Hope Creek Ultimate Heat Sink (UHS)
NRC Pre-submittal Meeting March 30, 2021
Agenda
- Purpose of Meeting
- Background of UHS TS 3.7.1.3
- Proposed Scope of Changes to TS 3.7.1.3
- Technical Bases
- Schedule
- Questions 2
Purpose of Meeting
- Proposing changes to UHS TS 3.7.1.3 to avoid future NOED requests
- Current TS require unnecessary shutdown for single equipment failure scenarios that are currently analyzed
- Sufficient margins are present in existing calculations to raise limits 3
Background of TS 3.7.1.3
- TS 3.7.1.3 based on TS Amendments 106, 120 and 168
- Amendment 106
- LCO temperature of 85°F
- Added TS Action for Emergency Discharge Valves
- Maximum temperature limit of 87°F 4
Background of TS 3.7.1.3
- Amendment 120
- Increased maximum temperature from 87°F to 89°F
- Amendment 168
- Incorporated TSTF-330 temperature average
- Average of 89°F with peak not to exceed 91.4°F 5
Proposed Scope of Changes to TS 3.7.1.3
- Revise the temperature in UHS LCO 3.7.1.3b and in TS Action for Emergency Discharge Valves from 85°F to 88°F
- Replace TS action to have all EDGs, SACS pumps and SSWS pumps operable above 88°F with new 72-hour AOT for one EDG, SACS pump or SSW pump inoperable
- Revise TS average temperature to 91°F with a peak of 93°F
- Revise Surveillance Requirement (SR) 4.7.1.3.b temperature from 82°F to 85°F for implementing increased monitoring frequency
- No changes are made to the EDG, SACS or SSWS TS 6
Technical Bases
- Increase in temperatures for LCO and Actions are supported by margin in the existing calculation
- Allowance of 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> action for an EDG, SACS pump or SSWS pump is consistent with single failure assumption 7
Schedule
- Current target for submission is April 2021
- Requesting a normal review period Any Questions?
8