| | {{#Wiki_filter:Inspection / Activity Plan Page 1 of 2 03/05/2012 08:52:58 Report 22 03/01/2012 |
| | -06/30/2013 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site North Anna PSB1-RP-OCCUPATIONAL RP BASELINE WK1 3 1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/12/2012 03/16/2012 1, 2 IP Occupational ALARA Planning and Controls 71124.02 03/12/2012 03/16/2012 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/12/2012 03/16/2012 1, 2 IP Occupational Dose Assessment 71124.04 03/12/2012 03/16/2012 1, 2 IP Radiation Monitoring Instrumentation 71124.05 03/12/2012 03/16/2012 1, 2 IP Performance Indicator Verification 71151 03/12/2012 03/16/2012 CDBI-COMPONENT DESIGN BASES INSPECTION 5 1, 2 IP Component Design Bases Inspection 7111121 04/30/2012 05/04/2012 1, 2 IP Component Design Bases Inspection 7111121 05/21/2012 05/25/2012 1, 2 IP Component Design Bases Inspection 7111121 06/04/2012 06/08/2012 1, 2 IP Component Design Bases Inspection 7111121 06/18/2012 06/22/2012 EB3 ISI-UNIT 1 INSERVICE INSPECTION & RPVH EXAMS 1 1 IP Inservice Inspection Activities - PWR 7111108P 03/19/2012 03/23/2012 PSB1-RP-OCCUPATIONAL RP BASELINE WK2 3 1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/26/2012 03/30/2012 1, 2 IP Occupational ALARA Planning and Controls 71124.02 03/26/2012 03/30/2012 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/26/2012 03/30/2012 1, 2 IP Occupational Dose Assessment 71124.04 03/26/2012 03/30/2012 1, 2 IP Radiation Monitoring Instrumentation 71124.05 03/26/2012 03/30/2012 1, 2 IP Performance Indicator Verification 71151 03/26/2012 03/30/2012 PSB1EP-EMERGENCY PREPAREDNESS EXERCISE 4 1, 2 IP Exercise Evaluation 7111401 07/09/2012 07/13/2012 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 07/09/2012 07/13/2012 1, 2 IP Performance Indicator Verification 71151 07/09/2012 07/13/2012 OL EXAM-INITIAL EXAM PREP 3 1 NORTH ANNA / JUNE 2012 EXAM AT POWER FACILITIES V23372 08/13/2012 08/17/2012 OL EXAM-INITIAL EXAM - WEEK 1 3 1 NORTH ANNA / JUNE 2012 EXAM AT POWER FACILITIES V23372 09/10/2012 09/14/2012 OL EXAM-INITIAL EXAM - WEEK 2 3 1 NORTH ANNA / JUNE 2012 EXAM AT POWER FACILITIES V23372 09/17/2012 09/21/2012 TI-177-TI-177 3 1, 2 IP Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 2515/177 10/22/2012 10/26/2012 NA TFPI-TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 IP Fire Protection [Triennial] |
| | 7111105T 11/06/2012 11/08/2012 This report does not include INPO and OUTAGE activities. |
| | This report shows only on-site and announced inspection procedures. |
| | Inspection / Activity Plan Page 2 of 2 03/05/2012 08:52:58 Report 22 03/01/2012 |
| | -06/30/2013 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site North Anna NA TFPI-TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 IP Fire Protection [Triennial] |
| | 7111105T 11/26/2012 11/30/2012 1, 2 IP Fire Protection [Triennial] |
| | 7111105T 12/10/2012 12/14/2012 TI-182-TI-182 BURIED PIPING/TANK - PHASE 1 1 1, 2 IP Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 2515/182 12/03/2012 12/07/2012 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 5 1, 2 IP Problem Identification and Resolution 71152B 03/11/2013 03/15/2013 1, 2 IP Problem Identification and Resolution 71152B 03/25/2013 03/29/2013 This report does not include INPO and OUTAGE activities. |
| | This report shows only on-site and announced inspection procedures.}} |
Revision as of 04:34, 30 July 2018
|
---|
Category:Inspection Plan
MONTHYEARIR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) IR 05000338/20230062024-02-28028 February 2024 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2023006 and 05000339/2023006 IR 05000338/20230052023-08-25025 August 2023 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338 2023005 and 05000339 2023005) IR 05000338/20220062023-03-0101 March 2023 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2022006 and 05000339/2022006 ML23046A1952023-02-15015 February 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000338/20220052022-08-30030 August 2022 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 Reports 05000338/2022005 and 05000339/2022005 IR 05000338/20210062022-03-0202 March 2022 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 (Reports No. 05000338/2021006 and 05000339/2021006) IR 05000338/20210052021-08-31031 August 2021 Mid-Cycle Letter Revised Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2021005 and 05000339/2021005) ML21165A1222021-06-14014 June 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21154A0662021-06-0202 June 2021 Notification of North Anna Power Station, Units 1 & 2 - Design Bases Assurance Inspection (Team) U.S. Nuuclear Regulatory Commission Inspection Report 05000338/2021010 and 05000339/2021010 ML21145A0052021-05-25025 May 2021 2021003 North Anna Nuclear Power Station Document Request Letter ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 IR 05000338/20200062021-03-0303 March 2021 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 NRC Inspection Reports 05000338/2020006 and 05000339/2020006 ML21028A4352021-01-28028 January 2021 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000338/2021404 and 05000339/2021404) ML21019A4512021-01-19019 January 2021 Notification of Inspection and Request for Information IR 05000338/20200052020-08-24024 August 2020 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2020005 and 05000339/2020005) ML20223A3412020-08-10010 August 2020 003 Radiation Safety Baseline Inspection Information Request ML20218A4282020-08-0505 August 2020 Notification of Inspection and Request for Information ML20182A0332020-06-30030 June 2020 Notification of Inspection and Request for Information ML20175A5532020-06-23023 June 2020 Emergency Preparedness Exercise Inspection Request for Information IR 05000338/20190062020-03-0303 March 2020 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2019006 and 05000339/2019006 ML19326C9882019-11-21021 November 2019 Requalification Program Inspection North Anna Power Station IR 05000338/20190052019-08-27027 August 2019 Updated Inspection Plan for North Anna Power Station, Units 1 and 2, NRC Report 05000338/2019005 and 05000339/2019005 ML19235A1992019-08-23023 August 2019 Baseline Inservice Inspection RFI IR 05000338/20180062019-03-0404 March 2019 Annual Assessment Letter for North Anna, Units 1 and 2; NRC Inspection Report 05000338/2018006 and 05000339/2018006 ML19030A6962019-01-29029 January 2019 ISI RFI IR 05000338/20180052018-08-23023 August 2018 Updated Inspection Plan for North Anna Power Station Units 1 and 2, NRC Report 05000338/2018005 and 05000339/2018005 ML18059A0942018-02-28028 February 2018 EOC Assessment Letter IR 05000338/20170052017-08-21021 August 2017 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 - Report 05000338/2017005 and 05000339/2017005 ML17156A0662017-06-0202 June 2017 Notification of Inspection and Request for Information IR 05000338/20160062017-03-0101 March 2017 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2016006 and 05000339/2016006 IR 05000338/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Report 05000338, 339/2016005 ML16222A9132016-08-0808 August 2016 Notification of Inspection and Request for Information IR 05000338/20150062016-03-0202 March 2016 Annual Assessment Letter for North Anna Power Station Units 1 and 2 - NRC Inspection Report 05000338/2015006 and 05000339/2015006 ML16013A0622016-01-12012 January 2016 North Anna Power Station, Unit 2 - Notification of Inspection and Request for Information IR 05000338/20150052015-09-0101 September 2015 Mid-Cycle Letter for North Anna Power Station, Units 1 and 2 - NRC Assessment Report 05000338/2015005 and 05000339/2015005 IR 05000338/20140012015-03-0404 March 2015 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2014001 and 05000339/2014001 ML14245A1902014-09-0202 September 2014 Mid-Cycle Ltr 2014 IR 05000338/20130012014-03-0404 March 2014 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2013001 and 05000339/2013001 ML14022A0412014-01-21021 January 2014 TI-182 Phase 2 RFI Final ML13246A1322013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000338/20120012013-03-0404 March 2013 Annual Assessment Letter North Anna, Units 1 and 2, 05000338/2012001 and 05000339/2012001 ML13037A1712013-02-0101 February 2013 Notification of Inspection and Request for Information ML13032A5532013-02-0101 February 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML12248A1102012-09-0404 September 2012 Mid Cycle Assessment Letter North Anna 2012 ML12235A2912012-08-17017 August 2012 IR 05000338-12-012, 05000339-12-012, on 10/28/2011, North Anna Power Station, Units 1 & 2 - Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML1206506412012-03-0505 March 2012 End of Cycle Assessment Report 22 ML1124400992011-09-0101 September 2011 Report 22, Inspection/Activity Plan ML1106303432011-03-0404 March 2011 Inspection/Activity Plan 03/01/2011 - 06/30/2012, EOC Report 22 ML1024402812010-09-0101 September 2010 Report 22 - 2010 Mid Cycle Inspection/Activity Plan 2024-08-27
[Table view] Category:Inspection Report
MONTHYEARIR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) IR 05000338/20240022024-08-0202 August 2024 Integrated Inspection Report 05000338/2024002 and 05000339/2024002 IR 05000338/20240012024-05-10010 May 2024 Integrated Inspection Report 05000338/2024001 and 05000339/2024001 IR 05000338/20244032024-04-30030 April 2024 – Security Baseline Inspection Report 05000338-2024403 and 05000339-2024403 IR 05000338/20244012024-03-0808 March 2024 Security Baseline Inspection Report 05000338/2024401, 05000339/2024401 and 07200016/2024401 IR 05000338/20230062024-02-28028 February 2024 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2023006 and 05000339/2023006 IR 05000338/20240102024-02-22022 February 2024 Notification of an NRC Fire Protection Team Inspection - NRC Inspection Report 05000338/2024010- 05000339/2024010- RFI IR 05000338/20230042024-02-12012 February 2024 Integrated Inspection Report 05000338/2023004 and 05000339/2023004 IR 05000339/20234022023-11-27027 November 2023 Security Baseline Inspection Report 05000338 and 05000339/2023402 IR 05000338/20230032023-11-13013 November 2023 Integrated Inspection Report 05000338/2023003 and 05000339/2023003 IR 05000338/20234032023-10-0505 October 2023 Reissue - North Anna Power Station - Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 (Cover Letter) IR 05000338/20230112023-09-26026 September 2023 Quadrennial Focused Engineering Inspection Commercial Grade Dedication Report 05000338/2023011 and 05000339/2023011 IR 05000338/20230052023-08-25025 August 2023 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338 2023005 and 05000339 2023005) IR 05000338/20230022023-08-0909 August 2023 Integrated Inspection Report 05000338/2023002 and 05000339/2023002 IR 05000338/20234012023-07-13013 July 2023 Security Baseline Inspection Report 050003382023401 and 050003392023401 - Cover Letter IR 05000338/20230102023-05-31031 May 2023 Biennial Problem Identification and Resolution Inspection Report 05000338/2023010 and 05000339/2023010 IR 05000338/20230012023-05-0202 May 2023 Integrated Inspection Report 05000338/2023001 and 05000339/2023001 IR 05000338/20220062023-03-0101 March 2023 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2022006 and 05000339/2022006 IR 05000338/20220042023-02-0909 February 2023 Integrated Inspection Report 05000338/2022004 and 05000339/2022004 IR 05000338/20224402023-02-0101 February 2023 NRC Security Inspection Report 05000338/2022440 and 05000339/2022440 and Investigation Report 2-2021-001 and Notice of Violation Cover Letter IR 05000338/20224012023-01-31031 January 2023 Material Control and Accounting Program Inspection Report 05000338/2022401 and 05000339/2022401 - Cover ML23013A0142023-01-13013 January 2023 Information Request for the Cyber-Security Baseline Security Inspection, Notification to Perform Inspection 05000338/2023403 and 05000339/2023403 IR 05000338/20220032022-12-20020 December 2022 Reissue - North Anna Power Station Integrated Inspection Report 05000338/2022003 and 05000339/2022003 IR 05000338/20220012022-12-15015 December 2022 Reissue - North Anna Power Station Integrated Inspection Report 05000338/2022001 and 05000339/2022001 and 07200056/2022001 ML22311A5422022-11-0707 November 2022 Integrated Inspection Report 05000338/2022003 and 05000339/2022003 IR 05000338/20220102022-09-26026 September 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000338 2022010 and 05000339 2022010 IR 05000338/20224022022-08-31031 August 2022 Security Baseline Inspection Report 05000338/2022402 and 05000339/2022402 IR 05000338/20220052022-08-30030 August 2022 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 Reports 05000338/2022005 and 05000339/2022005 IR 05000338/20220022022-08-11011 August 2022 Integrated Inspection Report 05000338/2022002 and 05000339/2022002 IR 05000339/20220012022-05-13013 May 2022 Integrated Inspection Report 05000338/ 2022001 and 05000339/2022001 and 07200056/2022001 IR 05000338/20210062022-03-0202 March 2022 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 (Reports No. 05000338/2021006 and 05000339/2021006) IR 05000338/20210042022-02-14014 February 2022 Integrated Inspection Report, 05000338/2021004 and 05000339/2021004 IR 05000338/20214032021-12-0808 December 2021 Security Baseline Inspection Report 05000338/2021403 and 05000339/2021403 IR 05000338/20210102021-11-18018 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000338/2021010 and 05000339/2021010 IR 05000338/20210032021-11-12012 November 2021 Integrated Inspection Report 05000338/2021003 and 05000339/2021003 IR 05000338/20210132021-10-13013 October 2021 Biennial Problem Identification and Resolution Inspection Report 05000338/2021013 and 05000339/2021013 IR 05000338/20210052021-08-31031 August 2021 Mid-Cycle Letter Revised Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2021005 and 05000339/2021005) IR 05000338/20210022021-07-27027 July 2021 Integrated Inspection Report 05000338/2021002 and 05000339/2021002 ML21196A4112021-07-19019 July 2021 Inspection Report IR 05000338/20210122021-06-25025 June 2021 Triennial Fire Protection Inspection Report 05000338/2021012 and 05000339/2021012 IR 05000338/20214042021-06-14014 June 2021 Security Baseline Inspection Report 05000338/2021404 and 05000339/2021404 IR 05000338/20214022021-05-25025 May 2021 Unit and 2 - Security Baseline Inspection Report 05000338/2021402 and 05000339/2021402 IR 05000338/20210012021-05-11011 May 2021 Integrated Inspection Report 05000338/2021001 and 05000339/2021001 IR 05000338/20200062021-03-0303 March 2021 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 NRC Inspection Reports 05000338/2020006 and 05000339/2020006 IR 05000338/20214012021-02-10010 February 2021 Security Baseline Inspection Report 05000338/2021401, 05000339/2021401, 07200016/2021401, and 07200056/2021401 IR 05000338/20200042021-01-28028 January 2021 Integrated Inspection Report 05000338/2020004 and 05000339/2020004; 07200016/2020002 IR 05000339/20204112020-12-22022 December 2020 Cyber Security Inspection Report 05000338/ 2020411 and 05000339/2020411 (Public) IR 05000338/20200032020-11-0505 November 2020 Integrated Inspection Report 05000338/2020003 and 05000339/2020003 and Exercise of Enforcement Discretion IR 05000338/20203012020-09-16016 September 2020 NRC Operator License Examination Report 05000338/2020301, 05000339/2020301 IR 05000338/20200052020-08-24024 August 2020 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2020005 and 05000339/2020005) 2024-08-27
[Table view] |
Text
Inspection / Activity Plan Page 1 of 2 03/05/2012 08:52:58 Report 22 03/01/2012
-06/30/2013 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site North Anna PSB1-RP-OCCUPATIONAL RP BASELINE WK1 3 1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/12/2012 03/16/2012 1, 2 IP Occupational ALARA Planning and Controls 71124.02 03/12/2012 03/16/2012 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/12/2012 03/16/2012 1, 2 IP Occupational Dose Assessment 71124.04 03/12/2012 03/16/2012 1, 2 IP Radiation Monitoring Instrumentation 71124.05 03/12/2012 03/16/2012 1, 2 IP Performance Indicator Verification 71151 03/12/2012 03/16/2012 CDBI-COMPONENT DESIGN BASES INSPECTION 5 1, 2 IP Component Design Bases Inspection 7111121 04/30/2012 05/04/2012 1, 2 IP Component Design Bases Inspection 7111121 05/21/2012 05/25/2012 1, 2 IP Component Design Bases Inspection 7111121 06/04/2012 06/08/2012 1, 2 IP Component Design Bases Inspection 7111121 06/18/2012 06/22/2012 EB3 ISI-UNIT 1 INSERVICE INSPECTION & RPVH EXAMS 1 1 IP Inservice Inspection Activities - PWR 7111108P 03/19/2012 03/23/2012 PSB1-RP-OCCUPATIONAL RP BASELINE WK2 3 1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/26/2012 03/30/2012 1, 2 IP Occupational ALARA Planning and Controls 71124.02 03/26/2012 03/30/2012 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/26/2012 03/30/2012 1, 2 IP Occupational Dose Assessment 71124.04 03/26/2012 03/30/2012 1, 2 IP Radiation Monitoring Instrumentation 71124.05 03/26/2012 03/30/2012 1, 2 IP Performance Indicator Verification 71151 03/26/2012 03/30/2012 PSB1EP-EMERGENCY PREPAREDNESS EXERCISE 4 1, 2 IP Exercise Evaluation 7111401 07/09/2012 07/13/2012 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 07/09/2012 07/13/2012 1, 2 IP Performance Indicator Verification 71151 07/09/2012 07/13/2012 OL EXAM-INITIAL EXAM PREP 3 1 NORTH ANNA / JUNE 2012 EXAM AT POWER FACILITIES V23372 08/13/2012 08/17/2012 OL EXAM-INITIAL EXAM - WEEK 1 3 1 NORTH ANNA / JUNE 2012 EXAM AT POWER FACILITIES V23372 09/10/2012 09/14/2012 OL EXAM-INITIAL EXAM - WEEK 2 3 1 NORTH ANNA / JUNE 2012 EXAM AT POWER FACILITIES V23372 09/17/2012 09/21/2012 TI-177-TI-177 3 1, 2 IP Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 2515/177 10/22/2012 10/26/2012 NA TFPI-TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 IP Fire Protection [Triennial]
7111105T 11/06/2012 11/08/2012 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Inspection / Activity Plan Page 2 of 2 03/05/2012 08:52:58 Report 22 03/01/2012
-06/30/2013 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site North Anna NA TFPI-TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 IP Fire Protection [Triennial]
7111105T 11/26/2012 11/30/2012 1, 2 IP Fire Protection [Triennial]
7111105T 12/10/2012 12/14/2012 TI-182-TI-182 BURIED PIPING/TANK - PHASE 1 1 1, 2 IP Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 2515/182 12/03/2012 12/07/2012 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 5 1, 2 IP Problem Identification and Resolution 71152B 03/11/2013 03/15/2013 1, 2 IP Problem Identification and Resolution 71152B 03/25/2013 03/29/2013 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.