ER-AA-5400 BPP Guide
- ER-AA-5400-1002 BPP Examination Guide
- ER-AA-5400-1003 BPP PI's
Overall View Of Buried Piping Program (BPP) (cont'd)
- BPP Basis document, Risk Ranking, & database are in place for both Salem and Hope Creek stations
- Salem and Hope Creek have performed various non-intrusive and opportunistic visual inspections.
- Actively involved in industry:
- PSEG is member of EPRI's Buried Piping Issues Group (BPIG)
- INPO representatives attend BPIG meetings and provide insight/input on their focus
- PSEG benchmarking:
Dresden 2008 (INPO Strength 2007)
- Palo Verde (planned early 2010)
- PSEG BPP process modeled after NACE RP 0502
Overall View Of Buried Piping Program (BPP) (cont'd)
Salem & Hope Creek BPP Managers have attended EPRI's BPP Manager training
- Station BPP Health Reports/Pl's
- Trial issuance 3 rd Qtr 200.9
- Official issuance 4th Qtr 2009
° BPP Manager Cert Guide (Qual Card) issuance 4Q09
Overall View Of Buried Piping Program (BPP)
(cont'd)
PSEG Program Process StepD One P re-assessmentAnalysis
......... -Should ;the piping* systerm be. pa rt .of th e B P P pipgin:g'.
program?
D.ata Collection Where are the anomalies?
Identify Susceptibe 1Step > Three.
syteslnspectj.-iighs ~ DirectEx amiin ati rl
-Evaluate, Indirec tExamn Method?
Susepjtible Systems Adetil Sererity of integrity?
- ___iatiZonneons"For Step LýCom lete Risk 1ioritize Exa*" Post Asess"me nt.
the Progra rn. iethod; A's.ses m ent -Has L iyerit. been suc.- ssfu]I?
Indirectxam ToolExcavte -~ie What is the Examr fre ,qUency.
Seletionrequired?
CreateUp e "E. St-rength
.a . lu...ati ..n Basis .Docdum~ent r -t:
(NACE Recommended Practice 05.02-2002)
Piping systems in the program Hope Creek:
Auxiliary Boiler FO Storage, Aux Steam, Building Sewage, Chemical Waste, CW Acid Injection, CW Hypo chlorination, CW, CST, Cooling Tower Blow down Dechlorination, Cooling Tower Blow down, Demin Water Make-up/Storage. & Transfer, DFO Storage & Transfer, Domestic Water, FP, FW, Hydrogen/Oxygen Water Chemistry, Control Air, Normal Drains, Oily Waste, Process Radiation Monitoring, Service Compressed Air, Service Gases, SW, SW Dechlorination, Storm Drainage
Piping systems in the program (Cont'd)
Salem:
CW, SW, FW, Storm Drains, FP, Demineralized Water, Condensate Polishing, Station Air, Control Air, Fuel Oil (Gas Turbine, House Heating Boilers, TSC Emergency. Diesel Generator, Emergency Diesel Generators, Fire Pump Diesels, Circulating Water Intake Heating Boiler, & Service Water Intake Hot Air Furnace),
Hypo Chlorination, Liquid Waste, Potable Water, Fresh Water, Auxiliary Feed water, Sanitary Drains (Non-Rad Drains)
Materials involved in the program Hope Creek:
- Carbon Steel, Cast Iron, Cement Lined Ductile Iron, Cement Lined Carbon Steel, Copper, Fiberglass, Plastic, Pre-stressed. Concrete, Pre.stressed Concrete Embedded Cylinder, Reinforced Concrete, and Stainless Steel Salem:
- Carbon Steel, Cast Iron, Cast Steel,' Cement Lined Ductile Iron, Cement.Lined Carbon Steel, Copper, PVC, Pre-stressed Concrete, Pre-stressed Concrete Embedded Cylinder, and Stainless Steel
Methods used for inspecting the underground piping
- Opportunistic & Focused both used
- Current InDirect Methods available
- Guided Wave*, C-Scan*, DCVG*, ACVG
- Current Direct methods available
-'UT*, RFTC* LFET, Magnetic Flux Leakage, Tethered Pig, BEM*, Visual*
- Other Assessment techniques
- Tracer Gas, Acoustic Monitoring, Sahara, Gravity Drop Test*, N2 Pressure Decay*, Leak Rate*, GPR*
Fiberscope*
- Has been used at PSEG
- What success has the program had in finding leaks or near-leaks?
- No leaks have been identified since inception of BPP 89-13 program has noted ID degradation of Nuclear header Bell & Spigot (B&S) joints via visual exams & NDE (Salem & Hope Creek)
Installed WEKO seals in 3 of 4 Salem Nuclear Supply Headers B&S joints
° Cleaned and Epoxy Coated Salem Unit 2 SW Nuclear Discharge Header B&S Joints
° SW manned visual inspections have revealed Salem TGA header ID lining degradation
- Hope Creek Buried CW to Cooling Tower lines
- RFTC completed, degradation assessment complete
- Repair priorities established, options presented, repairs scheduled
What success has the program had in finding leaks or near-leaks? (Cont'd)
Inspections completed to date Opportunistic:.
Inspections completed at both Salem and Hope Creek
- Salem FO (SW/CW Boilers), Control Air, Liquid Waste, Dewatering line, FP, SW External (12 Nuc Header)
- Hope Creek FP, Domestic Water, Building Sewage Focused (As a result of Risk Ranking/BPP implementation):
- GUL (aka Guided Wave) completed on. Hope Creek CST 2/4/8/12/20" stainless steel lines, 4" DFO (coated carbon steel), Rad Waste (3" stainless steel).
- C-Scan completed on Hope Creek 4" DFO line (coated carbon steel) 4"/6" FP (Ductile Iron), 6" Domestic Water (mortar lined ductile iron), 18" Oily Waste (cement-lined ductile iron)
- RFTC Of Hope Creek CW Buried PCCP
What changes have. been made to the program due to recent industry events?
- More thorough and detailed prejob briefs & walk downs with inspectors
- Detailed drawing reviews with inspectors
- Field walk downs with inspectors
- Closer contact with industry peers
° Added requirement in all excavation orders to:
- Contact Buried Piping program manager for inspection of excavated piping - gives us an engineer with "Eyes On"
- Perform soil sampling on all excavations involving buried piping
- Exercising more rigor in post inspection analysis related to Guided Wave
t How is Salem and Hope Creek the same/different from the programs used at.the stations that are experiencing leaks?
Deltas - Leaking Oyster Creek Hope Creek OC CST Lines Material Carbon Steel (Coated) Stainless Steel Aluminum Piping Coal tar coating Corrosion resistant material Protection Portions encapsulated with foam &
secondary piping Pipe Age Installed 1969 1981 Fill Unknown - Excavated Engineered (easy drainage, non-wicking) many times Inspection Older Generation. G- Newer. Gen GUL Enhanced Technology Wave, 8 channel Circumferential Resolution Guided wave, (16 channel)
Inspection details Vague or inaccurate Detailed piping details provided, onsite detailed discussions on walk downs conducted with inspectors drawing details
How is Salem and Hope Creek the same/different from the programs used at the stations that'are experiencing leaks? ( Cont'd.)
Deltas - Leaking Indian Point Salem Indian Point 2 AFST Line Material Carbon Steel (Coated) Carbon Steel (Coated)
Piping Coal tar coating Coal tar coating Protection Leakage/Inspection Yes - due to coating No identified leakage. Salem Unit 2 Aux failure and subsequent Feed lines excavated in 1994 - piping in metal degradation excellent condition Fill Poor - Fill contained Engineered foreign material, weld rod, metal pieces
How is Salem and Hope Creek the same/different from the programs used at the stations that are experiencing leaks?
(Cont'd)
The elements of the program that select the buried piping scope and perform the risk ranking are essentially the same The indirect inspection techniques are currently available to anyone in the industry from a variety of sources, however:
- PSEG:
- Conducts up to date reviews of Guided Wave Technology prior to each inspection as GUL technology is an emerging technology 0 Conducts reviews of proposed NDE vendors to evaluate their performance at other utilities prior to issuance of a contract
- PSEG conducts onsite prejob planning using familiarization and walk downs prior to conducting these inspections
- Guided Wave companies now asked to have results reviewed &
validated by independent Level 2 Guided Wave analyst
Whatchanges to the program due you expect as a result of License Renewal?
- The Buried & Buried, Non-Steel Piping inspection program will be enhanced to include:
- Adding at least one opportunistic or focused excavation and inspection for inspection of specific piping materials (as well as the Salem buried piping SS bellows between the containment and FHB) within a span of 10 years prior to period of extended operation (PEO) as well as within the first 10 years of operation after the PEO.
- Guidance for inspection of concrete aging affects Salem U2 and -HC are currently not within the, 10 years to PEO
N Are there any specific inspections being planned during 2R17 & RF16 that are a direct result of License Renewal (LR)?
Salem Unit 2 and Hope Creek are not within the 10 years of the PEO, therefore no LR related inspections are scheduled for 2R1 7 or RF16 as a direct result of LR Focused inspections are scheduled in 2R18, 1.R20 & RF16 as a result of the BPP implementation based on risk ranking