{{#Wiki_filter:April 15, 2021 LICENSEE:      Vistra Operations Company LLC FACILITY:      Comanche Peak Nuclear Power Plant, Units Nos. 1 and 2
{{#Wiki_filter:}}
 
==SUBJECT:==
 
==SUMMARY==
OF MARCH 24, 2021, TELECONFERENCE WITH VISTRA OPERATIONS COMPANY LLC TO DISCUSS PROPOSED LICENSE AMENDMENT REQUEST TO ADOPT TSTF-505, REVISION 2, TO PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES (EPID L-2021-LRM-0031)
On March 24, 2021, an Observation public teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Vistra Operations Company LLC (the licensee). The purpose of the meeting was to discuss a proposed license amendment request (LAR) to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF [Risk-Informed TSTF] Initiative 4b, at Comanche Peak Nuclear Power Plant, Unit Nos. 1 and 2. The meeting notice and agenda, dated March 9, 2021, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML21068A152. A list of attendees is enclosed.
The licensee presented informational slides at the meeting, which can be found in ADAMS at Accession No. ML21068A029. During the meeting, the licensee discussed the proposed LAR content; identified variances from TSTF-505; and provided an overview of the probabilistic risk assessment models, the configuration risk management program, and the plan for implementing the risk-informed completion times. The licensee indicated it plans to submit the LAR in April 2021. The licensee and the NRC staff discussed each of these topics. The licensee indicated that they would consider the topics discussed in preparing its LAR.
 
One member of the public attended and had no comments. No public meeting feedback forms were received. No regulatory decisions were made at the meeting.
Please direct any inquiries to me at 301-415-6256 or by e-mail to Dennis.Galvin@nrc.gov.
                                            /RA/
Dennis J. Galvin, Project Manager Plant Licensing Branch 4 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446
 
==Enclosure:==
 
List of Attendees cc: Listserv
 
LIST OF ATTENDEES MARCH 24, 2021, PRESUBMITTAL TELECONFERENCE REGARDING PROPOSED LICENSE AMENDMENT REQUEST TO ADOPT TSTF-505, REVISION 2, TO PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES VISTRA OPERATIONS COMPANY LLC COMANCHE PEAK NUCLEAR POWER PLANT, UNITS NO. 1 AND 2 U.S. Nuclear Regulatory Commission R. Beaton                                      E. Miller G. Bedi                                        J. Patel J. Circle                                      R. Pascarelli V. Cusumano                                    A. Russell J. Dixon-Herrity                                M. Valentin J. Ellegood                                    S. Vasavada D. Galvin .                                    H. Wagage B. Grenier                                      K. West K. Hoffman                                      B. Wittick M. Li                                          D. Wu J. Medoff                                      S. Wyman Pacific Northwest National Laboratory Steve Short Vistra Operations Company LLC J. Hicks                                        G. Stuble C. McBeth Westinghouse W. Boatwright                                  D. Tirsun Members of the Public P. Ouellette, Engineering Planning and Management (EPM), Inc.
Enclosure
 
ML21099A275 OFFICE NRR/DORL/LPL4/PM            NRR/DORL/LPL4/LA          NRR/DSS/STSB/BC NAME      DGalvin                  PBlechman                VCusumano DATE      4/15/2021                4/13/2021                3/31/2021 OFFICE NRR/DRA/APLC/BC            NRR/DORL/LPL4/BC          NRR/DORL/LPL4/PM NAME      RPascarelli              JDixon-Herrity            DGalvin DATE      4/9/2021                4/15/2021                4/15/2021}}

Revision as of 21:28, 17 January 2022

Summary of Teleconference with Vistra Operations Company LLC to Discuss Proposed LAR to Adopt TSTF-505, Rev. 2, to Provide Risk-Informed Extended Completion Times for Comanche Peak, Units 1 and 2
ML21099A275
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 04/15/2021
From: Dennis Galvin
Plant Licensing Branch IV
To:
Vistra Operations Company
Galvin D
References
EPID L-2020-LRM-0031
Download: ML21099A275 (4)


Text