IR 05000440/2020005: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:ber 1, 2020
{{#Wiki_filter:September 1, 2020


==SUBJECT:==
==SUBJECT:==

Latest revision as of 05:04, 17 February 2021

Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2020005)
ML20244A285
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 09/01/2020
From: April Nguyen
NRC/RGN-III/DRP/B2
To: Payne F
Energy Harbor Nuclear Corp
References
IR 2020005
Download: ML20244A285 (7)


Text

September 1, 2020

SUBJECT:

UPDATED INSPECTION PLAN FOR PERRY NUCLEAR POWER PLANT (REPORT 05000440/2020005)

Dear Mr. Payne:

The enclosed inspection plan lists the inspections scheduled through June 30, 2022, for Perry Nuclear Power Plant. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP), including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the May 28, 2020 memo, Inspection Guidance During Transition From COVID-19 Mandatory Telework (ML20141L766). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:

https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.

The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these baseline inspections are being developed by the NRC staff. Anticipated baseline inspection dates are presented in the attached; however, the staff will confirm the schedule for these inspections with each utility separately.

Additionally, during this period the NRC will perform inspections per Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012-01).

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630-829-9587 with any questions you have regarding this letter.

Sincerely,

/RA/

April Nguyen, Acting Chief Branch 2 Division of Reactor Project Docket No. 50-440 License No. NPF-58 Enclosure(s):

Inspection Plan cc: Distribution via LISTSERV Letter to Frank Payne from April Nguyen dated September 1, 2020.

SUBJECT: UPDATED INSPECTION PLAN FOR PERRY NUCLEAR POWER PLANT (REPORT 05000440/2020005)

DISTRIBUTION:

Jessie Quichocho Elise Burket RidsNrrPMPerry Resource RidsNrrDorlLpl3 RidsNrrDroIrib Resource John Giessner Kenneth OBrien Jamnes Cameron Allan Barker DRPIII DRSIII ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML20244A285 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII RIII NAME RRuiz:wc via email ANguyen via email DATE 8/28/2020 8/28/2020 OFFICIAL RECORD COPY

IP 22 Inspection Activity Plan Report Perry 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count Radiation Protection Baseline Inspection 1 1 07/20/2020 07/31/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1 07/20/2020 07/31/2020 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment Security Baseline Inspection 2 1 08/03/2020 08/07/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 10/01/2020 12/31/2020 IP 71130.09 001656 Security Plan Changes 1 10/05/2020 10/09/2020 IP 71130.02 000734 Access Control 1 10/05/2020 10/09/2020 IP 71130.05 000737 Protective Strategy Evaluation ISFSI Cask Loading Inspection 3Q2020 2 1 08/17/2020 08/21/2020 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants Emergency Preparedness Exercise Inspection / Performance Indicator Verification 4 1 09/14/2020 09/18/2020 IP 71114.01 000716 Exercise Evaluation 1 09/14/2020 09/18/2020 IP 71151 001397 Performance Indicator Verification Radiation Protection Baseline Inspection 1 1 10/26/2020 10/30/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation Perry Biennial Licensed Operator Requalification Program Inspection 2 1 12/06/2020 12/12/2020 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Perry February 2021 Initial License Exam 4 1 01/03/2021 01/09/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1 02/07/2021 02/13/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

1 02/14/2021 02/20/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

This report does not include INPO and OUTAGE activities. Page 1 of 4 This report shows only on-site and announced inspection procedures.

8/31/2020 1:31:59 PM

IP 22 Inspection Activity Plan Report Perry 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count Radiation Protection Baseline Inspection 1 1 02/01/2021 02/05/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation Emergency Preparedness Baseline Inspection / Performance Indicator Verification 1 1 02/08/2021 02/12/2021 IP 71114.02 000717 Alert and Notification System Testing 1 02/08/2021 02/12/2021 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 02/08/2021 02/12/2021 IP 71114.05 000720 Maintenance of Emergency Preparedness 1 02/08/2021 02/12/2021 IP 71151 001397 Performance Indicator Verification Corporate Security Baseline Inspection 1 1, 2 02/08/2021 02/12/2021 IP 71130.01 000733 Access Authorization Inservice Inspection Perry 1 1 03/01/2021 03/29/2021 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

Radiation Protection Baseline Inspection 1 1 03/15/2021 03/19/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 03/15/2021 03/19/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls OPC Temporary Instruction 2515/194 1 1 04/24/2021 04/28/2021 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)

Security Baseline Inspection 1 1, 2 04/26/2021 04/30/2021 IP 71130.02 000734 Access Control 1, 2 04/26/2021 04/30/2021 IP 71130.14 Review of Power Reactor Target Sets This report does not include INPO and OUTAGE activities. Page 2 of 4 This report shows only on-site and announced inspection procedures.

8/31/2020 1:31:59 PM

IP 22 Inspection Activity Plan Report Perry 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count Biennial Problem Identification and Resolution Inspection 4 1 05/24/2021 06/11/2021 IP 71152B 000747 Problem Identification and Resolution Design Basis Assurance Inspection (Programs) 3 1 06/28/2021 07/19/2021 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements Triennial Fire Protection Inspection 3 1 09/13/2021 10/01/2021 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

Security Baseline Inspection 1 1, 2 09/20/2021 09/24/2021 IP 71130.07 000739 Security Training 1, 2 09/20/2021 09/24/2021 IP 71151 001338 Performance Indicator Verification 1, 2 10/01/2021 12/31/2021 IP 71130.09 001656 Security Plan Changes Radiation Protection Baseline Inspection 1 1 11/29/2021 12/03/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls RP Baseline Inpsection 1 1 03/21/2022 03/25/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1 03/21/2022 03/25/2022 IP 71124.04 000728 Occupational Dose Assessment Cyber Security Inspection 4 1 03/21/2022 04/08/2022 IP 71130.10P 000741 Cyber Security ISFSI Preoperational and Initial Loading 2Q2022 4 1 05/23/2022 05/27/2022 IP 60856.1 001002 Review of 10 CFR 72.212(b) Evaluations at Operating Plants This report does not include INPO and OUTAGE activities. Page 3 of 4 This report shows only on-site and announced inspection procedures.

8/31/2020 1:31:59 PM

IP 22 Inspection Activity Plan Report Perry 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count ISFSI Preoperational and Initial Loading 2Q2022 4 1 06/06/2022 06/10/2022 IP 60854.1 000589 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants RP Baseline Inspection 1 1 06/06/2022 06/10/2022 IP 71124.07 000731 Radiological Environmental Monitoring Program This report does not include INPO and OUTAGE activities. Page 4 of 4 This report shows only on-site and announced inspection procedures.

8/31/2020 1:31:59 PM