|
|
Line 95: |
Line 95: |
| No findings were identified. | | No findings were identified. |
| {{a|1R04}} | | {{a|1R04}} |
| ==1R04 Equipment Alignment== | | ==1R04 Equipment Alignment Partial System Walkdowns (71111.04Q - 5 samples) |
| | |
| Partial System Walkdowns (71111.04Q - 5 samples) | |
|
| |
|
| ====a. Inspection Scope==== | | ====a. Inspection Scope==== |
| | == |
| The inspectors performed partial walkdowns of the following systems: | | The inspectors performed partial walkdowns of the following systems: |
| * Unit 2 and Unit 3 A standby gas treatment (SBGT) train with the B SBGT train out of service (OOS) on July 7, 2016 | | * Unit 2 and Unit 3 A standby gas treatment (SBGT) train with the B SBGT train out of service (OOS) on July 7, 2016 |
Line 110: |
Line 109: |
| No findings were identified. | | No findings were identified. |
| {{a|1R05}} | | {{a|1R05}} |
| ==1R05 Fire Protection== | | ==1R05 Fire Protection |
|
| |
|
| ===.1 Resident Inspector Quarterly Walkdowns=== | | ===.1 Resident Inspector Quarterly Walkdowns=== |
| {{IP sample|IP=IP 71111.05Q|count=6}} | | {{IP sample|IP=IP 71111.05Q|count== |
| | =6}} |
|
| |
|
| ====a. Inspection Scope==== | | ====a. Inspection Scope==== |
|
---|
Category:Inspection Report
MONTHYEARIR 05000277/20240032024-11-0404 November 2024 Integrated Inspection Report 05000277/2024003 and 05000278/2024003 IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) IR 05000277/20240102024-08-23023 August 2024 Fire Protection Team Inspection Report 05000277/2024010 and 05000278/2024010 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) IR 05000277/20240022024-08-14014 August 2024 Integrated Inspection Report 05000277/2024002 and 05000278/2024002 IR 05000277/20243012024-06-13013 June 2024 Initial Operator Licensing Examination Report 05000277/2024301 and 05000278/2024301 IR 05000277/20240012024-05-13013 May 2024 Integrated Inspection Report 05000277/2024001 and 05000278/2024001 IR 05000277/20245012024-05-0808 May 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2024501 and 05000278/2024501 IR 05000277/20244022024-03-12012 March 2024 Cybersecurity Inspection Report 05000277/2024402 and 05000278/2024402 (Cover Letter Only) IR 05000277/20230062024-02-28028 February 2024 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2023006 and 05000278/2023006) IR 05000171/20230012024-02-20020 February 2024 Constellation Energy Generation, LLC - Peach Bottom Atomic Power Station, Unit 1 - NRC Inspection Report No. 05000171/2023001 IR 05000277/20230042024-02-12012 February 2024 Integrated Inspection Report 05000277/2023004 and 05000278/2023004 IR 05000277/20234022024-01-11011 January 2024 Security Baseline Inspection Report 05000277/2023402 and 05000278/2023402 and Independent Spent Fuel Storage Installation Security Inspection 07200029/2023401 IR 05000277/20230032023-10-30030 October 2023 Integrated Inspection Report 05000277/2023003 and 05000278/2023003 and Exercise of Enforcement Discretion IR 05000277/20244012023-10-0505 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000277/2024401 and 05000278/2024401 IR 05000277/20230102023-09-15015 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000277/2023010 and 05000278/2023010 and Notice of Violation ML23251A2022023-09-11011 September 2023 Cover Letter W/Report IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) IR 05000277/20230112023-08-15015 August 2023 Comprehensive Engineering Team Inspection Report 05000277/2023011 and 05000278/2023011 IR 05000277/20230022023-08-0808 August 2023 Integrated Inspection Report 05000277/2023002 and 05000278/2023002 IR 05000277/20230402023-07-17017 July 2023 95001 Inspection Supplemental Report 05000277/2023040 and Follow-Up Assessment Letter IR 05000277/20230012023-05-0808 May 2023 Integrated Inspection Report 05000277/2023001 and 05000278/2023001 IR 05000277/20220042023-04-0505 April 2023 Acknowledgement of Dispute of Green Finding - NRC Inspection Report 05000277/2022004 and 05000278/2022004 IR 05000277/20234012023-03-27027 March 2023 Security Baseline Inspection Report 05000277/2023401 and 05000278/2023401 IR 05000277/20230122023-03-10010 March 2023 Title 10 of the Code of Federal Regulations 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components Inspection Report 05000277/2023012 and 05000278/2023012 IR 05000277/20220062023-03-0101 March 2023 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2022006 and 05000278/2022006) ML23033A3332023-02-0202 February 2023 Integrated Inspection Report 05000277/2022004 and 05000278/2022004 IR 05000171/20220012023-01-0404 January 2023 Constellation Energy Generation, LLC, Peach Bottom Atomic Power Station, Unit 1 - NRC Inspection Report 05000171/2022001 IR 05000277/20220902022-11-28028 November 2022 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation, Inspection Report 05000277/2022090 IR 05000277/20220032022-10-27027 October 2022 Integrated Inspection Report 05000277/2022003 and 05000278/2022003 and Preliminary White Finding and Apparent Violation IR 05000277/20224012022-09-27027 September 2022 Material Control and Accounting Program Inspection Report 05000277/2022401 and 05000278/2022401 (Cover Letter Only) IR 05000277/20220052022-08-31031 August 2022 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2022005 and 05000278/2022005) IR 05000277/19570012022-08-19019 August 2022 631999-Termination License 50-27757-01 for G. Scott Crowther Dba Crowther Associates IR 07200079/20224042022-08-0404 August 2022 NRC Security Inspection Report 07200079/2022404 (Cover Letter) IR 05000277/20220022022-07-28028 July 2022 Integrated Inspection Report 05000277/2022002 and 05000278/2022002 IR 05000277/20223012022-07-28028 July 2022 Initial Operator Licensing Examination Report 05000277/2022301 and 05000278/2022301 IR 05000277/20224022022-06-15015 June 2022 Security Baseline Inspection Report 05000277/2022402 and 05000278/2022402 and Independent Spent Fuel Storage Installation Security Inspection Report 07200029/2022401 (Cover Letter Only) IR 05000277/20225012022-06-0808 June 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2022501 and 05000278/2022501 ML22117A0362022-04-27027 April 2022 Integrated Inspection Report 05000277/2022001 and 05000278/2022001 IR 05000482/20220012022-04-25025 April 2022 Integrated Inspection Report 05000482/2022001 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2022001 IR 05000277/20210062022-03-0202 March 2022 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2021006 and 05000278/2021006) IR 05000277/20210042022-02-0909 February 2022 Integrated Inspection Report 05000277/2021004 and 05000278/2021004 IR 05000277/20224032022-01-21021 January 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000277/2022403 and 05000278/2022403 IR 05000482/20210042022-01-19019 January 2022 Integrated Inspection Report 05000482/2021004 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2021002 IR 05000171/20210012022-01-12012 January 2022 Safstor Inspection Report 05000171/2021001 IR 05000277/20223022022-01-10010 January 2022 Operator Licensing Retake Examination Report 05000277/2022302 and 05000278/2022302 IR 05000277/20220112021-12-14014 December 2021 Information Request to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000277/2022011 and 05000278/2022011 IR 05000277/20210032021-11-0909 November 2021 Integrated Inspection Report 05000277/2021003 and 05000278/2021003 IR 05000482/20210032021-11-0505 November 2021 Integrated Inspection Report 05000482/2021003 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2021001, WC2021003 IR Ch IR 07200079/20214012021-10-21021 October 2021 ISFSI Security Inspection Report 07200079/2021401 2024-08-29
[Table view] Category:Letter
MONTHYEARIR 05000277/20240032024-11-0404 November 2024 Integrated Inspection Report 05000277/2024003 and 05000278/2024003 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24281A1012024-10-0707 October 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24221A2582024-09-0606 September 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Peach Bottom Atomic Power Station, Units 2 and 3 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification 05000277/LER-2024-003, Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum2024-09-0505 September 2024 Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24235A0342024-08-23023 August 2024 U.S. Nuclear Regulatory Commission’S Analysis of Constellation Energy Generation’S Decommissioning Funding Status Report IR 05000277/20240102024-08-23023 August 2024 Fire Protection Team Inspection Report 05000277/2024010 and 05000278/2024010 IR 05000277/20240022024-08-14014 August 2024 Integrated Inspection Report 05000277/2024002 and 05000278/2024002 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24225A1692024-08-12012 August 2024 10 CFR 50.46 Annual Report ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24214A3232024-08-0101 August 2024 Response to Request for Additional Information - Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) ML24191A0612024-07-0606 July 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24177A1512024-06-24024 June 2024 Post Accident Monitoring Instrumentation Report ML24166A1172024-06-20020 June 2024 Regulatory Audit Summary Regarding Proposed Alternative Schedule to Complete Decommissioning Beyond 60 Years RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000277/20243012024-06-13013 June 2024 Initial Operator Licensing Examination Report 05000277/2024301 and 05000278/2024301 RS-24-058, Regarding Subsequent License Renewal Environmental Review2024-06-0505 June 2024 Regarding Subsequent License Renewal Environmental Review ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24150A2722024-05-29029 May 2024 Annual Radiological Environmental Operating Report 81, January 1, 2023 Through December 31, 2023 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000277/20240012024-05-13013 May 2024 Integrated Inspection Report 05000277/2024001 and 05000278/2024001 ML24134A1792024-05-13013 May 2024 Supplemental Information in Support of Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations IR 05000277/20245012024-05-0808 May 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2024501 and 05000278/2024501 ML24121A1832024-04-30030 April 2024 Pre-Submittal Meeting Presentation Material Peach Bottom ECCS Compensated Level System Replacement Project RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24120A2762024-04-23023 April 2024 Independent Spent Fuel Storage Installation (ISFSI) Facility - Annual Radioactive Effluent Release Report 66 January 1, 2023 Through December 31, 2023 CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24107A2462024-04-15015 April 2024 Submittal of Changes to Technical Specifications Bases ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24102A0472024-04-11011 April 2024 Operator Licensing Examination Approval 05000277/LER-2024-002, Uncoordinated DC Circuits Cause Unanalyzed Condition2024-04-0808 April 2024 Uncoordinated DC Circuits Cause Unanalyzed Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. IR 05000277/20244022024-03-12012 March 2024 Cybersecurity Inspection Report 05000277/2024402 and 05000278/2024402 (Cover Letter Only) ML24061A2642024-03-0101 March 2024 Revision of Two Procedures That Implement the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) Commissioners ML24060A1192024-02-29029 February 2024 Notification of Conduct of a Fire Protection Team Inspection 2024-09-06
[Table view] |
Text
{{#Wiki_filter:[Type here]
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION I
2100 RENAISSANCE BLVD.
KING OF PRUSSIA, PA 19406-2713 November 3, 2016 Mr. Bryan Hanson Senior Vice President, Exelon Generation, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd.
Warrenville, IL 60555 SUBJECT: PEACH BOTTOM ATOMIC POWER STATION - INTEGRATED INSPECTION REPORT 05000277/2016003 AND 05000278/2016003
Dear Mr. Hanson:
On September 30, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Peach Bottom Atomic Power Station (PB), Units 2 and 3. On October 14, 2016, the NRC inspectors discussed the results of this inspection with Mr. Michael Massaro, Peach Bottom Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
NRC inspectors documented one finding of very low safety significance (Green) in this report.
The finding did not involve a violation of NRC requirements. If you disagree with the finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U. S.
Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC, 20555-0001; with copies to the Regional Administrator, Region I, and the NRC Resident Inspector at Peach Bottom.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with 10 Code of Federal Regulations (CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Daniel L. Schroeder, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos. 50-277 and 50-278 License Nos. DPR-44 and DPR-56
Enclosure:
Inspection Report 05000277/2016003 and 05000278/2016003 w/Attachment: Supplementary Information
REGION I==
Docket Nos. 50-277 and 50-278 License Nos. DPR-44 and DPR-56 Report No. 05000277/2016003 and 05000278/2016003 Licensee: Exelon Generation Company, LLC Facility: Peach Bottom Atomic Power Station, Units 2 and 3 Location: Delta, Pennsylvania Dates: July 1, 2016 through September 30, 2016 Inspectors: J. Heinly, Senior Resident Inspector B. Smith, Resident Inspector Approved By: Daniel L. Schroeder, Chief Reactor Projects Branch 4 Division of Reactor Projects Enclosure
SUMMARY
Inspection Report 05000277/2016003, 05000278/2016003; 07/01/2016 - 09/30/2016;
Peach Bottom Atomic Power Station (PB), Units 2 and 3; Follow-Up of Events and Notices of Enforcement Discretion.
This report covered a three-month period of inspection by resident inspectors. The inspectors identified one finding, which was of very low safety significance (Green). The significance of most findings is indicated by their color (i.e., greater than Green, or Green, White, Yellow, Red)and determined using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP), dated April 29, 2015. Cross-cutting aspects are determined using IMC 0310,
Aspects Within Cross-Cutting Areas, dated December 4, 2014. All violations of the Nuclear Regulatory Commission (NRC) requirements are dispositioned in accordance with the NRCs Enforcement Policy, dated August 1, 2016. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649,
Reactor Oversight Process, Revision 6.
Cornerstone: Initiating Events
A self-revealing finding of very low safety significance (Green) was identified for Exelons failure to maintain the Unit 2 C reactor feed pump (RFP) Woodward controller secondary power supply in accordance with PES-S-002, Exelon Shelf Life Program. Specifically, on May 27, 2016, the Unit 2 C RFP experienced speed oscillations due to an age-related failure of the Woodward controller secondary power supply, which resulted in an automatic recirculation runback to 53 percent rated thermal power (RTP). The power supply contained an electrolytic capacitor that had exceeded its shelf life per PES-S-002. This issue was entered into Exelons corrective action program (CAP) under issue report (IR) 02691322.
Exelons corrective actions included replacement of the faulted power supply and an extent of condition (EOC) review of proper expiration date entry for shelf life program components.
The finding was more than minor because it was associated with the equipment performance attribute of the Initiating Events cornerstone and affected the cornerstones objective of limiting the likelihood of events that upset plant stability during power operations. The inspectors evaluated the finding in accordance with Exhibit 1 of Inspection Manual Chapter (IMC) 0609, Appendix A, SDP for Findings At-Power, and determined the finding was of very low safety significance (Green) because it did not cause a reactor trip and the loss of mitigation equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition. The inspectors determined that no cross-cutting aspect was applicable to this finding because the performance deficiency (PD) was not indicative of current performance. The PD occurred between 1997 and 1999 when the power supply expiration date was incorrectly coded in Exelons work management process in accordance with PES-S-002. (Section 4OA3)
Other Findings
None.
REPORT DETAILS
Summary of Plant Status
Unit 2 began the inspection period at 100 percent RTP. On September 2, 2016, operators reduced power to 59 percent RTP to support waterbox cleaning in order to improve degraded vacuum in the main condenser. The unit was returned to full power on September 3, 2016. The unit remained at 100 percent RTP except for brief periods to support planned testing and control rod pattern adjustments. The unit then began end-of-cycle coastdown for refueling outage (RFO) 2R21 on September 28, 2016, and ended the inspection period at 98 percent RTP.
Unit 3 began the inspection period at 100 percent RTP. On July 29, 2016, operators responded to a high differential alarm on the 3C intake structure traveling screen by reducing power to 84 percent RTP and removing the 3C circulating water pump from service. The unit was returned to full power that same day following the repairs. Unit 3 remained at 100 percent RTP until the end of the inspection period, except for brief periods to support planned testing and control rod pattern adjustments.
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1R01 Adverse Weather Protection
Main article: IP 71111.01
External Flooding
a. Inspection Scope
On August 29, 2016, the inspectors performed an inspection of the external flood protection measures for PB. The inspectors reviewed technical specification (TS),procedures, design documents, and Updated Final Safety Analysis Report (UFSAR)
Chapter 2.3.4.5 and Appendix C.2.5.4, which depict the design flood levels and protection areas containing safety-related equipment. The inspectors conducted a walkdown of the internal and external features of the safety-related pump structure for Units 2 and 3 to ensure the stations flood protection measures were controlled in accordance with the design specifications. The inspectors also reviewed operating procedures for mitigating external flooding during severe weather to determine if Exelon planned or established adequate measures to protect against external flooding events.
Documents reviewed for each section of this inspection report are listed in the
.
b. Findings
No findings were identified.
==1R04 Equipment Alignment Partial System Walkdowns (71111.04Q - 5 samples)
a. Inspection Scope
==
The inspectors performed partial walkdowns of the following systems:
- Unit 2 and Unit 3 A standby gas treatment (SBGT) train with the B SBGT train out of service (OOS) on July 7, 2016
- Unit 2 and Unit 3 A and B emergency cooling tower cells with the C cell OOS on July 25, 2016
- Unit 2 reactor core isolation cooling (RCIC) system during high-pressure coolant injection (HPCI) system testing on August 25, 2016
- Offsite power source alignment with the Unit 3 start-up source removed from service on September 13, 2016
- Unit 2 and Unit 3 A main control room emergency ventilation system during a planned E-4 emergency diesel generator (EDG) overhaul on September 22, 2016 The inspectors selected these systems based on their risk-significance relative to the Reactor Safety cornerstones at the time they were inspected. The inspectors reviewed applicable operating procedures, system diagrams, the UFSAR, TSs, work orders (WOs), IRs, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have impacted the systems performance of its intended safety functions. The inspectors also performed field walkdowns of accessible portions of the systems to verify system components and support equipment were aligned correctly and were operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no deficiencies. The inspectors also reviewed whether Exelon staff had properly identified equipment issues and entered them into the CAP for resolution with the appropriate significance characterization.
b. Findings
No findings were identified.
==1R05 Fire Protection
.1 Resident Inspector Quarterly Walkdowns
Main article: IP 71111.05Q