IR 05000338/2021010

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000338/2021010 and 05000339/2021010
ML21323A199
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 11/18/2021
From: James Baptist
NRC/RGN-II/DRS/EB1
To: Stoddard D
Dominion Energy Virginia, Virginia Electric & Power Co (VEPCO)
References
IR 2021010
Download: ML21323A199 (20)


Text

November 18, 2021

SUBJECT:

NORTH ANNA POWER STATION - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000338/2021010 AND 05000339/2021010

Dear Mr. Stoddard:

On October 8, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at North Anna Power Station and discussed the results of this inspection with Fred Mladen and other members of your staff. The results of this inspection are documented in the enclosed report.

Three findings of very low safety significance (Green) are documented in this report. Three of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at North Anna Power Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

James B. Baptist, Chief Engineering Br 1 Division of Reactor Safety Docket Nos. 05000338 and 05000339 License Nos. NPF-4 and NPF-7

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000338 and 05000339

License Numbers:

NPF-4 and NPF-7

Report Numbers:

05000338/2021010 and 05000339/2021010

Enterprise Identifier: I-2021-010-0042

Licensee:

Dominion Energy

Facility:

NORTH ANNA POWER STATION

Location:

Mineral, VA

Inspection Dates:

September 20, 2021 to October 08, 2021

Inspectors:

P. Braxton, Reactor Inspector

T. Fanelli, Senior Reactor Inspector

M. Schwieg, Senior Reactor Inspector

T. Su, Reactor Inspector

Craig Baron, Mechanical Contractor

Maty Yeminy, Mechanical Contractor

Chase Franklin, Reactor Inspector ( trainee)

Approved By:

James B. Baptist, Chief

Engineering Br 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at North Anna Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Inadequate Calculation to Ensure Diesel Cooling System Met Pressure Transient Requirements Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000338,05000339/2021010-01 Open/Closed None (NPP)71111.21M The inspectors identified a Green finding and an associated NCV of 10 CFR Part 50 Appendix B, Criterion 3, Design Control, for the licensee's failure to meet the DOM-QA-1 design verification requirements and the design control procedure requirements in calculation (USB-272, Emergency Diesel Generator Room Tornado Analysis).

Failure to scope safety related MOVs into the MOV test program Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000338,05000339/2021010-02 Open/Closed None (NPP)71111.21M The inspectors identified a Green finding and an associated NCV of 10 CFR Part 50.55a Codes and Standards for removing safety-related Charging (CH) pump Motor Operated Valves (MOVs) from the station MOV testing program. The required scope of the program was specified by the scoping provisions in NRC Generic Letter (GL) 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance Results of the Public Workshops (Generic Letter 89-10) and GL96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves (Generic Letter 96-05).

Inadequate procedure for handling age degraded safety related cable.

Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000338,05000339/2021010-03 Open/Closed None 71111.21M The inspectors identified a Green finding and an associated NCV of 10 CFR Part 50 Appendix B, Criterion V, "Instructions, Procedures, and Drawings," for the licensees failure to include work instructions to ensure the safety function of aged cables during and after handling.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (9 Samples)

(1)2-EE-MCC 2J1-1 and 2-EE-MCC 2J1-1A

  • Compliance with UFSAR, Technical Specifications (TS), and TS Bases
  • Conformance with manufacturer instructions for installation, maintenance, and operation
  • Material condition and configuration (i.e. walkdown of area)
  • System health reports
  • Design requirements
  • Operating Environment
  • Maintenance and preventive maintenance effectiveness
(2) Unit 1 - Diesel Driven Fire Pump System (01-FP-P-2-PUMP, 01-FP-P-2-ENGINE)
  • Design bases documents, system descriptions, and training documents
  • Primary design calculations
  • Normal and Emergency Operating Procedures
  • Surveillance Test Procedures and Recent Results
  • Material Condition of Pump and Associated Equipment
  • Vendor Manuals for Engine and Pump
  • Corrective Action History
  • Condition reports associated with component
(3) Unit 1 CCW Heat Exchanger
  • Reviewed heat Exchanger procurement specification
  • Reviewed heat Exchanger data sheet
  • Reviewed maximum allowed fouling factor
  • Reviewed maximum number for plugged tubes
  • Reviewed list of system & component CRs since last DBI. Review for Potential issues. Recorded in system health reports?
  • Reviewed licensee response letter(s) to GL 89-13
  • Reviewed completed surveillance test for the Heat Exchanger. Reviewed test set up and instrument uncertainty (compare the energy removed from the hot medium to the energy added to the cold medium).
  • Reviewed acceptance Criteria values
(4) Service Water Valve House (Settling)
  • Assess methodology for setting the monuments
  • Assess validity of benchmarking
  • Reviewed settling trend.
  • Reviewed the method North Anna used to release all stresses
(5) Uni1 and Unit 2 EDG Sequencers
  • Design bases documents, system description
  • Primary design calculations
  • Surveillance Test Procedures Recent Results
  • Preventative Maintenance Procedures
  • Vendor Manuals
  • Corrective Action History
  • Condition reports associated with component
(6) Unit 1 DC System Switchgear
  • Design bases documents, system description
  • Primary design calculations
  • Surveillance Test Procedures
  • Preventative Maintenance Procedures
  • Vendor Manuals for the Sequencer
  • Corrective Action History
  • Condition reports associated with component
(7) Offsite Power (1E and non-1E) and High-Voltage Switchyard
  • Design bases documents, system description
  • Primary design calculations
  • Surveillance Test Procedures Recent Results
  • Preventative Maintenance Procedures
  • Vendor Manuals for RSST
  • Engineering design changes
  • Corrective Action History
  • Condition reports associated with component
(8) Unit 1 Motor-Operated Valves MOV 1863 A/B, MOV-1267 A/B, 1269 A/B, 1270 A/B, and associated check valves
  • Normal and Emergency Operating Procedures
  • Surveillance Test Procedures and Recent Results
  • Inservice Test Procedures and Recent Results
  • Setpoint for Automatic Opening of Valves MOV 1863 A/B
  • MOV Program Scoping
  • Material Condition of Valves and Associated Equipment Corrective Action History
(9) Unit 1 & 2 Flex Equipment, Including Portable Diesel Generators[List sampled component with description/number (e.g., Essential 4.16kV Switchgear EH12)
  • Licensing Commitments associated with FLEX Equipment
  • Operating Procedures for Extended Station Blackouts
  • Maintenance and Testing of FLEX Equipment
  • Method of Delivering Fuel Oil to FLEX Equipment
  • Storage of FLEX Equipment
  • Corrective Action History

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

(1) NA-21-00056, Temporary Missile Shield for Unit 1 Containment, Rev. 0
  • Quality of installation
  • Quality Assurance
(2) EDG Fuel Oil System, EDG Cooling, and EDG Room Ventilation
  • Reviewed critical parameters
  • Reviewed component procurement specifications
  • Reviewed vendor certified fuel oil pump Head Capacity curves
  • Reviewed pump NPSH curve
  • Reviewed vendor manuals for components
  • Reviewed equipment assembly drawings with Bill of Materials
  • Reviewed system normal operating procedure
  • Reviewed system abnormal operating procedure
  • Reviewed IST acceptance criteria
  • Reviewed completed IST procedures
  • Reviewed system health report - last quarter
  • Reviewed protection from Tornado under-pressure
  • Verified day tank design pressure, vents and relief valves
  • Reviewed check valves boundary between safety and non-safety equip
  • Verified motor environment
  • Verified motor HP

Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)

(1) NA-17-00248-05, Vital Bus 2-1, 2-II, 2-III and 2-IV Non-Safety Branch Circuit Fuse Installation
(2) NA-19-00122-02, Remove Input From Loop Stop Valve Cabinet
(3) NA-13-01190, Reserve Station Service Transformer "A" and "B" Replacement
(4) DCP 96-106, Install Pressure Equalizing Line/ NAPS/ Unit 2, 05/15/96

Review of Operating Experience Issues (IP Section 02.06) (3 Samples)

(1) IN2016-09, Recent Issues Identified When Using Reverse Engineering Techniques in the Procurement of Safety-Related Components
(2) IN 2020-02 FLEX Diesel Generator Operational Challenges
(3) IN 2021-01 Lessons Learned from U.S. Nuclear Regulatory Commission Inspections of Design-Basis Capability of Power-Operated Valves at Nuclear Power Plants

INSPECTION RESULTS

Inadequate Calculation to Ensure Diesel Cooling System Met Pressure Transient Requirements Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000338,05000339/2021010-01 Open/Closed

None (NPP)71111.21M The inspectors identified a Green finding and an associated NCV of 10 CFR Part 50 Appendix B, Criterion 3, Design Control, for the licensee's failure to meet the DOM-QA-1 design verification requirements and the design control procedure requirements in calculation (USB-272, Emergency Diesel Generator Room Tornado Analysis).

Description:

The team reviewed calculation USB-272, Rev 0, "Emergency Diesel Generator (EDGR) Room Tornado Analysis," to determine the diesel cooling system response to a tornado event and verify whether it met the licensees Quality Assurance (QA)requirements. The purpose of the calculation stated, to determine the design basis transient pressure response of the Emergency Diesel Generator Room (EDGR) for the tornado event.

The transient velocity, density, and differential pressure on the components in the air exhaust flow path will be determined.

The team noted that the design of the EDGR components were determined by walkdowns to be used in the calculation. The calculation modeled the radiator and fan as thick-walled orifices instead of the actual design, which was a flat-tube and plate (fin) radiator six inches thick with 858 tubes arranged in six staggered layers of tubes forming a tortuous air path for increased heat transfer. It did not describe the details of the as-installed design of the radiator and the fan, but it did estimate how much blockage each caused to the respective flow path to estimate the diameter of the thick-walled orifice model. The calculation underestimated the blockage caused by the radiator because the walkdown misidentified the radiator tube blockage as only ten percent of the total blockage (see radiator design above). Additionally, the analysis did not identify the acceptance criteria for maximum loading to be applied to the radiator or axial fan to which the analysis results were to be compared. The EDGR room inlet dampers can be open letting in full air flow causing high dynamic pressures through these components which was not evaluated in the calculation. The calculation evaluated the barometric pressure drop from the tornado (-3 psi) but it did not evaluate the dynamic pressures developed from air flow through and across the radiator (tortuous path through small diverging apertures) or the fan blades (airfoils) that could cause damage.

The team determined that the calculation did not suitably model the potential tornado pressure responses for the radiator or axial fan, and thus did not meet the purpose stated in the calculation. The team noted that the licensees referenced technical handbook discussed mathematical models for staggered flat-tube and plate radiator with six tube layers and axial fans, (Handbook of Hydraulic Resistance, I.E. Idel'Chik, 1960).

The Quality Assurance Program Documents (DOM-QA-1) design control Section 3.2.3, Design Verification, states, in part, that the design control program ensures that appropriate verification methods are used, the appropriate design parameters are chosen, the acceptance criteria are identified, the verification is satisfactorily accomplished, and the results are properly recorded. The administrative design control procedure for engineering calculations (CM-AA-CLC-301), Attachment 1, Fundamental Expectations specifies, in part, that calculations shall provide technically correct results that meet the objectives stated in the Purpose section of the calculation. The team determined that the calculation did not meet the QA requirements prescribed in DOM-QA-1 or the calculation design control procedure.

Corrective Actions: In response to the inspectors concerns, the licensee-initiated condition report CR1182226 on October 8, 2021 and CR1183893 on October 26, 2021 to correct the tornado analysis.

Corrective Action References: CR1182226, CR1183893

Performance Assessment:

Performance Deficiency: The inspectors determined that the calculation (USB-272, Emergency Diesel Generator Room Tornado Analysis) failed to meet the DOM-QA-1 design verification requirements and the design control procedure requirements, which was a performance deficiency. The calculation did not suitably identify the as-installed design of the EDG radiator and EDG fan. It did not model the EDG room configurations pertinent to both the static and dynamic pressure responses. Nor did it use appropriate mathematical models or appropriate acceptance criteria for the radiator and cooling fan during tornado events. Based on this, the analysis did not meet the QA requirements and stated purpose of the calculation.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to adequately verify the performance of the EDG cooling system during tornado events affected the availability and reliability of the emergency power system when needed during external events and a loss of offsite power.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. A risk evaluation was performed by a regional senior reactor analyst using SAPHIRE Version 8.2.5 and NRC North Anna SPAR model Version 8.56. The conditional analysis assumed failure of the EDGs and operator recovery actions for all tornado initiating events with a one-year exposure time. The dominant sequences involved a tornado initiator accompanied by a loss of offsite power with failures of the emergency diesel generators, FLEX equipment and operator actions to recover offsite power. The analysis determined that the estimated increase in core damage frequency was less than 1E-06/year and did not involve sequences associated with an increase in large early release frequency, representing a finding of very low safety significance (Green).

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: 10 CFR 50, Appendix B, Criterion 3, Design Control, that states, in part, that design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program Design control measures shall be applied to items such as the following: reactor physics, stress, thermal, hydraulic, and accident analyses; and the delineation of acceptance criteria for inspections and tests.

Contrary to Criterion 3, since 1/7/1992 the site failed to provide design control measures for verifying or checking the adequacy of the diesel cooling system during design such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program, and failed to apply design control measures to items such as analyses for design basis pressure responses; and the delineation of acceptance criteria for inspections and tests of the EDG cooling system.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to scope safety related MOVs into the MOV test program Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000338,05000339/2021010-02 Open/Closed

None (NPP)71111.21M The inspectors identified a Green finding and an associated NCV of 10 CFR Part 50.55a Codes and Standards for removing safety-related Charging (CH) pump Motor Operated Valves (MOVs) from the station MOV testing program. The required scope of the program was specified by the scoping provisions in NRC Generic Letter (GL) 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance Results of the Public Workshops (Generic Letter 89-10) and GL96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves (Generic Letter 96-05).

Description:

The inspectors reviewed Engineering Transmittal (ET)-CME-07-0003, Justification for Removal of CH Pump Suction Valves from the Scope of the NAPS MOV Program, Rev. 0, approved on May 23, 2007. The ET evaluation included Unit 1 valves 1-CH-MOV-1267A/B, 1-CH-MOV-1269A/B, 1-CH-MOV-1270A/B and Unit 2 valves 2-CH-MOV-2267A/B, 2-CH-MOV-2269A/B, 2-CH-MOV-2270A/B. The ET reviewed the Inservice Testing (IST) basis document, the Updated Final Safety Analysis Report (UFSAR), and Emergency Operating Procedures (EOPs). Because the MOVs were not identified in the documents to establish alternate flow paths for any events, the licensee determined that they did not perform a safety related function. Based on this, the MOVs were removed from the MOV test program on January 15, 2008, with Addendum No. 2 to Technical Report EP-0020, Engineering Position and Technical Overview for Generic Letter 96-05 - Periodic Verification of Design-Basis Capability of Safety Related Motor Operated Valves, Rev. 0.

The inspectors noted that the EOPs did not identify every alternate flow path for every emergency condition. The inspectors identified that station operators could use these MOVs in response to certain emergency conditions based on applicable maintenance operating procedures to isolate a portion of the system during the long-term phase of an accident. For example, procedure 1-MOP-8.01, 1-CH-P-1A - A Charging Pump, Revision 67 directed that valves 1-CH-MOV-1267A and 1267B be closed from the control room to isolate the unit 1 A charging pump. The inspectors determined that these MOVs had a safety related function to establish an alternate flow path for certain events such as charging pump seal failures.

Corrective Actions: In response to the inspectors concerns, the licensee-initiated condition report CR1181633 on September 29, 2021. On October 26, 2021, the licensee approved prompt operability determination (OD) CA 8587871 to address reasonable assurance of operability of these motor operated valves. The OD concluded that these valves were non-conforming due to their removal from the site MOV program but were considered operable. The OD also included the results of an evaluation performed to ensure the valves ability to close under the most limiting differential pressure.

Corrective Action References: CR1181633 CA 8587871

Performance Assessment:

Performance Deficiency: The failure include safety related MOVs in the scope of the testing program as required by GL89-10 and GL96-05 was a performance deficiency

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to ensure that MOV performance was in accordance with the MOV testing program affected the reliability of the ECCS system in the event of a passive failure after an accident.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, the finding was determined to be of very low safety significance because it was a design deficiency confirmed not to result in a loss of operability.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: 10 CFR Part 50.55a(b)(3)(ii), Motor-Operated Valve Testing, requires, in part, that licensees comply with the provisions for testing MOVs in ASME OM Code, ISTC 4.2, 1995 Edition with the 1996 and 1997 Addenda, or ISTC-3500, 1998 Edition through the latest edition and addenda incorporated by reference in paragraph (a)(1)(iv) of 10 CFR 50.55a, and establish a program to ensure that MOVs continue to be capable of performing their design basis safety functions. 10 CFR 50.55a(b)(3)(ii) also requires that licensees implementing ASME OM Code, Mandatory Appendix III, Preservice and In-service Testing of Active Electric Motor Operated Valve Assemblies in Light-Water Reactor Power Plants, of the 2009 Edition, 2011 Addenda, and 2012 Edition shall comply with specific conditions.

Contrary to 50.55a(b)(3)(ii), since 2008, the licensee failed to include the subject MOVs in a testing program to ensure they could perform their design basis safety function.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Inadequate procedure for handling age degraded safety related cable.

Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000338,05000339/2021010-03 Open/Closed

None 71111.21M The inspectors identified a Green finding and an associated NCV of 10 CFR Part 50 Appendix B, Criterion V, "Instructions, Procedures, and Drawings," for the licensees failure to include work instructions to ensure the safety function of aged cables during and after handling.

Description:

Based on the walkdown pictures. For Unit 1 safety related battery 1-2, the cables terminated on the negative post of Cell 60 exceeded the bend radius of 3.52. The cable involved was 250 MCM Aluminum Triplex 600 V NGP-07 cable. The measured cable radius was 1.75. The inspectors noted that bend radii was exceeded on multiple safety related batteries around the plant. The Unit 2 safety related battery 2-II and the 1H diesel generator battery exceeded the minimum bend radii.

The inspectors determined that these cables in question were the original cables from initial installation more than 40 years old. Because aging can cause degradations that can damage insulation during handling such as micro fracturing, the inspectors reviewed work order (WO)to determine the work practices established to ensure the safety function of the cables during and after handling. The inspectors noted that the WO disassembled the batteries and storage racks from the room and then reassembled them. The cables could not be removed from the room as they went to a floor penetration to switchgear below. No work instruction concerning the handling of aged cables or minimum bend radii were included in the WOs to ensure the safety function of the cables during and after handling.

Corrective Actions: The licensee entered this into the corrective action program to determine the condition of the cables and correct the deficiency.

Corrective Action References: CR1181138, CR1181190

Performance Assessment:

Performance Deficiency: The failure to include work instructions to ensure the safety function of aged cables during and after handling was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Procedure Quality attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to ensure the safety function of the safety related cables failed to ensure their reliability and capability of safety related battery systems.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, the finding was determined to be of very low safety significance because it was a design deficiency confirmed not to result in a loss of operability.

Cross-Cutting Aspect: None

Enforcement:

Violation: 10 CFR 50, Appendix B criterion V, Instructions, Procedures, and Drawings states in part that instructions, procedures, or drawings shall include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished.

Contrary to the above, since 2019 the site failed to include appropriate quantitative acceptance criteria in instructions and procedures to ensure the safety function of aged cables during and after handling.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 8, 2021, the inspectors presented the The team performed exit meeting inspection results to Fred Mladen - Site VP and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

11715-ES-103

LHSI Pump NPSH

Rev. 0

71111.21M Calculations

2050-ES-220

Containment Floor Volume with Respect to Elevation, Addendum

H

Rev. 0

71111.21M Calculations

13075.49-ES-

194

Maximum Sump Water Level - Final NPSH Modification,

Addendum H

Rev. 2

71111.21M Calculations

19096.0510-E-4

25V DC MAXIMUM VOLTAGE ANALYSIS (CLASS IE BUSES)

Rev. 0

71111.21M Calculations

CALC 59-01-

PT-213.8A

Valve Inservice Inspection

Rev. 4

71111.21M Calculations

CALC 59-01-

PT-213.8B

Valve Inservice Inspection

Rev. 3

71111.21M Calculations

CALC 59-02-

PT-213.8A

Valve Inservice Inspection

Rev. 4

71111.21M Calculations

CALC 59-02-

PT-213.8B

Valve Inservice Inspection

Rev. 3

71111.21M Calculations

CE-1559

Containment Liner & Concrete Parametric Study Addendums A,

C, and D

Rev. 0

71111.21M Calculations

EE-0008

North Anna Voltage Profiles

Rev. 3

71111.21M Calculations

EE-0008

North Anna Voltage Profiles

Rev. 3

71111.21M Calculations

EE-0009

25 Vdc System Analysis

Rev. 2

71111.21M Calculations

EE-0025

North Atlanta Station Electrical Load List

Rev. 4

71111.21M Calculations

EE-0027

Emergency Diesel Generator Load Sequencing

Rev. 3

71111.21M Calculations

EE-0395

Safety Related 480V Load Center Coordination

Rev. 6

71111.21M Calculations

EE-0806

NAPS 4160V and 480V Short Circuit Analysis

Rev. 2

71111.21M Calculations

EE-0845

4160V and 480V Emergency Buses-Voltage Drops to

Switchgear DC COntrol Circuit Components

Rev. 0

71111.21M Calculations

EEE-0500

Motor Terminal Voltage for Motor Operated Valves Addendums

A and B

Rev. 6

71111.21M Calculations

ET-N-06-0043

Evaluation of Emergency Diesel Generator Ambient Room

Temperature

Rev. 1

71111.21M Calculations

ME-0314

Maximum Differential Pressure, High Pressure Safety Injection

and Auxiliary Feedwater Valves

Rev. 0

71111.21M Calculations

ME-0492

Thrust Band Calculation for North Anna Safety Related Motor

Rev. 1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Operated Valves, Addendums 1 and 1A

71111.21M Calculations

ME-0595

NAPS Fire Pumps Hydraulic Model

71111.21M Calculations

ME-0700

MOV Differential Pressure (DP) Calculation for the Subject

Valves

Rev. 0

71111.21M Calculations

ME-0792

Fire hose station design calculation

71111.21M Calculations

ME-3069

JOG Calculation of Required Thrust Settings for MOV 1-Sl-MOV-

1863A

Rev. 2

71111.21M Calculations

ME-3070

JOG Calculation of Required Thrust Settings for MOV 1-SI-MOV-

1863B

Rev. 2

71111.21M Calculations

ME-3200

JOG Calculation of Required Thrust Settings for MOV 2-SI-MOV-

2863A

Rev. 2

71111.21M Calculations

ME-530

Component Cooling Heat Exchanger Tube Plugging Study

Rev. 0

71111.21M Calculations

NA-Calc-ZZZ-

01040.4910-M-1

Emergency Diesel Generator Room and Battery Area

Temperature Profile

Rev. 1

71111.21M Calculations

NA-CALC-ZZZ-

11715-12050-

7.1-FO-3

Fuel Oil System

03/11/1978

71111.21M Calculations

SM-1176

Impact of Maintaining NA Automatic RMT Setpoint at 19.4%

RWST Level, Addendum A

Rev. 1

71111.21M Calculations

SM-1511

Design Inputs for GOTHIC Containment Analysis for NA Power

Station

Rev. 1

71111.21M Calculations

US(B)-272

Emergency Diesel Generator Room Tornado Analysis

Rev. 0

71111.21M Calculations

ZZZ-

11715_12050-

7.1-FP-2

Fire Pumps

71111.21M Corrective

Action

Documents

CR3052285, CR3052405, CR3064396, CR7616236,

CR7618752, CR7707420, CR7866652, CR8467896,

CR1177118, CR1177264, CR1003896, CR0361181,

CR0358809, CR0356650, CR1149511, CR1162288,

CR1166642, CR1172946, CR1175367

71111.21M Corrective

Action

Documents

Resulting from

CR1175367

NRC Identified: Cracked cable jackets on RSST overhead cables

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Inspection

71111.21M Corrective

Action

Documents

Resulting from

Inspection

CR1181038

NRC DBAI inspector noticed a typographical error on CALC EE-

0009

9/21/2021

71111.21M Corrective

Action

Documents

Resulting from

Inspection

CR1181138

NRC DBAI Inspector noted a incorrect bend radius on Battery 1-

9/22/2021

71111.21M Corrective

Action

Documents

Resulting from

Inspection

CR1181190

Incorrect bend radius on cable in the 2-II Battery Room

9/23/2021

71111.21M Corrective

Action

Documents

Resulting from

Inspection

CR1181493

DBAI Inspector noted improvements needed in CALC EE-0009

9/28/2021

71111.21M Drawings

11715-FB-035A

Fuel Oil Lines

Rev. 44

71111.21M Drawings

11715-FB-41A

Flow Diagram Fire Protection and Domestic Water

71111.21M Drawings

11715-FB-41B

Valve Operating Numbers Fire Protection & Domestic Water

71111.21M Drawings

11715-FB-4B

Yard Fuel Oil Lines Sh. 2

Rev. 17

71111.21M Drawings

11715-FB-9A

Floor Drainage Auxiliary Building Sh-1

01/17/1990

71111.21M Drawings

11715-FC-24B-

Plan EL 244' Outline Sh 1 Auxiliary Building

71111.21M Drawings

11715-FV-56A-

Underground Fuel Oil Storage Tanks 1-EG-TK-2A & 2B

Rev. 8

71111.21M Engineering

Changes03-122

Emergency Generator Load Sequencing Timer Replacements

/NAPS /Unit #2

3/30/2004

71111.21M Engineering

Changes

NA-13-01190

Reserve Station Service Transformer "A" and "B" Replacement

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Engineering

Changes

NA-14-00022

Spare Conductors of RSST A to Transfer Bus "D' Due to

Damaged Insulation

04/04/2014

71111.21M Engineering

Changes

NA-15-00061

Installation of Voltage Unbalance Protection (1H)

06/06/2017

71111.21M Engineering

Changes

NA-16-01034

Reserve Station Service Transformer C Replacement

71111.21M Engineering

Changes

NA-17-00214

Diesel Driven Fire Pump (1-FP-P-2) Appendix R Fused Circuit

Protection

71111.21M Engineering

Changes

NA-19-00122

Remove Input from Loop Stop Valve Cabinet

Rev. 2

71111.21M Engineering

Evaluations

GOTHIC

Evaluation 1

NAPS EDG Room Louver dP during Tornado - Normal Exhaust

Fan and EDG OFF

9/28/2021

71111.21M Engineering

Evaluations

GOTHIC

Evaluation 2

NAPS EDG Room Louver dP during Tornado - Normal Exhaust

Fan and EDG OFF with dirtier radiator

9/29/2021

71111.21M Engineering

Evaluations

GOTHIC

Evaluation 3

NAPS EDG Room Louver dP during Tornado - Normal Exhaust

Fan and EDG Running

9/29/2021

71111.21M Miscellaneous

Dominion-Virginia Power North Anna Environmental Zone

Description, Units 1 & 2

Rev. 28

71111.21M Miscellaneous

59-G533-00080

Installation, Operation and Maintenance Manual - Power

Transformers

71111.21M Miscellaneous

59-N104-00005

Klockner Moeller 100 Series Motor Control Center Cubicles

Rev. 9

71111.21M Miscellaneous

59-R217-00004

Load Tap Changer Type RMV-II 1500A/2000A/2500A VACUTAP

71111.21M Miscellaneous

DNES-VA-EEN-

0002

Design Standard for Cable

Rev. 1

71111.21M Miscellaneous

GC Cable Install

Manual

GC Cable Install Manual

Rev. 9

71111.21M Miscellaneous

MODULE

NCRODP-55-

NA

STATION DIESEL GENERATOR SYSTEMS

04/15/2020

71111.21M Miscellaneous

MS-AA-PTE-

401-1004

Commercial Grade Dedication

Rev. 10

71111.21M Miscellaneous

NA-220/1220

Procurement Specification Emergency Diesel Generator Sets

Rev. 3

71111.21M Miscellaneous

NA-SPEC-000-

NAS-0087A

Specification for miscellaneous Vertical Sump Pumps

10/05/1970

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Miscellaneous

NA-VTM-000-

59-C550-00001

Cummins Diesel NH/NT/NTA 855 C.I.D. Engines

71111.21M Miscellaneous

NA-VTM-000-

59-C550-00002

H, NH, NT Series Operations & Maintenance Manual

71111.21M Miscellaneous

NA-VTM-000-

59-P276-00001

Vertical Turbine Pumps Open Lineshaft Construction

71111.21M Miscellaneous

NAS-227

Procurement Specification, Fuel Oil Pumps

Rev. 2A1

71111.21M Miscellaneous

NAS-96

Procurement Specification Component Cooling Water Heat

Exchangers

Rev. 2A1

71111.21M Miscellaneous

SDBD-NAPS-

CC

System Design Basis Document for Component Cooling System

Rev. 20

71111.21M Miscellaneous

SDBD-NAPS-

ED

SYSTEM DESIGN BASIS DOCUMENT FOR 125 VDC

EMERGENCY POWER SYSTEM

Rev. 19

71111.21M Miscellaneous

SDBD-NAPS-

EG

SYSTEM DESIGN BASIS DOCUMENT FOR EMERGENCY

DIESEL GENERATOR SYSTEM

Rev. 20

71111.21M Miscellaneous

SDBD-NAPS-

EV

SYSTEM DESIGN BASIS DOCUMENT FOR EMERGENCY

POWER AND VITAL BUS (120-240V) SYSTEM

Rev. 20

71111.21M Miscellaneous

SDBD-NAPS-

FP

SYSTEM DESIGN BASIS DOCUMENT FOR FIRE

PROTECTION SYSTEM

71111.21M Miscellaneous

SDBD-NAPS-

SW

System Design Basis Document for Service Water System

Rev. 28

71111.21M Procedures

0-AP-10

LOSS OF ELECTRICAL POWER

Rev. 94

71111.21M Procedures

0-AP-10

LOSS OF ELECTRICAL POWER

Rev. 94

71111.21M Procedures

0-AP-8

RESPONSE TO GRID INSTABILITY

Rev. 14

71111.21M Procedures

0-MCM-0107-02 REPAIR OF DIESEL-DRIVEN FIRE PUMP 1-FP-P-2 AND

MOTOR-DRIVEN FIRE PUMP 1-FP-P-1

71111.21M Procedures

0-MPM-0107-01

DIESEL FIRE PUMP PREVENTIVE MAINTENANCE

71111.21M Procedures

0-MPM-0107-01

DIESEL FIRE PUMP PREVENTIVE MAINTENANCE

71111.21M Procedures

0-MPM-0107-02

DIESEL FIRE PUMP HOSE REPLACEMENT

71111.21M Procedures

0-PT-100.1.2

DIESEL-DRIVEN FIRE PROTECTION PUMP 1-FP-P-2

EXERCISE

71111.21M Procedures

1-LOG-6E

OUTSIDES LOG

117

71111.21M Procedures

1-OP-26.1

TRANSFERRING 4160-VOLT BUSSES

71111.21M Procedures

1-PT-142.9A.1

Valve Inservice Inspection Associated with 1-EG-TK-IH FOR 1-

Rev. 42

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EG-254

71111.21M Procedures

1-PT-80.2

TESTING OF THE EMERGENCY BUS ALTERNATE POWER

SUPPLY

71111.21M Procedures

1-PT-81.1A

Emergency Diesel Generator Fuel Oil Transfer Pumps 1EP-P-

1HA and 1EP-P-1HB

Rev. 26

71111.21M Procedures

1-PT-83.3A

LOAD SEQUENCING TIMERS VERIFICATION TEST

Rev. 1

71111.21M Procedures

1-PT-83.3B

LOAD SEQUENCING TIMERS VERIFICATION TEST

Rev. 0

71111.21M Procedures

2-LOG-6F

UNIT 2 SAFEGUARDS LOG

134

71111.21M Procedures

MS-AA-PTE-

401

Procurement Technical Evaluation Determination

Rev. 17

71111.21M Procedures

O-PT-100.2

FIRE PROTECTION PUMPS ANNUAL TESTING

71111.21M Work Orders

59102428535

FOPH Strainer Inspection/Cleaning 02-EG-2HA-Filter

2/30/20

71111.21M Work Orders

203307849,

203307881,

203308857,

203324848,

203355689,

203365694,

203136470,

203275091,

203275093,

203275095,

203284437,

203284472,

203284473,

203284475,

203284476,

59303284493,

203284532,

59102126128,

59102948061,

59102126136