IR 05000338/2022004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000338/2022004 and 05000339/2022004
ML23040A030
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 02/09/2023
From: Matthew Fannon
NRC/RGN-II/DRP/RPB4
To: Stoddard D
Dominion Energy Co
References
IR 2022004
Download: ML23040A030 (19)


Text

SUBJECT:

NORTH ANNA POWER STATION, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000338/2022004 AND 05000339/2022004

Dear Mr. Stoddard:

On December 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at North Anna Power Station, Units 1 and 2. On January 25, 2023, the NRC inspectors discussed the results of this inspection with Mr. James Jenkins and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Matthew S. Fannon, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos. 05000338 and 05000339 License Nos. NPF-4 and NPF-7

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000338 and 05000339

License Numbers:

NPF-4 and NPF-7

Report Numbers:

05000338/2022004 and 05000339/2022004

Enterprise Identifier:

I-2022-004-0029

Licensee:

Virginia Electric & Power Company; Dominion Energy

Facility:

North Anna Power Station, Units 1 and 2

Location:

Mineral, VA

Inspection Dates:

October 01, 2022, to December 31, 2022

Inspectors:

K. Carrington, Senior Resident Inspector

D. Bacon, Senior Operations Engineer

D. Jung, Project Engineer

B. Smith, Nuclear Systems Engineer

D. Turpin, Resident Inspector

A. Wilson, Senior Project Engineer

Approved By:

Matthew S. Fannon, Chief

Reactor Projects Branch 4

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at North Anna Power Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period shutdown for Refuel Outage 1R29. The unit was restarted, and the generator was synchronized to the grid on October 26. The unit reached rated thermal power on October 28, where it continued to operate for the remainder of the inspection period.

Unit 2 began the inspection period operating at or near rated thermal power, where it remained through the end of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated whether flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding in the Unit 2 safeguards building, on November 28, 2022.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 "A" and "B" motor-driven auxiliary feedwater (AFW) systems following performance of 1-PT-71.2Q and 1-PT-71.3Q, on October 20, 2022
(2) Unit 1 "A" and "B" inside recirculation spray systems prior to unit transition to Mode 4, on October 26, 2022
(3) Unit 2 "A" and "C" main control room chiller systems following "A" main control room chiller maintenance, on December 13, 2022

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 1 residual heat removal system, on October 6, 2022.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 9A-2, Unit 2 "H" emergency diesel generator (EDG) room, on October 4, 2022
(2) Fire Zone 9B-1, Unit 1 "J" EDG room, on October 4, 2022
(3) Fire Zone 9A-1, Unit 1 "H" EDG room, on October 4, 2022
(4) Fire Zone 15-1, Unit 1 quench spray building, on December 28, 2022
(5) Fire Zone 7C-2, Unit 2 2-III battery room, on December 29, 2022

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Unit 1 quench spray pump house, on October 31, 2022

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The licensee completed the annual requalification operating examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2), "Requalification Requirements," of the NRC's "Operator's Licenses." During the week of November 7, 2022, the inspector performed an in-office review of the overall pass/fail results of the individual operating examinations and the crew simulator operating examinations in accordance with Inspection Procedure (IP) 71111.11, "Licensed Operator Requalification Program." These results were compared to the thresholds established in Section 3.03, "Requalification Examination Results," of IP 71111.11.

The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam completed on February 25, 2022.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the main control room during Unit 1 startup from refueling outage (RFO) 1R29, on October 20, 2022.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator training in the simulator, on November 15, 2022.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (4 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 1 1-SW-MOV-101D leak-by associated with condition report (CR) 1211470 on October 29, 2022
(2) Units 1 and 2 boric acid transfer pumps 2A, 2B, 2C, and 2D, associated with CR1173153, CR1175543, CR1191821, CR1201239, CR1203440, and CR1208156, on November 2, 2022
(3) Unit 2 "J" EDG associated with CA11202928 and CA11198262, on November 8, 2022
(4) Unit 1 and 2 main control room chiller service water piping due to recent microbiologically induced corrosion leaks, on December 30, 2022

Aging Management (IP Section 03.03) (1 Sample)

The inspectors evaluated the effectiveness of the aging management program for the following SSCs that did not meet their inspection or test acceptance criteria:

(1) CR1209780, As-Found License Renewal Inspection Unsatisfactory

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (2 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Preconditioning of Unit 1 feedwater pump discharge motor-operated valves during performance of 1-PT-210.26, on December 14, 2022
(2) CR1213309, 2-III Battery Room Door Issues, on December 16, 2022

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Design Changes NA-21-00046 and NA-21-00021, associated with the removal of Unit 2 'B' hot leg loop stop isolation valve internals

Severe Accident Management Guidelines (SAMG) Update (IP Section 03.03) (1 Sample)

(1) The inspectors verified the site Severe Accident Management Guidelines (SAMGs)were updated in accordance with the pressurized water reactors generic SAMG technical guidelines and validated in accordance with Nuclear Energy Institute (NEI)14-01, Emergency Response Procedures and Guidelines for Beyond Design Basis Events and Severe Accidents, Revision 1.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (10 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1)0-MCM-0300-03, packing adjustment with thrust verification testing of "A" low head safety injection pump recirculation motor-operated valve (MOV), 1-SI-MOV-1885C, following planned maintenance under work orders (WOs) 59203285567 and

===59203297752, on October 4, 2022 (2)1-PT-78.4 and 1-PT-214.16, in-service inspection and remote valve position indication verification testing of residual heat removal system valves, 1-RHR-MOV-1700A, -1700B, and -1701, following planned maintenance during RFO 1R29, on October 5, 2022 (3)0-ECM-1509-03, testing of quarter turn MOVs, 1-SW-MOV-104A and 1-SW-MOV-104B, following planned maintenance under WOs 59203300979 and 59203300982, on October 5, 2022 (4)1-PT-88.4J, modified performance testing of I-IV station battery, following planned maintenance under WO 59101803884, on October 12, 2022 (5)1-PT-61.1, integrated leak-rate testing of Unit 1 containment, following RFO 1R29, on October 16, 2022 (6)1-PT-71.2Q, testing of 1-FW-P-3B, "B" motor-driven AFW (MDAFW) pump and valve system, following planned maintenance under WOs 59203387457 and 59203293493, on October 20, 2022 (7)1-PT-71.2Q, testing of 1-FW-P-3A, "A" MDAFW pump and valve system, following planned maintenance under WO 59203386675, on October 20, 2022 (8)0-PT-82.11, testing of alternate AC diesel generator (station blackout diesel 0-AAC-DG-OM), following unplanned maintenance under WOs 59203397436 and 59203397470, on November 10, 2022 (9)1-PT-201.12, in-service inspection and testing of reactor coolant gaseous vent system solenoid operated valves, 1-RC-SOV-101B-1, and 1-RC-SOV-101B-2, following RFO 1R29, on November 17, 2022 (10)2-OP-21.6, testing of Unit 2 'B' main control room chiller, 2-HV-E-4B, following unplanned maintenance under WO 59203398384, on December 12, 2022

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01)===

(1) The inspectors evaluated Unit 1 refueling outage 1R29 activities from October 1, 2022 to October 26, 2022.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:

Inservice Testing (IP Section 03.01) (1 Sample)

(1)2-PT-57.1B, Low Head Safety Injection Pump (2-SI-P-1B) Inservice Test, on November 12, 2022

FLEX Testing (IP Section 03.02) (1 Sample)

(1) Beyond Design Basis (BDB) AFW Pump Triennial Functional Testing associated with WO 59203194100

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) Emergency Plan (EP) Drill NDEC22FSD associated with a large break loss of coolant accident, medical emergency, and fuel failure, on December 6, 2022

Drill/Training Evolution Observation (IP Section 03.02) (2 Samples)

The inspectors evaluated:

(1) EP proficiency training drill on November 17, 2022
(2) EP proficiency training drill on December 1,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (October 1, 2021 through September 30, 2022)
(2) Unit 2 (October 1, 2021 through September 30, 2022)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (October 1, 2021 through September 30, 2022)
(2) Unit 2 (October 1, 2021 through September 30, 2022)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) CR1192702, Incorrect fuse sizes in replacement motor control center (MCC) buckets;
(2) CR1209614, 1-CC-RV-104C failed as left seat integrity test, and CR1209516, 1-SI-RV-1894 failed as found seat integrity testing
(3) CR1212064 and CR1211940 related to Surry main feedwater bypass susceptibility to flow accelerated corrosion (FAC) wear (log 11/08)
(4) CR 1194292 (Surry CR) related to application of safety-related DC breakers in AC application
(5) CR1213473 U2 Chemical addition tank indicating erratically

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in pump vibrations and oil analysis that might be indicative of a more significant safety issue.

INSPECTION RESULTS

Observation: Semi-Annual Trend Review of Oil and Vibration Analysis 71152S The inspectors reviewed the licensee's corrective program to determine if a potentially adverse trend existed in human performance or equipment reliability related to increased vibrations and oil particulates for various pumps and motors, which could be indicative of a more significant safety concern. Specifically, the inspectors reviewed the following condition reports generated in the last year related to particulate discovered in oil samples for 01-CN-P-1B (Unit 1 B condensate pump) and 1-CH-P-1C-MOTOR (Unit 1 C charging pump) and elevated vibrations in pumps 1-FC-P-1B (B spent fuel pit cooling pump), 2-FW-P-3A (A motor-driven auxiliary feedwater pump), and 1-SW-P-4 (no. 4 auxiliary service water pump):

CR1203250, CR1202766, CR1206113, CR1198472, CR1202941 The inspectors noted that the station independently evaluated each issue, however the corrective actions and evaluations did not consider if a common-cause or theme for degradation existed in pumps across different systems. The inspectors noted the stations process for trending similar components across various systems focused primarily on components on the stations top equipment list and that based on this approach there may be a common cause or contributor that has not been evaluated.

In addition to the broader trend discussion, the inspectors questioned how station personnel identified degrading oil color quality. The inspectors noted the stations procedure evaluates oil quality by visually identifying color changes using a visual aid across a spectrum which the inspectors determined to have many gradations. These gradations were so similar in color that the inspectors asked maintenance personnel how they would determine two color changes, which is the procedural criteria to determine if a sample is unsatisfactory. Station personnel acknowledged the inspectors concern and informed the inspectors that action was being pursued to evaluate a more reliable method to be used.

No findings of significance were identified as a result of this inspection.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On January 25, 2023, the inspectors presented the integrated inspection results to Mr.

James Jenkins, Nuclear Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Calibration

Records

CR 1152820

Rain Water and Ground Water Intrusion

08/04/2020

71111.01

Corrective Action

Documents

CR 1140865

Excessive Water Intrusion Around Ductwork While Raining

2/07/2020

71111.01

Corrective Action

Documents

CR 1174971

Rain water is leaking into Unit 1 and unit 2 Safeguards

06/11/2021

71111.01

Miscellaneous

SDBD-NAPS-RS

System Design Basis Document for Recirculation Spray

System

71111.01

Work Orders

203314347

Rain Water Intrusion

08/05/2020

71111.01

Work Orders

WO 59203367644

Rain water is leaking into Unit 1 and unit 2 Safeguards

6/14/2021

71111.01

Work Orders

WO 59203367645

Rain water is leaking into Unit 1 and unit 2 Safeguards

06/14/2021

71111.04

Corrective Action

Documents

CR 1214932

2-SW-PP-4.00-WS-PIPE-H138-163-Q3 has a MIC leak

2/09/2022

71111.04

Drawings

11715-FB-40D

Flow/Valve Operating Numbers Diagram Air Conditioning

Condenser Water System North Anna Power Station Unit 2

Virginia Power

71111.04

Drawings

11715-FB-40E

Flow/Valve Operating Numbers Diagram Air Conditioning

Refrigerant System North Anna Power Station - Units 1 & 2

Virginia Power

71111.04

Drawings

11715-FM-074A,

Sheet 1

Flow/Valve Operating Numbers Diagram, Feedwater

System, North Anna Power Station, Unit 1

71111.04

Drawings

11715-FM-091B,

Sheet 1

Flow/Valve Operating Numbers Diagram, Cont Quench &

Recirc Spray Sub Sys, North Anna Power Station Unit 1

71111.04

Drawings

11715-FM-094A,

Sheet 1

FLOW/VALVE OPERATING NUMBERS DIAGRAM-

RESIDUAL HEAT REMOVAL SYSTEM, NORTH ANNA

POWER STATION UNIT 1

71111.04

Drawings

11715-FM-094A,

Sheet 2

FLOW/VALVE OPERATING NUMBERS DIAGRAM -

RESIDUAL HEAT REMOVAL SYSTEM, NORTH ANNA

POWER STATION UNIT 1

71111.04

Drawings

11715-FM-91A,

Sheet 1

Flow/Valve Operating Numbers Diagram, Cont Quench &

Recirc Spray Sub Sys, North Anna Power Station Unit 1

71111.04

Procedures

0-OP-49.9A

Valve Checkoff - Control Room A/C Service Water

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Procedures

1-OP-14A

Valve Checkoff - Residual Heat Removal

71111.04

Procedures

2-OP-21.6

Main Control and Relay Room Air Conditioning

71111.04

Work Orders

WO 59203398384

2-SW-PP-4.00-WS-PIPE-H138-163-Q3 has a MIC leak

2/14/2022

71111.05

Engineering

Evaluations

ETE-NA-2011-0021

Evaluation of Permanently Stored Combustible Material

Rev 9

71111.05

Procedures

0-FS-CT-1

Cable Tray Spreading Room and Battery Room 2-1. 1-1, 2-

3, 1-3

Rev 5

71111.05

Procedures

1-FPMP-2.7

Fire Extinguisher Inspector-Service Building and Misc

71111.05

Procedures

1-FS-QS-1

Quench Spray Building (SG-74) Unit 1

71111.05

Procedures

1-FS-QS-1

Quench Spray Building (SG-74) Unit 1

Rev 5

71111.05

Procedures

CM-AA-FPA-100

Fire Protection/Appendix R (Fire Safe Shutdown) Program

Rev 19

71111.05

Procedures

CM-AA-FPA-100

Fire Protection/Appendix R (Fire Safe Shutdown) Program

71111.05

Procedures

CM-AA-FPA-101

Control of Combustible and Flammable Materials

Rev 15

71111.12

Calibration

Records

CR1151122,

CR11882246,

CR1214932

71111.12

Corrective Action

Documents

CA11202928,

CA11198262

71111.12

Corrective Action

Documents

CR1173153,

CR1175543,

CR1191821,

CR1201239,

CR1203440, and

CR1208156

71111.12

Corrective Action

Documents

CR1209780

71111.12

Corrective Action

Documents

CR1211470

71111.12

Corrective Action

Documents

LA302037

Update DNES-AA-GN-1002 and DNES-AA-GN-1003

71111.12

Corrective Action

LA302044

Update EP-AA-504 as necessary

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

71111.12

Corrective Action

Documents

LC1023117

Commitment to Maintain Severe Accident Management

Guidelines

71111.12

Miscellaneous

CA8520676

Level of Effort Evaluation for 1-CH-P-2D-Pump

6/22/2021

71111.12

Miscellaneous

New PWROG

SAMG Technical

Guidelines, North

Anna FSRC

Presentation

1/17/2019

01/17/2019

71111.12

Miscellaneous

NU-REG 1766

Docket Nos. 50-338, 50-339, 50-280, and 50-281, Safety

Evaluation Report Related to the License Renewal of North

Anna Power Station, Units 1 and 2, and Surry Power

Station, Units 1 and 2

71111.12

Miscellaneous

Serial No.15-538

SAMG Commitments

2/18/2015

71111.12

Procedures

DNES-AA-GN-1002

Document Impact Summary

71111.12

Procedures

DNES-AA-GN-1002

Document Impact Summary

71111.12

Procedures

EP-AA-504

Severe Accident Management (SAM) Program

Administration

71111.12

Procedures

EP-AA-504

Severe Accident Management (SAM) Program

Administration

71111.12

Work Orders

203326109

71111.15

Corrective Action

Documents

CR 1213309

2-III Battery Room Door Issues

11/18/2022

71111.15

Corrective Action

Documents

CR 1213566

Unit 2 Entered 2 Hour Limiting TS 3.8.4.A due to 2-III

Battery Room Steel Door Issues

11/22/2022

71111.15

Corrective Action

Documents

CR 1213715

2-BLD-STR-S94-9 remains Non-Functional following 7 day

action of TR 7.2.A.2

11/24/2022

71111.15

Corrective Action

Documents

CR1213501

2-III Battery Room Rolling Steel Door is difficult to operate

11/21/2022

71111.15

Engineering

Evaluations

ETE-NA-2022-0056

2-BLD-STR-S94-9 (2-III Battery Room Door) Repair

71111.15

Miscellaneous

SDBD-NAPS-FW

System Design Basis Document for Feedwater System

Rev 25

71111.15

Procedures

1-PT-210.26

Valve Inservice Inspection (Feedwater Pump Discharge

10/21/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

MOVs)

71111.15

Procedures

1-PT-210.26

Valve Inservice Inspection (Feedwater Pump Discharge

MOVs)

09/20/2022

71111.15

Procedures

1-PT-210.26

Valve Inservice Inspection (Feedwater Pump Discharge

MOVs)

Rev 2

71111.15

Work Orders

WO 59102840210

As Found Periodic Verification MOV Test

10/02/2022

71111.15

Work Orders

WO 59203298422

MOV Stem Inspection/Lubrication

10/02/2022

71111.15

Work Orders

WO 59203397717

2-III Battery Room Door Issues

11/18/2022

71111.15

Work Orders

WO 59203397761

Repair Door IAW ETE-NA-2022-0056

11/23/2022

71111.18

Calculations

NA-CALC-MEC-

EDNS04000014089

Computational Fluid Dynamics simulation of the Loop Stop

Valve at north Anna

Rev 1

71111.18

Corrective Action

Documents

CR 1194578

2-RC-MOV-2592 B Hot Loop Isolation Valve

03/23/2022

71111.18

Corrective Action

Documents

CR1176178

A Programmatic Work Order is needed to install DC NA-21-

00046

07/01/2021

71111.18

Engineering

Changes

DC NA-12-00028

1-RC-MOV-1595 Disc Removal

04/17/2012

71111.18

Engineering

Changes

DC NA-21-00046

Repair Reactor Coolant Loop Stop Valve2-RC-MOV-2592

Rev 0

71111.18

Engineering

Changes

DC NA-22-00021

2-RC-MOV-2592 Internals Removal

Rev 0

71111.18

Engineering

Changes

ET-CEM-10-0002

Evaluation for Reactor Coolant Loop Piping for Temporary

Modification of 2-RC-MOV-2593 per DC NA-10-00122

Rev 0

71111.18

Engineering

Evaluations

DC NA-10-00122

Removal of discs from 2-RC-MOV-2593

04/06/2010

71111.18

Miscellaneous

50.59 Applicability for Enhanced SAMG Procedure

Implementation Package

01/15/2019

71111.18

Miscellaneous

New PWROG SAMG Technical Guidelines - North Anna -

FSRC Presentation 01/17/19

01/17/2019

71111.18

Miscellaneous

CME 01-0036

RCS Valve Stem Embrittlement Evaluation North Anna &

Surry Power Stations - Units 1 & 2

Rev 0

71111.18

Miscellaneous

FSRC Agenda

Notes from

01/23/2019

Dominion SAMG Project Update Timeline

01/23/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.18

Miscellaneous

LA3020237

Update DNES-AA-GN-1002 and DNES-AA-GN-1003

71111.18

Miscellaneous

LA3020244

Update EP-AA-504 as necessary

71111.18

Miscellaneous

LC1023117

Commitment to Maintain Severe Accident Management

Guidelines

71111.18

Miscellaneous

NAPS-UCR-2022-

005

2-RC-MOV-2595 Internals Removal

03/24/2022

71111.18

Miscellaneous

Serial No.15-538

SAMG Commitments

2/22/2015

71111.18

Procedures

DNES-AA-GN-1002

Document Impact Summary

71111.18

Procedures

EP-AA-504

Severe Accident Management (SAM) Program

Administration

71111.18

Procedures

EP-AA-504

Severe Accident Management (SAM) Program

Administration

71111.18

Work Orders

203368342

Internal Inspection / Repair (DC 21-00046)(Sec XI)(SPV)

7/14/2022

71111.18

Work Orders

WO 59203384153

Perform DC-22-00021 Requirements / PMT

03/27/2022

71111.18

Work Orders

WO 59203384279

Install Valve Bonnet without Disc / Guides IAW AWA 1 to

DC NA-22-00021

04/18/2022

71111.19

Corrective Action

Documents

CR 1212445

Bolts Missing on the Starting Air Line Downstream on SBO

Diesel

11/09/2022

71111.19

Corrective Action

Documents

CR 1212590

SBO Diesel Keine Valves on cylinders 2 and 12 require

replacement

11/10/2022

71111.19

Corrective Action

Documents

CR 1213207

00-AAC-DG-0M Performed Abbreviated Maintenance

11/17/2022

71111.19

Corrective Action

Documents

CR 1214932

2-SW-PP-4.00-WS-PIPE-467-151-Q3 has a MIC Leak

2/09/2022

71111.19

Corrective Action

Documents

Resulting from

Inspection

CR1210829

NRC identified - excessive leakage from 1-FW-P-3B OB

packing during pump PT

10/20/2022

71111.19

Engineering

Changes

EE-0009

25 Vdc System Analysis

01/16/2018

71111.19

Miscellaneous

Nu-Reg 1483

Performance-Based Containment Leak-Test Program

July 1995

71111.19

Procedures

0-ECM-1509-03

MOV Testing - Quarter Turn Valves

Rev. 1

71111.19

Procedures

0-MCM-0300-03

MOV Packing Adjustment with Thrust Verification Testing

Rev. 10

71111.19

Procedures

0-PT-82.11

Quarterly Test of 0-AAC-DG-OM, Alternate AC Diesel

Rev 37

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Generator (SBO Diesel), On D Transfer Bus

71111.19

Procedures

01-PT-71.2Q

1-FW-P-3A, A Motor-Driven AFW Pump and Valve Test

71111.19

Procedures

1-PT-61.1

Reactor Containment Integrated Leak Rate Test

71111.19

Procedures

1-PT-71.3Q

1-FW-P-3B, B Motor-Driven AFW Pump and Valve Test

71111.19

Procedures

2-PT-88.3J

Station Battery 2-III Modified Performance Test

71111.19

Work Orders

203285567

71111.19

Work Orders

203297752

71111.19

Work Orders

203300979

71111.19

Work Orders

203300982

71111.19

Work Orders

WO 59203378607

Oil Sample/Data Collection/Maintenance Inspection

11/23/2022

71111.19

Work Orders

WO 59203397436

Bolts missing from flange to Turbocharger / Repair Replace

11/14/2022

71111.19

Work Orders

WO 59203397470

Kiene Indicator valves on cylinders 2 and 12 require

replacement

11/17/2022

71111.19

Work Orders

WO 59203398384

2-SW-PP-4.00-WS-PIPE-467-151-Q3 has a MIC Leak

71111.20

Corrective Action

Documents

CR1208989

71111.20

Miscellaneous

Work Schedules for Protected Workers during 1R29

71111.20

Miscellaneous

N1R29 Report

Core Reload Assessment

10/03/2022

71111.20

Procedures

1-OP-1.5

Unit Startup from Mode 3 to Mode 2

71111.20

Procedures

1-OP-3.7

71111.22

Miscellaneous

SDBD-NAPS-SI

"System Design Basis Document For Safety Injection

System North Anna Power Station"

71111.22

Procedures

2-PT-57.1B

"Emergency Core Cooling Subsystem - Low Head Safety

Injection Pump (2-SI-P-1B)"

71111.22

Procedures

O-MPM-2000-06

BDB AFW Pump Triennial Functional Testing 0-BDB-P-2A,

0-BDB-P-2B and 0-BDB-P-2C

08/23/2021

71111.22

Work Orders

WO 59203194100

EWP 3 Year Functional Testing

71114.06

Miscellaneous

EP-AA-103,

39

Classification Opportunity (Dep) for Drill Scenario

NDEC22FSD in Simulator, TSC, and CERC for Alert, Site

Area, and General Emergency Classifications

71114.06

Miscellaneous

EPIP 1.01, Page 3

Emergency Manager Controlling Procedure (for Drill

Scenario NDEC22FSD)

71114.06

Miscellaneous

EPIP 4.07,

Radiological Protective Action Recommendations for

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

3, Rev

NDEC22FSD

71114.06

Miscellaneous

NFAD-TSC

22 NAPS Proficiency Drill and DEP PI

71152A

Corrective Action

Documents

CR 1194292

71152A

Corrective Action

Documents

CR1192702

71152A

Corrective Action

Documents

CR1209614

71152A

Corrective Action

Documents

CR1211940

71152A

Corrective Action

Documents

CR1212064

71152A

Corrective Action

Documents

CR1213473

71152S

Corrective Action

Documents

CR1203250