MONTHYEARIR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) IR 05000338/20230062024-02-28028 February 2024 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2023006 and 05000339/2023006 IR 05000338/20230052023-08-25025 August 2023 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338 2023005 and 05000339 2023005) IR 05000338/20220062023-03-0101 March 2023 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2022006 and 05000339/2022006 ML23046A1952023-02-15015 February 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000338/20220052022-08-30030 August 2022 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 Reports 05000338/2022005 and 05000339/2022005 IR 05000338/20210062022-03-0202 March 2022 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 (Reports No. 05000338/2021006 and 05000339/2021006) IR 05000338/20210052021-08-31031 August 2021 Mid-Cycle Letter Revised Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2021005 and 05000339/2021005) ML21165A1222021-06-14014 June 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21154A0662021-06-0202 June 2021 Notification of North Anna Power Station, Units 1 & 2 - Design Bases Assurance Inspection (Team) U.S. Nuuclear Regulatory Commission Inspection Report 05000338/2021010 and 05000339/2021010 ML21145A0052021-05-25025 May 2021 2021003 North Anna Nuclear Power Station Document Request Letter ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 IR 05000338/20200062021-03-0303 March 2021 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 NRC Inspection Reports 05000338/2020006 and 05000339/2020006 ML21028A4352021-01-28028 January 2021 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000338/2021404 and 05000339/2021404) ML21019A4512021-01-19019 January 2021 Notification of Inspection and Request for Information IR 05000338/20200052020-08-24024 August 2020 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2020005 and 05000339/2020005) ML20223A3412020-08-10010 August 2020 003 Radiation Safety Baseline Inspection Information Request ML20218A4282020-08-0505 August 2020 Notification of Inspection and Request for Information ML20182A0332020-06-30030 June 2020 Notification of Inspection and Request for Information ML20175A5532020-06-23023 June 2020 Emergency Preparedness Exercise Inspection Request for Information IR 05000338/20190062020-03-0303 March 2020 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2019006 and 05000339/2019006 ML19326C9882019-11-21021 November 2019 Requalification Program Inspection North Anna Power Station IR 05000338/20190052019-08-27027 August 2019 Updated Inspection Plan for North Anna Power Station, Units 1 and 2, NRC Report 05000338/2019005 and 05000339/2019005 ML19235A1992019-08-23023 August 2019 Baseline Inservice Inspection RFI IR 05000338/20180062019-03-0404 March 2019 Annual Assessment Letter for North Anna, Units 1 and 2; NRC Inspection Report 05000338/2018006 and 05000339/2018006 ML19030A6962019-01-29029 January 2019 ISI RFI IR 05000338/20180052018-08-23023 August 2018 Updated Inspection Plan for North Anna Power Station Units 1 and 2, NRC Report 05000338/2018005 and 05000339/2018005 ML18059A0942018-02-28028 February 2018 EOC Assessment Letter IR 05000338/20170052017-08-21021 August 2017 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 - Report 05000338/2017005 and 05000339/2017005 ML17156A0662017-06-0202 June 2017 Notification of Inspection and Request for Information IR 05000338/20160062017-03-0101 March 2017 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2016006 and 05000339/2016006 IR 05000338/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Report 05000338, 339/2016005 ML16222A9132016-08-0808 August 2016 Notification of Inspection and Request for Information IR 05000338/20150062016-03-0202 March 2016 Annual Assessment Letter for North Anna Power Station Units 1 and 2 - NRC Inspection Report 05000338/2015006 and 05000339/2015006 ML16013A0622016-01-12012 January 2016 North Anna Power Station, Unit 2 - Notification of Inspection and Request for Information IR 05000338/20150052015-09-0101 September 2015 Mid-Cycle Letter for North Anna Power Station, Units 1 and 2 - NRC Assessment Report 05000338/2015005 and 05000339/2015005 IR 05000338/20140012015-03-0404 March 2015 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2014001 and 05000339/2014001 ML14245A1902014-09-0202 September 2014 Mid-Cycle Ltr 2014 IR 05000338/20130012014-03-0404 March 2014 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2013001 and 05000339/2013001 ML14022A0412014-01-21021 January 2014 TI-182 Phase 2 RFI Final ML13246A1322013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000338/20120012013-03-0404 March 2013 Annual Assessment Letter North Anna, Units 1 and 2, 05000338/2012001 and 05000339/2012001 ML13037A1712013-02-0101 February 2013 Notification of Inspection and Request for Information ML13032A5532013-02-0101 February 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML12248A1102012-09-0404 September 2012 Mid Cycle Assessment Letter North Anna 2012 ML12235A2912012-08-17017 August 2012 IR 05000338-12-012, 05000339-12-012, on 10/28/2011, North Anna Power Station, Units 1 & 2 - Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML1206506412012-03-0505 March 2012 End of Cycle Assessment Report 22 ML1124400992011-09-0101 September 2011 Report 22, Inspection/Activity Plan ML1106303432011-03-0404 March 2011 Inspection/Activity Plan 03/01/2011 - 06/30/2012, EOC Report 22 ML1024402812010-09-0101 September 2010 Report 22 - 2010 Mid Cycle Inspection/Activity Plan 2024-08-27
[Table view] Category:Letter
MONTHYEARIR 05000338/20240032024-10-28028 October 2024 – Integrated Inspection Report 05000338-2024003 and 05000339-2024003 ML24283A0392024-10-0909 October 2024 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.D ML24281A1372024-10-0707 October 2024 ISFSI - Submittal of Cask Registration for Spent Fuel Storage 05000338/LER-2024-001-01, Automatic Reactor Trip Due to Prni High Negative Rate2024-09-24024 September 2024 Automatic Reactor Trip Due to Prni High Negative Rate IR 05000338/20244202024-09-23023 September 2024 Security Baseline Inspection Report 05000338/2024420 and 05000339/2024420, Cover Letter ML24243A0872024-09-20020 September 2024 Response to EPA Comments Regarding the Final Site Specific Supplement to the Generic Eist for License Renewal North Anna Power Station, Units 1 and 2 IR 05000338/20244022024-09-17017 September 2024 Security Baseline Inspection Report 05000338/2024402 and 05000339/2024402 ML24215A2622024-08-28028 August 2024 Transmittal Letter for Subsequent Renewed License IR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) 05000339/LER-2024-001-01, Loss of Generator Field for 2J Eog During 2-PT-82.282024-08-20020 August 2024 Loss of Generator Field for 2J Eog During 2-PT-82.28 ML24234A0742024-08-15015 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-23-63, NEI 03-08 Needed Guidance: PWR Thermal Shield Flexure Inspection Requirements ML24221A1932024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Upper Mattaponi Tribe ML24206A0052024-08-0808 August 2024 SLR Final EIS Letter to Achp ML24221A1882024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Monacan Indian Nation ML24221A1842024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Nation, Oklahoma ML24221A1922024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Tuscarora Nation of New York ML24221A1912024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Rappahannock Tribe, Inc ML24221A1942024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-United Keetoowah Band of Cherokee Indians in Oklahoma ML24221A1852024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Tribe of Indians ML24221A1832024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Chickahominy Indian Tribe-Eastern Division ML24206A0062024-08-0808 August 2024 Notice of Availability of the Final Environmental Impact Statement for the North Anna Nuclear Power Station Unit Numbers 1 and 2 Subsequent License Renewal (Docket Numbers: 50-338 and 50-339) ML24163A3002024-08-0808 August 2024 Request for Relief Request N1-I5-NDE-007 Inservice Inspection Alternative ML24208A0142024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-Absentee-Shawnee Tribe of Indians of Oklahoma ML24221A1872024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Shawnee Tribe of Oklahoma ML24221A1862024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Band of Cherokee Indians ML24221A1902024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Pamunkey Indian Tribe ML24221A1812024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Catawba Indian Nation ML24221A1822024-08-0808 August 2024 Tribal Section 106 Letters - North Anna - Chickahominy Indian Tribe ML24221A1892024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Nansemond Indian Nation ML24241A0692024-08-0606 August 2024 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000338/20240022024-08-0202 August 2024 Integrated Inspection Report 05000338/2024002 and 05000339/2024002 ML24206A0432024-07-26026 July 2024 Feis - Letter to the Applicant 05000338/LER-2024-001, Automatic Reactor Trip Due to Prni High Negative Rate2024-07-25025 July 2024 Automatic Reactor Trip Due to Prni High Negative Rate ML24206A0902024-07-24024 July 2024 Owners Activity Report ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code 05000339/LER-2024-001, Loss of Generator Field for 2J EDG During 2-PT-82.282024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 ML24165A1462024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 IR 05000338/20240102024-05-24024 May 2024 NRC Fire Protection Team Inspection (FPTI) Report 05000338/2024010 and 05000339/2024010 IR 05000338/20240012024-05-10010 May 2024 Integrated Inspection Report 05000338/2024001 and 05000339/2024001 IR 05000338/20244032024-04-30030 April 2024 – Security Baseline Inspection Report 05000338-2024403 and 05000339-2024403 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24110A1462024-04-18018 April 2024 Independent Spent Fuel Storage Installation (Sfsi) - Annual Radiological Environmental Operating Report ML24110A1502024-04-18018 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24110A1392024-04-18018 April 2024 Annual Environmental Operating Report ML24087A0572024-04-16016 April 2024 Correction to Issuance of Amendment Nos. 296 and 279 ML24088A2692024-03-27027 March 2024 Core Operating Limits Report Cycle 31 Pattern Sos Revision 0 ML24086A4292024-03-25025 March 2024 Response to Request for Additional Information Associated with Alternative Request N1-I5-NDE-007 Request to Deter Additional Required Reactor Coolant Pump Casing Inspection 2024-09-24
[Table view] |
Text
February 15, 2023 Daniel Stoddard Senior Vice President and Chief Nuclear Officer Virginia Electric & Power Company; Dominion Energy 5000 Dominion Boulevard Glen Allen, VA 23060
SUBJECT:
NORTH ANNA POWER STATION, UNITS 1 AND 2 - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION FOR NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION
Dear Daniel Stoddard:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a problem identification and resolution (PI&R) inspection at your North Anna Power Station during the weeks of April 17-21, 2023, and May 1-5, 2023. The inspection team will be led by Mr. Adam Wilson, a Senior Project Engineer from the NRC Region II office. This inspection will be conducted in accordance with the baseline inspection procedure (IP), 71152, Problem Identification and Resolution (ADAMS Accession No. ML21281A181).
The biennial PI&R inspection and assessment of the licensees corrective action program complements and expands upon the resident baseline inspections of routine daily screening of all corrective action program issues, quarterly focused issue reviews, and semiannual trend PI&R reviews.
On February 14, 2023, Mr. Wilson confirmed with Bob Page, of Dominion Energy, arrangements for the two-week inspection.
The enclosure lists documents that will be needed prior to the inspection. Please have the referenced information available no later than April 6, 2023. Contact Mr. Wilson with any questions concerning the requested information. The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for inspection preparation.
If additional documents are needed, they will be requested when identified. Prior to the onsite inspection, NRC staff will discuss with your staff the following inspection support administrative details: availability of knowledgeable plant engineering and licensing personnel to serve as points of contact during the inspection; method of tracking inspector requests during the inspection; access to licensee computers; and if necessary: working space and arrangements for site access; and other applicable information.
D. Stoddard 2 In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding the information requested or the inspection, please contact Mr. Wilson at (404) 997-4574 or the resident inspectors.
Sincerely, Signed by Fannon, Matthew on 02/15/23 Matthew S. Fannon, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos.: 05000338 and 05000339 License Nos.: NPF-4 and NPF-7
Enclosure:
Information Request for North Anna PI&R Inspection cc: Distribution via ListServ PAPERWORK REDUCTION ACT STATEMENT This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011.
PUBLIC PROTECTION NOTIFICATION The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
ML23046A195 x SUNSI Review X Non-Sensitive X Publicly Available Sensitive Non-Publicly Available OFFICE RII: DRP RII: DRP NAME A. Wilson M. Fannon DATE 02/15/2023 02/15/2023 INFORMATION REQUEST FOR NORTH ANNA PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION (APRIL 17-21, 2023 AND MAY 1-5, 2023)
Note: Unless otherwise noted, the information requested below corresponds to documents generated since April 1, 2021. Please provide the requested documents in electronic format. If the information is not available in electronic format, please contact the inspection team leader to coordinate other available methods to provide the information.
- 1. Copies of the corporate and site level procedures and sub-tier procedures associated with the corrective action program. This should include procedures related to:
a) Corrective action process b) Cause evaluation c) Operating experience program d) Employee concerns program e) Self-assessment program f) Maintenance rule program and implementing procedures g) Operability determination process h) Degraded/non-conforming condition process (e.g., RIS 2005-20) i) System health process or equivalent equipment reliability improvement programs j) Preventive maintenance deferral process If any of the procedures requested above were revised after April 1, 2021, please provide (or have available) copies of all revisions during the onsite inspection.
- 2. List of top ten risk-significant systems, top ten risk-significant components for each one of the top ten risk-significant systems, and top ten risk-significant operator manual actions.
- 3. List of all Condition Reports (CRs) initiated including the following information or each CR:
a) CR number b) Brief, but complete problem description c) Priority or level d) Affected system e) Affected component f) Responsible plant department g) CR completion status If possible, provide this list in a format compatible with spreadsheet software (i.e. Excel example shown below) and ensure the list is searchable and can be filtered by system.
CR # Problem Priority System Component Org Status CR001 A RHR Pump 2 RHR 2-RHR- ENG Open failed flow criteria PMP-A per SR 5.0.5.4 Enclosure
- 4. List of outstanding corrective actions including the following information for each action:
a) Corrective action number b) Corrective action type (e.g., corrective action to prevent recurrence, enhancement, maintenance rule evaluation, etc.)
c) Brief, but complete corrective action description d) Associated CR number e) Corrective action initiation date f) Number of extensions g) Corrective action due date h) Completion status If possible, provide this list in a format compatible with spreadsheet software (i.e. Excel, example shown below) and ensure the list is searchable and can be filtered by system.
Corrective Type Description CR System Initiation Extensions Due Status Action # Date Date 001 CAPR Revise CR005 RHR 01/05/20 2 06/15/20 Awaiting Procedure CARB NGK-003-4585 review
- 5. List of control room deficiencies with a brief description and corresponding CR and/or work order (WO) number.
- 6. List of operator workarounds and operator burdens with a brief description and corresponding CR number, searchable and filtered by system.
- 7. List of all currently extended or overdue CRs, searchable and filtered by system and sorted by initiation date, with the following information:
a) CR number b) Priority or Significance c) CR title and short description
- 8. List of all CRs that have been voided, cancelled, or deleted searchable and filtered by system. Please provide the following information for each CR:
a) CR number b) Brief, but complete problem description c) Reason voided, cancelled, or deleted 2
- 9. List of all structures, systems, and components (SSCs) which were classified as (a)(1) in accordance with the maintenance rule since April 2021. Please include the following information for each system in (a)(1):
a) Date of classification in (a)(1) b) Reason for being placed in (a)(1) c) Planned actions and their status
- 10. List of Maintenance Preventable Functional Failures of risk-significant systems.
Please include actions completed and current status.
- 11. List of corrective maintenance work orders. Please include the following information for each work order:
a) WO number b) Brief, but complete work description c) Affected system and components d) Date of initiation e) Date of completion (if completed)
If possible, provide this list in a format compatible with spreadsheet software (i.e. Excel, example shown below) and ensure the list is searchable and can be filtered by system.
Work Description System Component Initiation Due Status Order # Date Date WO01345 Replace breaker SI 2A-SI-PMP, 01/05/21 03/15/21 Closed 2A-BKR-08-BB4 BKR-08-BB4 for 2A SI Pump.
- 12. Corrective action closeout packages, including CRs with description of corrective actions, for all NRC findings and licensee-identified violations (LIVs). Please include a cross reference linking NRC finding numbers and LIVs to appropriate CR numbers.
- 13. Corrective action closeout packages, including CRs with description of corrective actions, for all licensee event reports (LERs) issued. Please include a cross reference linking LER number to appropriate CR number.
- 14. List of all NRC generic communications (e.g., Information Notices, Generic Letters, etc.) and industry operating experience (OE) documents (e.g., Part 21 reports, vendor information letters, information from other sites, etc.) evaluated by the site for applicability to the station, regardless of the determination of applicability. Please include the reference number (e.g.,
CR number) for the documents that evaluated the aforementioned OE information.
- 15. Copies of all quality assurance audits and/or assessments issued, including the last two audits/assessments of the corrective action program.
- 16. Copies of all department self-assessments.
- 17. Copy of the most recent integrated plant trend report, departmental trend report(s), and corrective action trend reports, including any human performance and equipment reliability trends.
3
- 18. Copy of the latest corrective action program statistics (if any exists) such as the number of CRs initiated by department, human performance errors by department, and others as may be available.
- 19. Please provide a list of routine meetings involving the corrective action program to be held while team is onsite. If those meetings will be conducted remotely, please provide bridge call in numbers or any other links, if available (i.e. WebEx, etc.).
- 20. List of CRs related to equipment aging issues in the top ten risk- significant systems since April 1, 2018 (e.g., system erosion and/or corrosion problems; electronic component aging or obsolescence of circuit boards, power supplies, relays, etc.; environmental qualification).
Please provide the following information for each CR:
a) CR number b) Priority c) CR problem description
- 21. If performed, please provide any recent self-assessment of the site safety culture completed.
- 22. Copies of corrective action program documents related to cross-cutting issues (human performance, problem identification and resolution, and safety conscious work environment) identified via trending, self-assessments, safety review committee or other oversight methods
- 23. List of all root cause, apparent cause, common cause and related or similar equipment cause evaluations with a brief description.
- 24. Copy of Probabilistic Risk Assessment importance measures report, if available.
- 25. System health reports, system design basis documents, and system description information upon notification of system selections.
4